Laserfiche WebLink
Lexington Permanent Building Committee <br />4.0 Bridge & Bowman Renovation Projects <br />4.57 Project Update by Daedalus and DPC <br />3/14/13 <br />Bob white provided an update to the PBC on the work being completed by TLT as compared to the schedule that had been <br />developed. Daedalus reports that TLT is maintaining their schedule and completing tasks per schedule milestones. <br />D2 area is scheduled for completion at end of April school vacation week. <br />Daedalus also updated committee on updated schedule prepared by TLT. DPF did not print copies but emailed the schedule to the <br />PBC just prior to the meeting. Predecessors and successors along with critical path lines have been added to the schedule. An <br />electronic / live version was received and we hope to have the scheduling consultants report on further schedule detail by next <br />meeting. <br />4.59 TLT Payment requisition <br />6/13/13 <br />Motion to approve interim application for payment representing stored materials, as is allowed by contract documents, which was <br />previously removed from application #15, without exceeding value originally requested. <br />Motion Eric 2 Dick Vote 6-0-0 <br />nd <br />7/11/13 <br />Motion to approve application for payment #16, in the amount of $456,856.60 from TLT Construction as approved and <br />recommended by the Architect of Record, Design Partnership of Cambridge. <br />Motion Eric 2 Dick Vote 6-0-0 <br />nd <br />4.62 Update from DPC and Daedalus <br />6/13/13 <br />Bob White from Daedalus updated PBC on TLT scheduling. April and May were very productive months. He feels CPM schedule is <br />good with a critical path that can be monitored. Currently windows are almost completely installed. Progress in Phase 2 is excellent. <br />7/11/13 <br />PBC toured the Bridge school and noticed the significant improvements on site and cleanliness of the areas. Progress in the work <br />was easily observed. TLT representatives were on site for the tour of the phase 2 area. <br />DPC discussed the report from Cavanaugh Tocci Associates (dated July, 2013) it was determined sound levels around the site <br />were minimal and well under what is allowed for in the ordinance. PBC directed DPC to obtain credit proposal and to notify TLT <br />that steel reinforcing for acoustic panels at the roof of both Bridge and Bowman are not needed. <br />4.64 Change Order <br />7/11/13 <br />Motion to approve Change Order #16 in the amount of $38,754.00 which includes COR # 178, 181, 184, 185,187 as approved and <br />recommended by the Architect of Record, Design Partnership of Cambridge. <br />Motion Eric 2 Jon Vote 6-0-0 <br />nd <br />4.66 EBI additional testing <br />6/13/13 <br />Motion to approve Additional Service amendment to Design Partnership of Cambridge to include scope of EBI Consulting for <br />hazardous materials abatement monitoring and sampling in the amount not to exceed $80,000.00. <br />Motion Phil 2 Eric Vote 6-0-0 <br />nd <br /> Page 2 of 4 <br /> <br />