Laserfiche WebLink
coolant lines continuing, fire stopping ongoing, tile work continuing in the 2nd-floor bathrooms and locker rooms, <br />locker installations were generally complete with slope tops underway, drywall installation was mostly complete, <br />terrazzo flooring in the main lobby was complete, and priming and painting was ongoing throughout the building. <br />In February, the elevator cab work will be ongoing and completed in March, the interim metal work will be ongoing, <br />finish work in the bathrooms and locker rooms will be ongoing, exterior work on the brickwork will be addressed, <br />the millwork will continue for the rest of the month, and the solar canopy foundation work was being priced. He <br />presented photos of the building envelope progress, the electrical duct bank, and interior progress. <br /> <br />He reported that in December, overhead MEP rough installation and labeling were ongoing, AC piping and <br />ductwork passed the pressure testing, fire stopping was ongoing, wall tile began in the bathrooms, and most <br />windows were installed. The brick and brownstone continued through December. The drywall installation was <br />mostly done, and painting was ongoing. The exterior conduit was signed off from Eversource. The northwest <br />corner was filled, and it will be used for loading in the Spring once the binder is down. The roof trims and gutters <br />were ongoing. The main boiler and chiller were successfully pressure-tested. AT&T put a grounding ring around <br />the newly installed antenna base for the tower. The ceiling grid begins on the second floor. The plumber was <br />working on his items. There was curtain wall testing and one window-wall test, both of which passed. The town of <br />Lexington building inspector and electrical inspector were on the job. Mike Burton reported that there was more <br />dedicated focus from the Griffin Team on underground work, and it was hoped they would be able to have <br />Eversource sign off in the coming week. A date will be provided for the transformer once Eversource signs off. The <br />whole site had 400 amps, which was only enough to provide construction power. It was discussed that the move-in <br />date was not scheduled until June 20 subject to receiving a Certificate of Occupancy. <br /> <br />It was asked if power could be picked up from the adjacent buildings. It was confirmed that Eversource would not <br />give a date on the transformer until the underground work was complete and they came out. There was work being <br />done with CTA on the canopy, and other vendors were reached out to for estimates. Mike Burton reported that <br />galvanization, profile refinement, and tonnage were being examined to reduce the costs of the canopy. A new price <br />with the refinements was being sought. The PV was in a separate $3.4 million project. It was stated that the <br />building was doing okay financially. A series of changes were made. It was asked what the schedule was for the <br />monopole and the solar. It was reported that the tentative date for the monopole was the first week of March and <br />would come after the electrical trenching, and there was not an anticipated date for the solar until the pricing was <br />determined. It was discussed that the target was still fall 2024. <br /> <br />Update on Lexington High School Project <br />Lorraine Finnegan from SMMA provided an update on the Lexington High School Project. She reported that the <br />Existing Conditions Evaluation was completed and distributed to the SBC for review and comment and there were <br />no major comments. The Existing Space Evaluation was 95% complete. A final walkthrough will be done on <br />February 22nd. The final survey was received and is being gone through, and it will be used to help confirm the total <br />gross area. The Proposed Space Evaluation was 90% complete. There were multiple meetings with departments to <br />discuss the need and the use. The goal was to send the draft of the Proposed Space Evaluation on February 16th <br />to show the total existing and proposed existing spaces by category. The Existing Space Summary was presented <br />and discussed to explain how room types were combined. The net square footage included the area of the rooms, <br />and the total building gross floor area included the corridors and walls. The gross factor has to account for all of the <br />bathrooms, stairs, elevators, mechanical spaces, and more. The existing total building gross floor area was <br />351,930 square feet. The grossing factor was 1.39. The Preliminary Design Program (PDP) design workflow was <br />presented. <br /> <br />It was asked if 352,000 was the existing or new building area square footage. It was clarified it was the existing <br />building area. The total building net floor area was 253,441. It was stated that the MSBA will accept a grossing <br />factor up to 1.5. It was clarified that there was a school-only baseline requested. Mark Sandeen asked if there was <br />a ratio for square footage to student. Lorraine Finnegan reported that once there were 2,000 students, the ratio <br />stopped. Enrollment Projection at LHS is 2395. <br /> <br />Matthew Rice from SMMA discussed the focus groups. The groups were happening in isolation regarding <br />discussion, but the content and subject matter overlapped because there were existing synergies between the <br />working groups. There was a collection of four meetings, with the fourth including all focus groups. All four focus