HomeMy WebLinkAbout2009-11-02-CPC.min
Community Preservation Committee
Monday, November 2, 2009
Room G-15, Town Offices
3:30 pm
Present:
Betsey Weiss, Chair; Joel Adler, Norman Cohen, Marilyn Fenollosa, Jeanne
Krieger, Wendy Manz, Leo McSweeney, Nathalie Rice, Admin. Asst; Sandy Shaw, and
Dick Wolk. Mr. David Kanter of the Capital Expenditures Committee was in attendance
as well as Ms. Karen Simmons, Director of Recreation, Mr. Stew Kennedy of the
Conservation Commission and Ms. Peggy Enders.
Ms. Weiss called the meeting to order at 3:35 pm.
The purpose of the meeting was to listen to a presentation on three projects before the
CPC, and to address an issue raised the previous week regarding use of contingency
funds from a Cultural Resources Study approved in 2007.
1.Stormwater Mitigation on Marrett Road/the Old Res.
– Mr. Dave
Pinsonneault, Superintendent of Public Grounds, introduced this request for
$190,047 and updated the Committee on the status of the work approved in
FY 2009 and FY 2010. The gatehouse project from FY 2009 has been
completed, but the work approved for FY 2010 has not yet been commenced.
Mr. Pinsonneault explained that he and Ms. Simmons are awaiting word on
the State grant which the Town has applied for through the Massachusetts
Department of Environmental Protection (DEP), funded by USEPA under the
Clean Water Act, Section 319. Mr. Pinsonneault explained that when the
decision on the grant comes through, Phase 1 from FY 2010 and Phase II
proposed for FY 2011 would be commenced. Phase II would involve creating
a stormwater detention basin in the southwest corner of the wooded area
surrounding the Old Reservoir. This area of the watershed was unable to be
tied into the four catch basins to the east, and necessitated its own detention
basin.
Since Phase I of the study had not yet been started, the Committee questioned
whether the Reservoir had to be closed this past summer due to
contamination. Ms. Simmons said the Reservoir had to be closed on seven
different occasions but not because they found increased bacteria levels in the
water. She explained that there is a precautionary procedure in place, where
the Reservoir is closed for a day when there is ½ inch of rain or more in 24
hours. (This precaution is taken because runoff from Marrett Road and its
watershed was determined to be the primary source of the bacterial
contaminants entering the Reservoir.) Ms. Simmons added that they conduct
bacterial testing of the water in the Reservoir once per week. There was a
discussion of the timing of Phase I and II, and the delay caused by waiting to
hear about the DEP grant. Mr. Pinsonneault said the project would get
underway as soon as word came through about the grant.
1
2.Center Playfields Drainage – Implementation Phase
– Mr. Pinsonneault
next addressed the Center Playfields Project, (funding request of $875,173)
stating that the engineering firm, The Louis Berger Group, Inc., had
completed its report and had made recommendations about the types of
drainage improvements needed. Mr. Pinsonneault had provided the
Committee with additional support material in the form of a handout. He
said the work proposed for the Center Playfields would be divided into three
Phases, with Phase I taking place in FY 2011. The work would involve
regrading the baseball/softball/multipurpose field and installing additional
subsurface drainage. There was a discussion of the quality of the underlying
drainage infrastructure, especially the culvert at Vine Brook, which appears
to be undersized. There were questions from the CPC about whether the job
as proposed was adequate, since so much of the area is underlain by peat. Mr.
Wolk suggested that to address the issue on a permanent basis the underlying
soils might have to be removed. Mr. Pinsonneault agreed, but said that a
major earth removal and drainage project was just not feasible at this time.
Mr. Pinsonneault said that the fields would be rotated out of service for
approximately a year as each one was restored.
3.Minuteman Bikeway Preservation Project
– Mr. Pinsonneault explained
that this request for $320,000 would be used in conjunction with a $175,000
appropriation passed in 2007 by Town Meeting. He had given the Committee
a handout which explained the project. He said that the Bikeway is in a state
of disrepair in many locations due to root invasion, poor drainage, and
erosion. The CPC funds will be used to install root barriers, conduct drainage
repairs and restore swales. After all the restoration work has been completed,
the appropriation from 2007 will be used to repave the restored sections. CPC
dollars will not be used for repaving.
Mr. Stew Kennedy of the Conservation Commission and Ms. Peggy Enders
spoke in support of the Bikeway Restoration, stating that use of the Bikeway
was increasing, and that a recent use survey noted 3,000 trips in one Saturday
at the Depot. A tally taken during the commuting hours tallied 750 trips.
The CPC received letters of support from three groups in addition to those
submitted with the application. These included the Chamber of Commerce,
the Town Recreation Committee, and the Lexington Center Committee.
4.Cultural Resources Request
– Ms. Fenollosa, who had not been able to
attend the previous CPC meeting when this item was on the agenda,
2
addressed a request from the Historical Commission to use $10,000 in
contingency funds from the Cultural Resources Study approved for FY 2008.
She said the Historical Commission was requesting the use of the funds in
order to apply for a grant from the Massachusetts Historical Commission
(MHC). She explained that under the 2007 appropriation, the consultant for
the Commission had augmented and updated a nine volume set of historic
properties in Lexington. In Vol. 1 of this series, there are descriptions of
neighborhoods, among them mid-century “modern” neighborhoods. Ms.
Fenollosa explained that based upon the work completed in the study, the
Massachusetts Historical Commission suggested that Lexington seek
registration of certain of these mid-century neighborhoods on the National
Register of Historic Places. She said that only those neighborhoods and
homes that wished to be included in the National Register would be listed.
Ms. Fenollosa said her Commission believes the request to use the
contingency funds falls within the scope of the original project as approved
by Town Meeting in 2007. The $10,000 in funds would make it possible to
apply for a matching grant of $15,000 from the MHC. The application for the
th
grant must be received by November 15, hence the concern by the
Commission to have CPC approval as quickly as possible.
There was considerable discussion about registering homes in
neighborhoods, and whether the Commission knew if residents wanted the
work to be done. Ms. Fenollosa said the additional work would only focus on
Peacock Hill, where the neighborhood association has requested inclusion in
the study. Ms. Weiss brought up her concern that the work may be outside
the original scope of the CPC appropriation. After further discussion, Ms.
Manz made a motion to authorize the use of $10,000 of the appropriation to
apply for a State matching grant to do further research on the Peacock Hill
neighborhood, so that it may become a neighborhood on the National
Historic Register. The Committee voted (7-1) to support this motion, with
Ms. Weiss voting against it. The Committee later revisited this motion, and
Ms. Manz amended her motion to include the words, “and to include a
contextual study for the neighborhood and homes currently outside the
Peacock Hill neighborhood if neighbors consent”. This motion was voted on
and approved, (7-1) with Ms. Weiss again voting in the negative.
5.Request for Timely Appraisal Information
– Ms. Weiss brought up the
issue of the CPC’s review of appraisals for land acquisitions. She suggested a
time period of 7-10 business days prior to a Town Meeting vote for CPC
review of appraisals. She said this would eliminate the rush the Committee
experienced last May, when the CPC received the appraisal for the Busa
property the night before Town Meeting. This gave little time for the
Committee to formalize their report and vote on the proposal. Similarly, the
finance committees had to scramble to formally vote on the acquisition, and
3
were only able to do so just before the Town Meeting started. Mr. Cohen said
he felt 7-10 days was a good recommendation, but should not be a binding
time period. Ms. Krieger agreed, and said it could just be made clear to the
applicants that an adequate period for review of the appraisal would be
appreciated. It was suggested that the CPC could write the applicants
proposing land acquisitions, and request a 7-10 day period for appraisal
review. There was some discussion of the right of first refusal that
accompanies an agricultural restriction, and how this played into the Busa
time delay. Ms. Weiss will put this matter on the next agenda, since Mr.
Wolk was not present for this discussion.
The Meeting was adjourned at 4:55 pm.
After the meeting was adjourned, Ms. Fenollosa requested that Ms. Weiss
sign the letter from the Historical Commission so that the Commission could
commence its grant application process. Ms. Weiss signed the letter, granting
CPC approval of the use of $10,000 in contingency funds for the application
for a State matching grant.
Respectfully submitted,
Nathalie Rice
Administrative Assistant
Community Preservation Committee
4