Lexington Permanent Building Committee 29 March 2012 <br />7.21 Reading Room <br />2/9/12 <br />Reading Room: Sandy explained this area houses level literature which is different from literature in Library. It will also be used as a <br />Professional Development training room for teachers. If needed this room could become a classroom in the future. <br />Gym: Gym is used for voting segregating public from children is a concern as to how that can be done. Sandy discussed the thought <br />of possibly using room or rooms on the lower level for voting, this has been done in the past. <br />7.22 Fuel source for Generator <br />1/5/12 <br />Discussion on allowable fuel source, MB to follow up with fire department, for use of natural gas instead of diesel. <br />1/19/12 <br />Have verbal from fire department that natural gas is okay, waiting for verification in writing. <br />7.23.1 Historical Commission <br />1/5/12 <br />RFW and DDP will work with Historical Commission on any approvals necessary for demolition of existing Estabrook School <br />1/26/12 <br />RFW meeting on 2/9 with Historical Commission. <br />7.24 Permitting <br />1/26/12 <br />PBC expressed concern that permitting needs have not yet been identified and feel strongly that these issues should be <br />understood and included in the project schedule. <br />7.25 Resident Email - Elevator <br />2/9/12 <br />Resident email was discussed. <br />Elevator: Statement was discussed in length PBC agreed that there is no need for further investigation on the elevator as what is <br />designed meets code. <br />7.26 Designer Update <br />3/8/12 <br />Building Design Discussion <br />Building pushed back 7 feet on site and steps at front of building removed. DDP will bring grading plan to future meeting. DDP <br />discussed some design expectations. Group talked about fenestration, overall image should perhaps be "simple ". DDP circulated <br />photographs of other buildings and looked at 3d views of Estabrook to generate discussion. <br />7.27 Estabrook School Driveway Access and Queuing <br />3/8/12 <br />DDP provided an overview presentation of updates and developments in driveway access and queuing of vehicles. Several design <br />options had been developed, each responding to continued discussion of the needs and most appropriate or flexible solution. <br />Motion to recommend updated driveway access and queuing design for Estabrook School Project as reflected in Design Option 5 <br />modified, which contains 3 lanes of traffic from Grove Street with 1450 feet of proposed onsite queuing; with drop off/ pick up to <br />be curbside only. This meets BETA criteria. <br />Motion: Eric Brown 2 Dick Perry Vote: Unanimous <br />7.28 Designer Update for 3/29/12 <br />3/29/12 <br />DDP advises that MSBA formally accepted Schematic Design Submission <br />Final Grading plan due in from subs tomorrow <br />Food Service meeting recently conducted to inform designers of project needs <br />DDP presented a power point on overall updates, copy to file <br />Page 8of9 <br />