HomeMy WebLinkAbout2008-12-01-CPC-min
Community Preservation Committee
Monday, December 1, 2008
Legion Room
4:00 pm
Present:
Betsey Weiss, Chair; Marilyn Fenollosa, Vice Chair; Joel Adler, Norman
Cohen, Jeanne Krieger, Wendy Manz, Leo McSweeney, Nathalie Rice, Admin. Asst.;
Sandy Shaw and Dick Wolk. David Kanter, CEC liaison was also present.
The meeting was called to order at 4:05 pm.
The purpose of the meeting was to review three projects before the CPC for FY 2010.
These included renovation and redesign work at the Fire Headquarters, renovations to the
Stone Building, and the purchase of three properties by LexHAB.
1.Fire Headquarters Renovation and Redesign –
Chief Middlemiss opened the
discussion. He was joined by Pat Goddard and Mark Barrett of Facilities. The
Chief explained that the planning consultants, the Maguire Group, had come up
with three possible options; Option A, would include keeping the existing
footprint, upgrading the existing building, and reconstructing four bays at the rear
of the building , Option B would necessitate demolishing and completely
rebuilding the building, and Option C, would include only minor upgrades to the
interior of the existing building. These Options were anticipated to cost, 8 million,
10 million and 3 million respectively.
Chief Middlemiss explained that Option A was the most feasible and reasonable
option being considered. He said that it allowed for the station to remain in
service during the renovations and allowed for the addition of greatly needed
space for the fire trucks and for equipment storage. He said the Design and
Engineering cost for this option was $568,254 of which he would be requesting
approximately 29%. This would amount to approximately $168,154. (The
percentage of 29% was determined by the square footage of the area in the
existing building to be renovated compared to the square footage of the entire
construction. The CPC can only fund work associated with renovating the existing
structure, as opposed to new construction.) Similarly, the expected request for
CPC funds for the construction phase of the project would be 29% of the total of
$5,308,810, or approximately $1,539,554.
The Chief showed the Committee the floor plan for Option A, and explained that
under this option, the existing station would be salvaged, the construction of the
bays could continue with fairly little interruption to operations, the façade of the
building would remain intact, and there would be relatively little disturbance to
the site. In response to a question from Ms. Fenollosa, he added that the upgraded
Headquarters would be able to accommodate the East Lexington Station and its
1
operation if the East Lexington Station were closed. It was also noted that the
HDC has jurisdiction over the Fire Headquarters building, and that they would be
involved in the renovation. Mark Barrett said the final report from the Maguire
Group would probably be available to the Committee in the upcoming week.
2.Stone Building Renovation
– Connie Rawson, Director of the Library, and Pat
Goddard from Facilities spoke to this request for $271,660 for FY 2010. Ms.
Rawson explained that the study, which was approved by the CPC in 2006, had
recommended two options for upgrades to the building. One option called for the
renovation of the “ell”, while a second option suggested using the existing
footprint of the building for the necessary upgrades. The upgrades included
handicapped access on the first and second floors, the installation of an elevator,
and the construction of public bathrooms. Ms. Rawson said that at their
th
November 24 meeting, the Trustees of the Library had voted to discontinue
library services at the Stone Building, in favor of renovating the building for use
as a “Heritage Center”. Ms. Rawson explained that initial concepts for the Center
included meeting, performance and exhibition space. She said it would be more
than an Historical Center, and that it would include archive storage. She said the
Trustees were in favor of the reconstruction of the “ell” rather than trying to fit all
the necessary upgrades in the existing footprint of the building.
Ms. Weiss asked about the upgrades that were undertaken as part of the flood
insurance work. Ms. Rawson replied that there was a $25,000 deductible on the
policy, and that the work that was undertaken included replacing the ceilings, rugs
and other materials that were damaged. Mr. Goddard added that the net cost of the
work was $35,000.
There were a number of questions regarding the use of the Stone Building as a
“Heritage Center”. Ms. Shaw questioned whether more archive storage was
needed, in light of the CPC funding of the Town Offices archive project. Ms.
Fenollosa asked how the $271,660 would be expended, if the Library already had
plans showing two concepts for construction. Mr. Goddard replied that the
documents were not plans, and that more researched was needed into the issues of
access and historical preservation of the building. The Library will need detailed
design plans and specs before the work can go out to bid.
There were a number of questions about whether the Library’s idea of a Heritage
Center had received community exposure. Ms. Rawson said the meetings of the
Library Board had been well attended, and that to date the Waldorf School and
one of the area churches had expressed interest in using the Center for future
meetings. Mr. Kanter suggested that an article in the paper would be very helpful
and provide the Trustees with additional feedback before the process was too far
along. He felt broad community use would benefit the project during the
budgeting process. Mr. Wolk asked if the CPC would be better informed before
the Committee had to vote on the project. Ms. Krieger responded that the
Selectmen are represented on the Library Board of Trustees, and that the Board is
2
asking the CPC to preserve the building, which irrespective of its use, needs to be
done. Ms. Weiss asked if there would be a Historic Structures report as part of the
$271,660, to which Ms. Rawson replied that there would be. Mr. Adler
questioned whether the renovation of the Stone Building for a Heritage Center
would preclude the Town qualifying for any grant monies that would otherwise be
available to the library. Ms. Rawson said that the Town does receive such funds,
but only for the Carey Memorial Library.
Mr. Goddard briefly updated the Committee on the status of the fire suppression
work at the Monroe School (funded in 2008). He said the bid had been protested
by the bidders for lack of clarity, and that new documents had to be prepared. The
th.
new documents have been sent out, and bids are expected back in by January 14
3.LexHab Purchase of Three Properties
– Mr. Hays commenced his presentation
by stating that the CPC had funded the purchase of three condominium units at
Parker Manor. He said LexHAB would be seeking 80% of the funding price for
an additional three units this year. He described each of the properties, which
included a tear-down, a standard home, and a condominium unit. The first
property was located at 300 Woburn Street, and is selling for $325,500. Mr. Hays
explained that the home is in poor repair, and will be demolished and replaced
with a standard LexHAB cape cod style home. He said the Rotary and Minuteman
Vocational Tech, would be used to provide manpower for the reconstruction.
The second property was at 104 Emerson Gardens, and was a straightforward
purchase of a condominium unit. Mr. Hays said it was a single bedroom unit, and
was located on the first floor, which was beneficial for the elderly or a
handicapped individual. This unit has been purchased by LexHAB for $250,000.
The third property was on Ross Road off Massachusetts Avenue, and was valued
at $395,000. The house was lost to the bank, but not yet in foreclosure. Mr. Hays
said he felt that LexHAB could wait out the foreclosure and hoped to purchase the
home at a reasonable rate. He added that the house was structurally secure and on
a desirable lot, which made it an attractive purchase.
There was a general discussion of the applicability of the 40B process, and
whether the CPC funded properties would qualify as low and moderate income
properties. Mr. Hays told the Committee that LexHAB would make every effort
to structure the agreements for the three FY 2010 purchases so that the units
qualified as low and moderate housing under the provisions of 40B. Ms. Weiss
affirmed that there will be restrictions on these upcoming properties that would
prevent them from being sold out from under low and moderate income
restrictions. Ms. Weiss added that she wanted to see if the Parker Manor units
could be similarly restricted. In response to a question from Ms. Fenollosa, Mr.
Hays gave the Committee a brief update on LexHAB’s potential purchase of units
at Katahdin Woods for low and moderate housing.
3
4.Future Meeting Dates -
Future meeting dates were set as follows:
-December 15, 2008, 4-6pm Selectmen’s Meeting Room
-January 12, 2009, 4-6pm Selectmen’s Meeting Room
-January 15, 2009, 4-6pm Selectmen’s Meeting Room
5.Administrative Budget
- There was a discussion of the administrative budget
and the need to cover the salary of the Administrative Assistant. Ms. Weiss
explained that she wanted to include all of the Administrative Assistant’s salary
and associated costs, in case there were budget cuts to the position. She said she
needed to get the exact figures for the position from the Finance Department. The
Committee also discussed the inclusion of $50,000 for Conservation planning
monies to enable the Conservation Commission to do the due diligence needed for
potential land acquisitions.
The meeting was adjourned at 5:55 pm.
Respectfully submitted,
Nathalie Rice
Administrative Assistant
Community Preservation Committee
4