Laserfiche WebLink
<br />DPF status update on Police Station Construction <br />Steve Brown provided an update on the Police Station construction activities for the past month. He <br />reported that the delivery and installation of stair number two was complete. The concrete placement at <br />the second-floor slab was made. The installation of the first-floor HVAC ductwork had begun. The <br />installation of the exterior wall sheathing and air and vapor barrier application were ongoing. The site <br />subcontractor was working on trenching and installing the underground structures on the Northwest side <br />of the site. A lot of the interior blockwork was nearly complete. Brownstone deliveries and their schedule <br />were being closely monitored. The construction milestones included the roofing being nearly complete. <br />The building exterior façade is scheduled to be finished in November. The substantial completion for the <br />project is currently expected to be in April of 2024. <br /> <br />It was reported that there were no changes or updates on the expected delivery of transformers from the <br />utility company. It was reported that the main building transformer was a 1000 KVA 480/277-volt <br />transformer. The vehicle charging transformer was a 750 KVA three-phase 480/128-volt transformer. <br />There was some discussion on this sizing and a need to follow up on verifying sizes. <br /> <br />The change is Substantial Completion from March 12 to April 9, 2024 was due to a delayed switchgear <br />arrival. It was asked if the changed substantial completion date affected funding. It was reported that <br />there was an added cost to accommodate some new work implemented but no overhead or added costs <br />for time. <br />There were updated photos presented. <br /> <br />(post meeting note for clarity: It was later found that the transformers were reported in reverse of the proper make- <br />up. The building transformer is the 750 KVA and the Vehicle charging transformer is 1000 KVA) <br /> <br /> <br />Solar Canopy update <br />Jeff presented the revised conceptual site plan for the solar canopy project as it was last presented to <br />HDC on 8-10-23. There had been previous discussion about breaking down the overall mass of the solar <br />canopies or the large flat plane. The plane of the canopy was broken by raising a middle section above <br />the left and right sides. The 14’6” center clearance was maintained all the way through as the site <br />topography allowed for the center section to be above the two sides without changing the inside vehicle <br />clearance. There has been discussion about eliminating some of the arches, but this was still being <br />evaluated. There was a discussion about eliminating two columns at the end of the canopy and have one <br />long archway, which would also eliminate the two columns and two footings. There was also discussions <br />regarding exploring colors other than white, such as a warm gray or a gray -green at the end of the <br />discussion at the last HDC meeting, it was decided to explore other colors, but a decision on the color <br />still needed to be made. <br /> <br />The various plants that could be placed adjacent to the main canopy were reviewed and it was noted that <br />a neighborhood meeting was scheduled for 8/22 to receive input. It was noted that the parking layout <br />leaves a bit more space between the curb and the bike path for plantings. <br /> <br />Several meetings were held with the engineers, and there were original concerns about soil quality, <br />however the preliminary findings showed that the soils were better than anticipated. There was a <br />conversation about the foundation and the uplift and wind factors that are involved in a canopy structure. <br />It was decided to use spread footings, and the engineers are working on the final calcs and details. The <br />foundation designs should be available by the end of the next week. <br /> <br />