<br /> <br />Permanent Building Committee <br />201 Bedford Street, Room 221 <br />Lexington, MA <br />October 9, 2014, 7:00 p.m. <br /> <br /> <br />Members Present: Jon Himmel, Co-Chairman, Eric Brown, Co-Chairman, Dick Perry, Charles Favazzo and <br />Lee Noel Chase <br /> <br />Members Absent: Peter Johnson, Philip Coleman, Carl Oldenburg <br /> <br />Guests: Gary Ainslie and Jean McQuestion, DiNisco Design Partnership and John Park, Hill International <br /> <br />Lexington DPF: Patrick Goddard, Director of Public Facilities; Mark W. Barrett, RA., Project Manager <br /> <br />The Minutes were taken by Jean Curran, Recording Secretary <br />The Meeting convened at 7:05 p.m. <br /> <br />I. Estabrook Elementary School <br />1. Project update-Hill International <br />John Park of Hill International provided a project update to the Estabrook Elementary School. Mr. Park <br />shared they are working to reconcile the Furniture, Fixtures & Equipment (FF&E) and Administrative <br />Costs listed on the Project Budget. Mr. Hill reviewed the remaining punch list items which included (i) <br />$20,250; of items that Shawmut Design Construction (Shawmut) is actively addressing; (ii) $31,650, <br />items recommended to take the money; (iii) $2,900, items to be completed; and (iv)$4,950, total of the <br />remaining consultant items. These remaining punch list items total $59,750. <br /> <br />Gary Ainslie recommended that the Town take about $31,000 of the items monetized on the list. Mr. <br />Ainslie shared there was some disappointment in the ceramic tile installation. Some of the installation <br />standards. Mr. Ainslie also shared that Shawmut stepped up to their subs <br />performance and did the remaining punch list items themselves. Shawmut is still looking for additional <br />money. <br /> <br />The Members had questions comments and questions concerning (i) there is exposed mesh <br />approximately four feet off the ground at the rock wall; (ii) what was the tile installation problem; and <br />(iii) there is a broken light fixture in the lunchroom; (iv) the pine trees on the entrance do not appear to <br />be doing well and can they be replaced next year; (v) there are bare spots in some of the grassy areas, <br />should we put in for a notice on the 90-day warranty; (vi) Phase I is coming up on the 10 month period <br />warranty walkthrough and should that be performed right after Thanksgiving. <br /> <br />Jon Himmel shared that at the Community Center meeting; the gym at the Estabrook Elementary School <br />is an annex used as an experiment for three nights a week but is limited through December to make <br />sure that people do not drift throughout the school. Mr. Himmel wondered if it would be possible to <br />cordon off areas so people would not wander the school. <br /> <br />Pat Goddard stated they have cordoned off areas with signs and there is someone there to monitor. <br /> <br /> <br />PBC Meeting Minutes 100914 Page 1 <br /> <br /> <br />