Lexington Permanent Building Committee 4-11-13 <br />4.51 Payment Requisition #10 <br />1/10/13 <br />DPC presented application for payment #10 in the amount of $400,490.70 representing largely punch list completion and the start <br />of the D2 area. <br />Motion to approve TLT Construction Payment request #10 for December for $400,490.70. <br />Motion Dick 2nd Joe Vote: 6-0-0 <br />4.52 DCAM evaluation <br />1/10/13 <br />DPF had drafted 50% DCAM evaluation and sent to PBC for comments. DPC had reviewed and thought eval was an accurate and <br />honest report. DPF stated they would resend to PBC prior to sending to DCAM and verify with DCAM on impact of 505 Evals. <br />2/14/13 <br />DCAM eval draft was sent to PBC for review. Item was added at end about new project team being assigned and Town hopeful for <br />improved success. Also a change to Item c on housekeeping with reference to tools and ladders left about was discussed. DPF <br />reports that DCAM advised that 50% reports do not become permanent they are replaced by final reports. Eval being sent to state. <br />4.53 Change Order #12 <br />2/14/13 <br />DPC reviewed the scope and contents of Change Order No. 12 totaling $71,162.00 <br />Motion to approve Change Order No. #12 ($71,162.00) to the TLT Construction Contract as recommended by the Architect of <br />Record. <br />Motion Eric 2nd Dick Vote: unanimous <br />4.54 Re-class of Funds <br />2/14/13 <br />Motion to approve re-class of funds in the amount of $33,886.75 incurred by facilities operations budget for Custodial & <br />Maintenance overtime costs from TLT phase 1 completion failure and assign these costs to Project Budget Claims line 40019490- <br />52141. <br />Motion Dick 2nd Carl Vote: unanimous <br />4.55 TLT Payment requisition <br />2/14/13 <br />DPC reviewed the payment requisition for TLT construction with the PBC. Requisition #11 totals $590,087.13 <br />Motion to approve Payment requisition #11 to TLT Construction in the amount of $590,087.13 <br />Motion Dick 2nd Eric Vote: unanimous <br />4.56 February Update <br />2/14/13 <br />Bob White from Daedalus Projects provided an update on TLT Schedule. Bob had met with TLT a few times during their <br />development of the schedule and overall reported that the schedule appeared to be an honest practical methodology for <br />completing the project in accordance with the contract. There was general discussion on the schedule and inquiries regarding <br />successors and predecessors used in the schedule detail, the actual prescience or not of float along with the need to show the <br />Critical path line in the schedule documentation. <br />Daedalus will follow up on these items and is awaiting the opportunity to have their schedule consultant test the schedule once a <br />live electronic copy is received. <br />4.57 Project Update by Daedalus and DPC <br />3/14/13 <br />Bob white provided an update to the PBC on the work being completed by TLT as compared to the schedule that had been <br />developed. Daedalus reports that TLT is maintaining their schedule and completing tasks per schedule milestones. <br />D2 area is scheduled for completion at end of April school vacation week. <br />Daedalus also updated committee on updated schedule prepared by TLT. DPF did not print copies but emailed the schedule to the <br />PBC just prior to the meeting. Predecessors and successors along with critical path lines have been added to the schedule. An <br />electronic / live version was received and we hope to have the scheduling consultants report on further schedule detail by next <br />meeting. <br /> Page 3 of 9 <br /> <br />