HomeMy WebLinkAbout2767 Report, Louis E. Hawes, Engineer to Water Committee, September 11, 1901LOUIS HAWES,
CIVIL AND HYDRAULIC ENGINEER.
TREMONT BUILDING, BOSTON, MASS.
E7
Boston, Mass.
September 11, 1901.
Mr. A. E. Scott,
Chairman Committee on Water Works,
Lexington, Mass.
Dear Sir:-
The results of measurements of the flow of water from
various sources near the Lexington pumping station, as shown by
recent approximate measurements taken with such inexpensive
apparatus as was available, was as follows:-
INTO WELL NO. 1 Clear ground-water.
From Ball Field filter gallery, average of
4 measurements taken from Aug.292 to
Sept.9, at the rate of 12,720 gals.per day
From the Deep well, average of 5 measurements
taken from Sept.2 to 9, at the
rate of 91,526 " " " (gals.per day)
From the Reservoir conduit, ground-water
by gravity, average of 4 measurements
taken from Aug.29 to Sept.9, at the
rate of 143,784 " " " (gals.per day)
The flow into Well No. 1 from the ground or
rock at its bottom is in addition to
the above, but cannot be measured separately
until there is a collecting basin
for the other water to flow into. It
is probable that considerable of the
above flow is lost in well l and some
of it pumped over and over by the deep
well pump " " " [blank] (gals.per day)
INTO WELL NO. 2. Clear ground-water.
From the Seaverns Spring, average of 8
measurements taken from Aug.24 to Sept.
9, at the rate of 19,062 gals.per day
The flow into Well No. 2 from the ground or
rock at its bottom is in addition to
the above, but cannot be measured separately
until the proposed collecting
basin is built to take the other water,
some of which may also be lost before
reaching the pump [blank] " " " (gals.per day)
CIVIL AND HYDRAULIC ENGINEER,
TREMONT BUILDING, BOSTON, MASS. E8
INTO WELL NO. 2. Highly colored water.
From wells 3 and 4, average of 6 measurements
taken from Aug.27 to Sept.9
at the rate of 11,678 gals.per day
THE NEW WELL, Clear ground water.
The test well driven at the site of this
well pumped 50 gallons a minute as
reported by the well driver, and during
a short test later of 3 hours the
quantity was about the same, or as
reported by an assistant, from 40 to
50 gallons per minute.
During the construction of the well
the excavation has been pumped to the
bottom almost continuously for five weeks
during which time about 1,400,000
gallons have been pumped into the brook
and wasted, or at the rate of 40,000 " " " (gals.per day)
THE BROOK, at a point just above the new well,
fairly clear water, being spring water
a little further up.
Weir measurements were made from Aug.
21 to Sept. 7 which showed that during
the 5 weeks when the new well was being
pumped on continuously, the brook ran
to waste about 2,378,000 gallons,
or at the rate of 67,939 " " " (gals.per day)
Weir measurements made in the brook
below the new well and also opposite
the pumping station, showed that the
flow of the brook was not matierally
affected by the construction of the
new well. Nor does the Seaverns
spring appear to have been affected by
the pumping from the new well.
RESERVOIR. Storage.
In addition to the small storage afforded
by the standpipes the Reservoir holds
in reserve for fire purposes or an
emergency, from 5 to 15 million gallons,
depending upon the season, that is
collected m a i n l y from the fall and
spring rains, but is also contributed to
by springs, and which can be drawn upon
directly by the pumps at the Station.
[partial sentence from document underneath:]
as may be adopted at this meeting.
LOUIS HAWKES,
CIVIL AND HYDRAULIC ENGINEER.
TREMONT BUILDING, BOSTON, MASS.
E9 3
THE NEW WELL is 15 feet in diameter and 16.5
feet deep. The walls are of brick resting
on stone work and ledge. Sufficiently
substantial ledge for supporting the
masonry appeared under only a small portion
of it at the expected depth,
necessitating more excavation than was
anticipated and the laying of considerable
stone work in cement mortar.
As the water comes out of the ledge,
the brick work was started on the ledge
several feet lower than planned. Clay
seams and pockets were sealed over and
clean sand placed in the excavation
outside the brick work from bottom to
top to protect the well from infiltration
of discolored water.
Yours respectfully,
Louis E. Hawes
On motion of A. E. Scott it was
Voted:- To accept the report of the committee as a partial report
and that the same committee be instructed to continue their investigations,
to complete the work begun and to carry out such other measures
as may be adopted at this meeting.
200
2767