Findings <br />• The technical analysis found that implementing the project in one phase <br />instead of two should only extend the occupancy date by 4 to 6 weeks, with an <br />opening of the first week in March. <br />• The capital costs to perform the work in two phases increases direct costs <br />approximately $382,000, increasing project costs $484,000. <br />• The existing building has good insulating properties, and adding additional <br />insulation does not improve comfort or enough energy savings to justify the <br />expense. <br />• Replacing the chiller and boiler with more efficient, newer equipment would <br />result in a simple pay back of 27 years <br />LEXINGTON COMMUNITY CENTER — March 5, 2014 Steffian Bradley Architects United States • United Kingdom o Canada • China <br />