APPROPRIATION COMMITTEE REPORT TO THE NOVEMBER 2012 STM
<br />The primary cost drivers are listed in the table below; note that this is not a complete inventory of cost
<br />increases. However, the two main drivers appear to be material costs especially structural steel and greater
<br />regional construction activity reducing the number of subcontractors available.
<br />Source: Denisco Design Partnership
<br />A second estimate was developed to compare with the contractor's estimate. This estimate, provided by A.
<br />M. Fogarty and Associates, Inc., is approximately $800,000 higher than estimates provided by Shawmut,
<br />making potential cost increases closer to $2,800,000. Variances are also expected, though they have not been
<br />quantified, in the costs for demolition of the existing building.
<br />In September, the Town (Public Facilities Dept., Permanent Building Committee, School Committee, etc.)
<br />worked with Denisco Design Partnership and Shawmut Construction to identify areas for potential cost
<br />reduction and identified $652,400 in cost reductions. In October, the School Committee, with input from the
<br />Permanent Building Committee, voted additional value engineering adjustments totaling $858,252.
<br />Though the remaining gap of $1,252,674 could be reduced with the use of construction contingency funds, it
<br />is inadvisable to apply these contingency funds at this point in the project given the inherent potential for
<br />actual vs. estimated cost variances and for market forces to result in additional cost increases. Also,
<br />aggressive bid timing and the complexity of MSBA involvement warrant that a buffer of funds be put in
<br />place to assure that the project stays on track. The project schedule shows 100 % - complete bid documents are
<br />due in late November 2012, with bids due in late December 2012. With the final GMP due to be negotiated
<br />by December 30, 2012, and subcontracts to be awarded the first week of January, the Committee concurs that
<br />it is prudent to provide the necessary funds to keep the project on schedule through this critical phase. Even
<br />though a definite number for the request has not yet been set, the Committee voted 8 -0 to support a request of
<br />up to $2,800,000, an amount at the upper end of the range of preliminary estimates that were current during
<br />our deliberations prior to press time. This vote is not intended to place a ceiling on the proper amount to be
<br />requested; rather it merely is a statement on our knowledge of the amount to be requested. If the request is
<br />for an amount higher than $2,800,000, the Committee will deliberate and vote on the higher request.
<br />The Committee recommends approval of this request (8 -0).
<br />11
<br />Preliminary
<br />60% Constr.
<br />Difference
<br />Explanation
<br />Design
<br />Documents
<br />Concrete Foundations /
<br />$3,881,502
<br />$4,585,651
<br />$704,149
<br />Demand for steel. Reduced
<br />Structural Steel
<br />capacity of suppliers
<br />Increase in materials costs.
<br />Masonry
<br />$1,111,955
<br />$1,242,816
<br />$130,861
<br />Reduced number of pre-
<br />q ualified sub - contractors
<br />Interior Woodwork
<br />$801,754
<br />$1,021,559
<br />$219,805
<br />Union carpenters costs
<br />Membrane Roofing
<br />$375,630
<br />$695,925
<br />$320,295
<br />Design scope underprice
<br />Windows
<br />$307,900
<br />$442,499
<br />$134,599
<br />Increased materials costs
<br />Reduction in bid submission
<br />Electrical
<br />$2,342,050
<br />$2,871,480
<br />$529,430
<br />from sub - contractors. Increase
<br />in materials costs.
<br />SUM OF PRIMARY
<br />$2,039,139
<br />COST INCREASES
<br />Source: Denisco Design Partnership
<br />A second estimate was developed to compare with the contractor's estimate. This estimate, provided by A.
<br />M. Fogarty and Associates, Inc., is approximately $800,000 higher than estimates provided by Shawmut,
<br />making potential cost increases closer to $2,800,000. Variances are also expected, though they have not been
<br />quantified, in the costs for demolition of the existing building.
<br />In September, the Town (Public Facilities Dept., Permanent Building Committee, School Committee, etc.)
<br />worked with Denisco Design Partnership and Shawmut Construction to identify areas for potential cost
<br />reduction and identified $652,400 in cost reductions. In October, the School Committee, with input from the
<br />Permanent Building Committee, voted additional value engineering adjustments totaling $858,252.
<br />Though the remaining gap of $1,252,674 could be reduced with the use of construction contingency funds, it
<br />is inadvisable to apply these contingency funds at this point in the project given the inherent potential for
<br />actual vs. estimated cost variances and for market forces to result in additional cost increases. Also,
<br />aggressive bid timing and the complexity of MSBA involvement warrant that a buffer of funds be put in
<br />place to assure that the project stays on track. The project schedule shows 100 % - complete bid documents are
<br />due in late November 2012, with bids due in late December 2012. With the final GMP due to be negotiated
<br />by December 30, 2012, and subcontracts to be awarded the first week of January, the Committee concurs that
<br />it is prudent to provide the necessary funds to keep the project on schedule through this critical phase. Even
<br />though a definite number for the request has not yet been set, the Committee voted 8 -0 to support a request of
<br />up to $2,800,000, an amount at the upper end of the range of preliminary estimates that were current during
<br />our deliberations prior to press time. This vote is not intended to place a ceiling on the proper amount to be
<br />requested; rather it merely is a statement on our knowledge of the amount to be requested. If the request is
<br />for an amount higher than $2,800,000, the Committee will deliberate and vote on the higher request.
<br />The Committee recommends approval of this request (8 -0).
<br />11
<br />
|