Lexington Permanent Building Committee 4-11-13 <br />4.64 Change Order #14 <br />4/11/13 <br />DPC outlined the items contained within change order #14 with the PBC, which included resolve to earlier claims on abatement <br />costs for elbows and fittings in excess of quantities specified. <br />Motion to approve Change Order #14 to the TLT construction contract in the amount of $41,150.00 <br />Motion Carl 2nd Eric Vote 5-0-0 <br />4.65 Additional work to support Classroom Needs <br />4/11/13 <br />DPF presented selected items from a change order proposal that would move forward on some additional work in the modular <br />classrooms that is supported by the Superintendent to have these spaces better serve the school. The work includes sprinkler, <br />ceilings, and hvac work, and will later require a change for the electrical component. At a later date the installation of some <br />sheetrock walls and doors will be included to complete the spaces but not under the TLT work. <br />Motion to approve Sprinkler work $1,382.60, HVAC work $14,530.82, and Suspended Ceiling work $3,105.00.associated with <br /> <br />change proposal # 161 which shall have corresponding Change Ordermarkups added at the time of processing, in support of <br />minor modifications to the modular classrooms at Bowman. <br />Motion Carl 2nd Eric Vote 5-0-0 <br />DPF presented the needs to remove two dividing walls at two locations at the Bowman School that will convert 4 instructional <br />spaces into two regular classroom spaces to better support educational needs at the school. <br />Motion to approve change proposal # 171 in the amount of $14,999.00 to support required work to convert half size <br />instructional spaces into required full classrooms to support school needs. <br />Motion 2nd Vote <br />4.66 Cancellation of VAT work <br />4/11/13 <br />DPC presented a proposed Credit Change order to the PBC that would eliminate the removal and replacement of corridor flooring <br />at the Bridge school. TLT never completed this scope of work in phase 1 and would be challenged to complete it in this phase along <br />with phase 2 work. By crediting this work TLT will also credit the abatement of caulking between masonry walls and steel columns <br />that exists behind the lockers in these hallways. The lockers must be removed to replace the floor and that is when they were <br />going to abate the caulking. (The caulking is contained, non-friable, and not a danger. Any column caulking that can be removed <br />with locker replacement will still be completed. The credit from TLT for this work will be $63,237.00. The Town will pursue <br />rebidding this work next summer. <br />Motion to accept change proposal #169 as a credit in the amount of $63,237.00 removing VAT/VCT corridor flooring from the <br />Bridge Scope along with related column caulking abatement behind corridor lockers. <br />Motion Carl 2nd Dick Vote 5-0-0 <br /> Page 5 of 9 <br /> <br />