PBC Meeting Minutes <br />10 February 2011 Meeting <br />4.5 Proiect Direction <br />12/14/10 <br />With the School Committees support of pursuing increased funding to expand the base scope of the project discussion ensued on the <br />paths of the project and if and how work could continue until the spring town meeting. The DPC suggested a fee increase would be <br />warranted in the area of $280,000 to accommodate the increased scope. Multiple scenarios were discussed concerning what scope <br />items could continue, scheduling paths and what work could be continued contractually. <br />Motion to recommend that project go dormant until additional funding is authorized for expanded scope or direction to continue <br />with original scope received. <br />Motion: Dick Perry 2nd: Carl Oldenburg Vote: 6 -0 <br />4.6 <br />2/10/11 <br />Discussion regarding the scheduling of the continued project, town meetings, construction sequencing and phasing schedule. Also, <br />the fee negotiation with DPC. PBC discussed Pat, Jon and Eric continuing with fee negotiation issues. <br />4/14/11 <br />By Next meeting DPC will have started work again and come to the next meting with updates. <br />4.7 <br />4/14/11 <br />Reported to PBC that Town Meeting supported expanded Fee article for Bridge and Bowman Project. <br />5.0 Fire and Police Study and Design <br />5.6 Written report / hard copy <br />8/10/10 <br />It was stated that the final submission of this study would be in the form of a final written document /manual. Further, that a <br />submission should be made constituting a progress submission for this final document as portions of the manual will likely be <br />needed for a submittal to the selectmen. <br />12/14/10 <br />Final report for the Fire Station was received. PBC recommends that Donham & Sweeney complete the Police Station report in the <br />some fashion as the fire station report and submit copies to PBC to review at next meeting. <br />2/10/11 <br />Feedback from Eric Brown, Bruce and the chiefs was sent to the architects. PBC would like an electronic copy of the <br />report. <br />5.7 Apparatus Bay Floor Slab <br />2/10/11 <br />Further study of the apparatus floor slab is being undertaken with Donham & Sweeney through the facilities Department to fine <br />tune the scope and costs of the floor slab underpinning and or replacement. <br />4/14/11 <br />Town Meeting approved $450,000 for Floor Slab Project to be completed as a DPF project. <br />5.8 Final Study Reports <br />4/14/11 <br />Final Reports acknowledged by PBC and approved to pay final invoice upon receipt. <br />Page 5 of 6 <br />