HomeMy WebLinkAbout2011-11-14-STM -CEC-rpt
CAPITAL EXPENDITURES COMMITTEE REPORT TO 2011 STM (NOVEMBER 14,
CEC
APITAL XPENDITURES OMMITTEE
TL
OWN OF EXINGTON
REPORT TO THE
2011 SPECIAL TOWN MEETING (STM)
November 14, 2011
Released November 4, 2011
Submitted by:
Charles Lamb, Chairman
Ted Edson, Vice-Chairman
William Hurley
David G. Kanter
Shirley Stolz
CAPITAL EXPENDITURES COMMITTEE REPORT TO 2011 STM (NOVEMBER 14, 2011)
Warrant Article Analyses and Recommendations
Article 2:
Funding Committee
Funds Requested
Source Recommendation
APPROPRIATE FOR
$21,670,000 General Fund Approve (5Ã0)
BRIDGE AND
(Excluded Debt)
BOWMAN SCHOOLS
RECONSTRUCTION
ÅTo see if the Town will vote to appropriate a sum of money to remodel, reconstruct and m
extraordinary repairs to the Bridge and Bowman schools, includin
original equipment and landscaping, paving and other site improv or directly related to
such remodeling, reconstruction or repair¼.Æ
ÅDESCRIPTION: ¼Funds for the costs of design, engineering and generation of con
were appropriated at the 2010 and 2011 Annual Town Meetings.Æ
[Town of Lexington Warrant to the 2011 STM, November 14, 2011]
This article enables the Town of Lexington to preserve the Bridg Elementary Schools for
educational purposes for the foreseeable future. The work entail
essential mechanical, electrical, and heating, ventilating, & air-conditioning (HVAC) systems, as well as
the addition of classrooms to accommodate present and anticipate
The total-project costÄwhich includes the $1,030,000 previously appropriated for the design &
engineering (D&E) ($750,000 at the 2010 Annual Town Meeting [ATM] under Article 16(c) and the
$280,000 at the 2011 ATM under Article 13(a)Ähas increased from the $19,370,000 reported at the
2011 ATM based on the estimate at what was then the schematic-design stage to $22,639,000 based on
the just-completed 80%-construction-drawings stage. (Note: Still to be determined are the extent of, and
additional costs for, screening of roof-top air-handling units at both schools for acoustic and esthetic
purposes.) An increase of that magnitudeÄ$3,269,000 or $16.9%Äis not that extraordinary when taking
a phased project of this complexity from schematic to just about bid-ready.
The biggest contributor to that increase is an additional $1,121,000 to help ensure the phasing can be
accomplished so as not to cause unexpected impacts on the use of
The next biggest is $850,000 to recognize that the bidding environment is now not expected to be as
beneficial to the Town. The process of the more-detailed design accounts for $773,000 with the HVAC
and electrical work being a major factor. The more-detailed review of whatÈs needed to meet building-
code requirements accounts for $300,000. And finally, refined hazardous-materials (hazmat) abatement,
for $125,000, and noise abatement, for $100,000, account for the balance of the increase.
In the continuing process of evaluating what project scope is ap
capability in those two schools that is comparable with other schools in the district and provides the
needed facility upgrades, in building the current estimate, $375were not
needed in this project: $114,000 of exterior painting, lockers, and FF&E (furniture, fixtures, &
equipment) and $261,000 of generator enclosures, new doors, and excess capacityuninterruptable
power supplies (UPS). Also, $1,120,000 for window replacement that is currently included in the project
estimate may be structured as a bid alternate.
This Committee has considered the arguments for replacing, not r
that approach is neither fiscally wise nor prudent when considereducational impact.
à Fiscally, thereÈs no reason for expecting the building of two new schools wouldnÈt cost at least about
$80 million (twice the rounded-up, currently-estimated cost of the new Joseph Estabrook Elementary
School, without considering inflation). Even if the Massachusetts School Building Authority (MSBA)
were still to be operating under the current procedure with regard to
1
CAPITAL EXPENDITURES COMMITTEE REPORT TO 2011 STM (NOVEMBER 14, 2011)
municipality and, if itÄover timeÄaccepted both schools (which we consider unlikely in less than a
decade based on the MSBAÈs current evaluation of those schoolsÈ conditions being Ågenerally goodÆ),
and if it were still providing about 32% reimbursement, the total cost to the Town would still be at le
on the order of $54 millionÄand with the likely-by-then inflation, much more than that. So, with the
emergency need to rebuild the Joseph Estabrook Elementary School, and replacement of the Maria
Hastings Elementary School being the next higher priority, we donÈt find it reasonable to expect the Town
would have an approved project for even the first of the Bridge and Bowman schools (including swing
space) in less than 8 years and with MSBA funding assistance. Believing that, our reasonable expectation
remains that the Town would face at least an $80 million cost for new Bridge & Bowman schools. This
Committee believes the proposed project at about $22.7 million is the wise approach.
à Then turning to the educational impact, the current state of both of those schools means those
students do not have the benefit of what this Town considers theenvironment.
While this Committee recognizes that new schools would correct that, we are fully prepared to accept the
judgment of our School Superintendent, the Principals of these two schools, and the School Committee
that the proposed project will do so, also. But most significant to this Committee, these proposed
renovations to upgrade the Bridge and Bowman schools will be on line in just 2 years once construction
has begun under the currently projected construction scheduleÄnot some indeterminate period that may
well be a decade and, even then, a period filled with numerous u
Addressing now the creation of the appropriate educational environment for the
two schools is the prudent approach.
This Committee unanimously supports this proposed renovation project and believes it is the appropriate
solution to the educational needs and proper use of our taxpayerÈs funds.
Article 3:
Funding Committee
Funds Requested
Source Recommendation
APPROPRIATE FOR
$180,000 General Fund Approve (5Ã0)
FIRE
(Cash)
COMMUNICATION
SYSTEM
ÅTo see if the Town will vote to appropriate a sum of money to up
System¼.Æ
ÅDESCRIPTION: The Fire Department has been experiencing recurring problems with its radio
communications system in certain parts of the Town that have resrary losses of
communications. A team composed of representatives from the Fire Department, Pol
MIS, Dispatching and the TownÈs radio consultant are recommending the following upgrades to the radio
system to stabilize the system and bring it to acceptable standang the following
improvements: 1) the addition of two radio repeaters; 2) converting the repeat Dispatch Center to
a transmitter; 3) installation of fiber optic communications lin
connected via leased copper phone lines; and 4) replace and upgr
with the overall communications system. Some portion of the improvements may also include the Police
radio system where fire and police share common radio sites.Æ
[Town of Lexington Warrant to the 2011 STM, November 14, 2011]
The current Fire Department radio system has proven to be somewhat unreliable, thereby presenting a
potential public-safety issue. This Article requests an FY2012 appropriation, using what is now
understood to be excess tax-levy capacity, to provide a near-term upgrade to the radio system to enhance
its reliability. (An additional appropriation is expected to be requested at the 2012 Annual Town Meeting
for FY2013 D&E monies for an even-more-robust, redundant, radio system for all of the TownÈs needs,
public safety and otherÄto be followed by a "construction" request in the FY2014 budget.)
2
CAPITAL EXPENDITURES COMMITTEE REPORT TO 2011 STM (NOVEMBER 14, 2011)
The current problem stems from a variety of factors including an
lines (from dispatch to transmitter), incompatibility between syFederal Government
regulations, dead zones due to the existing transmitter topology, trees
falling on lines). The upgrade to be funded under this Article will make use of existing Town-controlled
fiber-optic lines, new network equipment, and new radio repeaters. The follow-on appropriations (in
FY2013 and FY2014) will add redundancy to the systemÄlikely to include, among other solutions,
installing microwave links between the repeaters and control points. It is contemplated that such
microwave links would become the primary links and the fiber links will become the bac
Article 5:
Funding Committee
Funds Requested
Source Recommendation
ESTABLISH AND
Transfer Cubist Approve (5Ã0)
APPROPRIATE TO
$28,500.01 into the Pharmaceuticals,
SPECIFIED
Traffic Mitigation Inc.(ÅCubistÆ)
STABILIZATION
Stabilization Fund
& Transfer
FUNDS
$10,500.00 into the
Transportation
Demand
Management
(TDM)
Stabilization Fund
ÅTo see if the Town will vote to create and/or appropriate sums oization Funds in
accordance with Section 5B of Chapter 40 of the Massachusetts Geeral Laws for the purposes of: ¼
(b) Traffic Mitigation, (c) Transportation Demand Management,¼(f) Center Improvement District;
(g) Debt Service, (h) Transportation Management Overlay District (TMO-1)¼.Æ
ÅDESCRIPTION: ¼The use of these funds may be appropriated for the specific desi
two-thirds vote of Town Meeting.Æ
[Town of Lexington Warrant to the 2011 STM, November 14, 2011]
For the above remaining-cited five Stabilization FundsÄwhich are those having capital implicationsÄat
the time of writing this report, this Committee is only aware of
$28,500.01 balance to be transferred into the Traffic Mitigationanda $10,500.00
balance to be transferred into the TDM Stabilization Fund. Both
Town by Cubist in accordance with the Memorandum of Understanding that accompanied the amendment
at the November 2009 Special Town Meeting of the Planned Commercial District (CD-9) to allow more
intense development in the Cubist portion at 65 Hayden Avenue.
Article 6:
Funding Committee
Funds Requested
Source Recommendation
APPROPRIATE TO
Not Applicable Not Applicable Approve Indefinite
STABILIZATION
Postponement (5Ã0)
FUND
ÅTo see if the Town will vote to appropriate a sum of money to thusly created Stabilization
Fund¼Æ
DESCRIPTION: ¼These funds may later be appropriated, by a two-thirds vote of an Annual or Special
Town Meeting, for any lawful purpose.
[Town of Lexington Warrant to the 2011 STM, November 14, 2011]
3
CAPITAL EXPENDITURES COMMITTEE REPORT TO 2011 STM (NOVEMBER 14, 2011)
At the time of writing this report, this Committee understands tappropriation is planned under this
Article and, thus, it will be moved to be Indefinitely Postponed.
Article 7:
Funding Committee
Funds Requested
Source Recommendation
APPROPRIATE FOR
$65,000 for Clarke $65,000 General Approve (5Ã0)
AUTHORIZED
Middle School Fund (Cash) +
CAPITAL
Paving $35,000
IMPROVEMENTS
Improvements & Community
$35,000 for Cary Preservation
Memorial Library Fund
Document Archive
ÅTo see if the Town will vote to make supplementary appropriation
money appropriated in prior years for the installation or constrand sewerage
systems, drains, streets, buildings, recreational facilities or
have heretofore been authorized; determine¼.Æ
ÅDESCRIPTION: This is an article to request funds for capital impenditures that
exceed the level of appropriation.Æ
[Town of Lexington Warrant to the 2011 STM, November 14, 2011]
At the time of writing this report, this Committee is only aware of two actions to provide such
supplemental funding under this Article to prior appropriations:
Clarke Middle School Paving Improvements (2011 Annual Town Meeting, Article 13(e), $125,000,
General Fund (Debt)): That appropriation was to address construction of two pedestrian-safety-related
projects. One was to relocate a parking lot; the other, construction of a sidewalk from the Clarke
pedestrian bridge over Clematis Brook to Brookside Avenue. When
the low bid for relocating the parking lot was about $105,000 anÄwhich had been
made an add alternateÄwas $69,000. The request for an additional $65,000 is based on recognizing that
the response to a new bid is likely to be on the order of $75,000, p
$10,000, and planning to use the about $20,000 remaining for the original appropriation.
Cary Library Preservation ProjectÄArchives (2010 Annual Town Meeting, Article 8(h), $100,000,
Community Preservation Fund): That appropriation was to design, engineer, and construct a fireproof,
climate-controlled room (using part of an existing storage room) for valuable, irreplaceable, historic
materials owned by the Library. After about $12,000 having been spent on D&E, there is an $88,000
balance available for construction. The bids from companies to act as general contractors came in
between $130,000 and $163,000Äwhich would represent a $42,000-to-$75,000 shortfall in available
funds. The request for only an additional $35,000 is because the Department of Public Facilities now
plans to be the general contractor and contract directly with State-approved trade-contractors for the
performance needed in the various construction disciplines. That request is expected to allow for all the
required construction performance and also include about $4,200 cient, archival-storage, shelving.
4