$450*1%*110000=$495,000 per each additional 1% over the 2% reimbursed by the <br />MSBA. Therefore, if the 149A premium is, say, 5%, Lexington would be on the hook for the $303,600 <br />, plus $450/sf*3%*110000= $1,788,600. <br /> <br />The OPM discussed the CM at Risk Selection process, which starts with the selection of a <br />Construction delivery method. If CM at Risk is selected, the OPM would then need to begin the IG <br />Application for submission. <br /> <br />The remainder of the steps will take place in a sequence that gets the CM on board in approximately <br />3 months, or in case, by the beginning of April 2017. Following the selection of the <br />Construction Delivery Method, the PBC would then have to select the CM Selection Committee at the <br />next meeting if they voted to select CM at Risk. <br /> <br />Motion to use the CM at Risk Construction Delivery method on the Hastings elementary <br />School Project and have the OPM submit the IG Application, by C. Favazzo, 2 by P Coleman. <br />nd <br /> <br />VOTE: <br /> Unanimous to approve the motion to use the CM at Risk Construction Delivery <br />Method and submit the IG application. <br /> <br />4.The Design Meeting update <br /> <br />D. DiNisco commented that the 1 design meeting that took place on the 11was primarily focused <br />stth <br />on the site aspects around the building. She reported that the tentative agendas for the next four <br />meetings were handed out in case any of the P/SBC members have interest in participating. <br /> <br />These meeting take place every other Wednesday at 7:30 AM at 201Bedford Street and PBC <br />Members are invited to contribute at these meetings. <br /> <br />5.Sustainable Building Process Update <br /> <br />C. Barrentine attended the Sustainability Stakeholders follow up meeting on January 9, 2017, and <br />summarized the additional detail generated in a spreadsheet, which was distributed and discussed. <br />(See the attached handout.) <br /> <br />Currently, the Stakeholders meetings are being scheduled to have a recommendation to the <br />Lexington Selectmen by March 1. This committee will be asked to vote their recommendations on <br />st <br />items in the next meeting. It was requested that the committee members be given a scoring sheet in <br />advance of the next PBC meeting which DPF agreed would be done. <br />6.Upcoming Meetings & Public Forums: <br />a.Scheduled meetings <br />i.TBD 2017 PBC Meeting <br /> <br />7.Motion to adjourn by D. Perry, 2 P Coleman. VOTE: Unanimous to approve. <br />nd <br />Hastings Project meeting ended at 9:35 PM <br /> <br />DORE AND WHITTIER MANAGEMENT PARTNERS, LLC <br />Trip Elmore <br />Dore & Whittier Management Partners <br /> <br />3 <br /> <br />