Laserfiche WebLink
Lexington Permanent Building Committee <br />27 September 2012 <br />Issue is that they can't commit to gmp @ 60 % docs because filed subs are not bid until 1005 docs. <br />Dwgs will be 60% at 9/13 mtg 100% at 12/1 <br />60 % estimate at September mtg. There should be 2 numbers from target subs for budgeting cross check to estimate. <br />Motion to approve Option #3 for GMP development with Budget updates at 60% & 90% CD. <br />Motion: Phil 2nd: Dick Vote 5 -0 -0 <br />7.49 Pre -Qual Sub Committee <br />8/9/12 <br />Need at least 1 volunteer for first meeting before 8/22/12 <br />Motion to approve Pat as committee representative to Pre Qual sub Comm. <br />Motion Dick 2 nd Peter Vote 5 -0 -0 <br />8/28/12 <br />Collaborative partners reports the pre -qual process is underway. <br />9/27/12 <br />Pre -Qual process continues, 92 responses were received for filed sub bids. Approx 20 reviews completed to date. <br />7.50 Proprietary Items <br />8/28/12 <br />DiNisco recapped need for approval on proprietary items <br />Discussion on value of proprietary items <br />Motion to approve Proprietary specifications to ensure systems are consistent with operation and maintenance needs in the <br />schools system, for Honeywell / Honeywell ATC controls ( see also supporting letter from Dir. Of Facilities) and for Security Systems <br />and Access control to be purchased through State Contract system and that Key system shall be a Sergeant key system to be under <br />the existing GM sergeant Key system in other Lexington school buildings. <br />Motion Eric 2 nd Carl Vote 5 -0 -0 <br />7.51 Update <br />8/28/12 <br />Site package received 5 bids <br />Shawmut requesting approval of site bid package of 3,177,669.00 <br />Project Budget Tracking summary shows 72,000 over but it is pointed out that there is a 1.5 million owners contingency in place. <br />Collaborative partners supports the site package as proposed by Shawmut as does DPF. <br />There was discussion regarding the conformance contingency ( +/- $61,260) and if that should be part of the site package approval. <br />Motion to approve Site contract work to Shawmut in the amount of $3,177,669 less the 61,260 conformance contingency. <br />Motion: Eric 2nd Chuck Vote 5 -0 -0 <br />7.52 Cost Estimator Change <br />8/28/12 <br />Motion to approve reduction of estimating consultants from 3 down to 2. Estimators will be Fogarty and Construction <br />Manager / Shawmut. <br />Motion: Eric 2 nd Carl Vote: 5 -0 <br />7.53 Construction Testing <br />9/27/12 <br />Collaborative Partners obtain unit pricing from several firms for Construction & Materials testing. The "low bidder" was deemed to <br />be UTS Testing of Stoneham. CP recommended approval of award to UTS Testing. <br />Motion to approve the recommendation of Collaborative Partners for award of the required Construction Testing Firm, UTS <br />Testing in the N. T. E amount of $50,000.00 to be invoiced T &M / Unit pricing per proposal. <br />Motion Jon 2nd Joe Vote 6 -0 -0 <br />Page 5 of 6 <br />