Lexington Permanent Building Committee 09 August 2012 <br />• By October Design Contingency is 0 <br />• By December Construction Contingency drops from 2.5% to 2% <br />• Shawmut back on 7/12 with formalized plan of above. <br />Summary from tonight. <br />• PBC would like to see a tabulation of how we went from $31.1 million to $35 million. <br />• RFW needs to advise Shawmut of PBC positions <br />• Eric thinks School Committee should support PBC in the Aesthetic issues as they don't involve educational issues. Cost <br />savings on exterior veneer. Jon agrees Aesthetic issues should not be school committee issues. <br />• PBC suggest if Shawmut is not at $31.1 at 7/12 meeting we should not continue any further discussion with them and <br />start talks with CTA. <br />• Ask Kevin Batt (Legal Counsel) for advice, letter from awarding authority <br />• Paul to give Shawmut Fogarty estimate and show them cost model we are striving for. <br />• OPM can approach 2 nd CM and see if they want to negotiate if we are not proceeding with Shawmut. <br />7.42 Summary from tonight <br />7/12/12 <br />Shawmut made presentation on GMP budget and proposes revised numbers that meet budget expectation at $31,150,670. <br />PBC discuss and agree 1 set of documents should be issued for pricing. Sept 1. for GMP on 9/15/12. <br />DiNisco disagrees with reduced design contingency. Contingency down to $1,000,000 not $1,200,000. <br />In presentation Shawmut outlined the following timelines: <br />Abatement February to mid April <br />Demo Mid April to mid May <br />Site Mid May to mid August <br />Logistics for spring 2014 and summer of 2014 concerning and will require further development and discussion. <br />Eric feels having <br />• Shawmut check the drawings is a good thing. <br />• Moisture mitigation is a big item and that it warrants a separate meeting. <br />• Schedule concern for spring 2014 and use of new bldg. with old bldg. still up and no new driveway. <br />Architects will provide a LEED Update at 60% CD. <br />7.43 Construction Testing <br />7/12/12 <br />PBC approved obtaining $2,000 PO for UTS for Testing <br />Next PBC meeting 8/9/12. <br />7.44 Update from Collaborative Partners on Estabrook <br />8/9/12 <br />Enabling work near complete, Phase 1 turnover 8/13 and phase 2 on track for turnover on 8/24 <br />Website to be updated over next 2 weeks <br />Budget summary distributed and reported as +30,000. <br />7.45 Value Management Items <br />8/9/12 Items reviewed for determination <br />#15 Defer <br />#20 Barier One - $80,000 included in estimate so $278375 can not be deducted. <br />#25 &@ 26 No <br />#39 Hold <br />#58 DDP to confirm scope <br />Page 10 of 11 <br />