Lexington Permanent Building Committee 13 December 2012 <br />Termination for convenience: <br />Project would be audited and the town would buy out oh&p from GC. Daedalus estimates approx. $700,000 payment to GC <br />plus cost to re-engineer project and re-bid. There would likely be a premium added by the new GC. Summer 2013 work likely <br />canceled. Overall added costs could easily exceed $1 to 1.5 million. <br />Continuation of Contract with GC: <br />Bob talked with GC and met with the Owners, they want to turn project around. Best advice from Daedalus is work with GC <br />and find a way to make the project better. <br />Brief discussion on expansion of Daedalus services. <br />Daedalus is already on board to review new schedule when it comes out from TLT, and provider feedback on schedule and <br />viability. <br /> <br />4.44 Custom Computer Specialists <br />12/13/12 <br />Facilities requested approval of a purchase order for school IT to purchase network switches required for the phase 2 renovation <br />that are required due to the renovation. <br />Motion: To approve Purchase Order for $12,202.88 to Custom Computer Specialists for Phase 2 Network switches not included in <br />Bridge & Bowman Construction Contract. <br />Motion Eric 2nd Phil Vote Unanimous <br />4.45 TLT Skylight Install in lieu of RTU relocation <br />DPC recommends acceptance of a proposal by TLT to install two new skylights at each school to make up for lost daylight when RTU <br />2 was placed partially blocking a window, at each school. <br />Motion: To accept the proposal by TLT construction to install 2 skylights in the main hallway at each school, instead of relocating <br />RTU-2 . This proposal also recommended by the Architect of Record, subject to design review with the owner. <br />Motion Phil 2nd Dick Vote unanimous <br />4.46 Conduit vs. Wire mold credit <br />DPF reports that DPC advised that conduit was installed in lieu of wiremold at the phase 1 area of each school. The electrical <br />contractor proposed a credit of $12,924.00 to accept the conduit at both phase 1 and 2. The school Principal and the PBC were not <br />in favor of this and would rather have the specified wiremold installed. <br />4.47 Light Fixture Acceptance <br />DPF reports that the architect had recommended acceptance of the light fixture manufacturers modifications to the existing lights <br />that resolved the issues for which the town and architect were concerned and extended the warranty on th fixture as well. <br />Motion: To accept manufacturers light fixture remedy and extended warranty as recommended by the Architect of Record for <br />both schools <br />Motion Eric 2nd Phil Vote: unanimous <br />4.48 Change Order 10 & 11 <br />Motion to approve Change Orders No. 10 ($39,532.70) and #11 ($31,404.39) to the TLT Construction Contract as recommended <br />by the Architect of Record. <br />Motion Eric 2nd Dick Vote: unanimous <br /> <br /> <br />4.49 TLT Payment Request for October and November <br />Motion to approve TLT Construction Payment request for October and November for $696,526.38 and $179,133.61 respectively. <br />Motion Phil 2nd Carl Vote: unanimous <br /> Page 3 of 6 <br /> <br />