LEXINGTON, MASS.
Boston, Aug. 6th 1902.
Alteration No. 3. Adding (see detail below) $369.30
Amount of Contract of Oct. 23, 1901, as modified by )
Alteration No. 1. of Jan. 21, 1902, and )
Alteration No. 2. of July 22, 1902 ) 51,083.10
Amount of Contract as modified hereby, 51,452.40
Brick wall under radiators 17.
Cutting door ending room to fresh air room 15.
Door and Transom for above, including frames
and wired glass in transom and door 20.
Cutting for and setting secong small iron
door in fresh air chamber, east end front 5.
Extra hardware, laboratories 38.
141 1in. ft. pipe trench and iron covers 176.25
Plastering Elevators. Dacey's Bill 40.
10% above and extra work in connection with wells 19.
Extra wiring 47.05
Flashing rods of balustrade 2.
Painting and sanding (second coat). 75.
[total] 454.30
Deduct.
For cesspool and two 50 ft. drains 85.
[total] #369.30
-2-
The foregoing changes are hereby approved as represented
and described, and this day ordered to be attached to the Contract.
All claims for extension of time within which to complete
the building, based upon alterations, changes and additions already
ordered (including those embraced herein) and for any suspension of
the work based upon the agreement of July 22, 1902, and for further
suspension as ordered by the architects under letter of Aug. 4,
1902, are hereby adjusted and agreed to as entitling the contractor
to seven days, and only seven days, beyond September 6th, 1902,
i.e. to September 13th, 1902; it being the intent hereof to provide
that all parts of the work heretofore and now respectively contracted
for shall be completed not later than said thirteenth day of
September, and that the fifty dollars ($50.) per day liquidated
damages stipulated in the main contract shall accrue as to each and
every day, if any, beyond September 13th, 1902, on which any part
of the work shall remain uncompleted. As a part of this provision
as to extension of time, it is mutually agreed that the deliveries
of kiln-dried finish shall be withheld until Friday, August 8th
current, and that the work of putting such finish in place (to be
suspended until then) may be begun on said Friday and prosecuted
without interruption thereafter.
The Contractor hereby acknowledges the receipt of the
specifications and drawings representing and describing the above
mentioned alterations, changes and additions.
H.P. Cummings Company
By A. W. Allen[?] Vice Pres
High School House Building Committee
By Rob't P Clark Chairman
H. W. Lewis Secretary.