November 2, 2026
Dear Town Meeting Members:
On behalf of the School Building Committee (SBC), I am pleased to share an update on
the Lexington High School project.
After an eight-year planning journey, Lexington residents said "yes" to a new high school. On
December 8, 2025, approximately 62% of voters approved the debt exclusion for the $659.7
million project and endorsed the Bloom design, clearing the way for a building designed
around the needs of our students. Then, in October 2026, the project reached another major
milestone- the Massachusetts Department of Environmental Protection (DEP) issued its
Superseding Order of Conditions, allowing full construction to begin. The project remains on
track for substantial completion in mid-July 2029, with a September 2029 move-in date being
planned.
PROJECT TIMELINE
The project is now advancing on two fronts at once- the design team is completing detailed
design while construction is underway on site. This overlap is possible because the project
uses the Construction Manager at Risk (CM at Risk) delivery method, which allows
construction to start before every construction document is finalized.
Production piling, the operational phase of installing deep foundational elements, is underway.
Because the DEP permitting process took longer than anticipated, the project team is also
exploring controlled blasting as a way to recover lost time and protect the schedule.
Key upcoming milestones:
• Nov. 2026: Production piling begins
• May 2027: 90% construction documents submitted to the MSBA
• July 2027: 100% construction documents submitted to the MSBA
• Mid-July 2029: Substantial completion
• September 2029: Students and staff move into the new high school
RECENT SCHOOL BUILDING COMMITTEE ACTIONS
September 2026 — The SBC debriefed the DEP site walkthrough and voted to keep the
existing concrete slab and banking for the Field House track. Avoiding the cost of a new slab
frees up funds to strip the old track surface down to the concrete, abate and repair the existing
flooring, and install new flooring throughout.
October 2026 —The SBC reviewed construction progress, DEP updates, and project finances.
Members also reviewed approved building materials that are free of Red List chemicals; these
selections are not expected to affect the overall project budget. The Committee continues to
review project expenditures monthly as part of its ongoing financial oversight.
Agendas, minutes, presentations, and recordings for all SBC meetings are available on the
School Building Committee meeting page.
MSBA MODULES, MILESTONES & MEETINGS
The Massachusetts School Building Authority (MSBA) guides every project it funds through
nine modules, from eligibility through post-occupancy evaluation. Lexington High School is
currently in Modules 6 (Detailed Design) and 7 (Construction). These phases usually happen
one after the other. Because the project uses the Construction Manager at Risk (CM at Risk)
delivery method, detailed design and construction are moving forward at the same time.
Module 6 — Detailed Design
The District and its Project Team are completing detailed design and preparing construction
documents while construction moves forward on site. The project is on track to submit 90%
construction documents to the MSBA in May 2027 and 100% construction documents in July
2027. All design, documentation, and scheduling work follows the scope, budget, and schedule
set in the Project Funding Agreement.
Module 7 — Construction
With the DEP's Superseding Order of Conditions in hand, construction is now underway. The
Project Team is coordinating day-to-day construction with the ongoing design work to keep the
project on schedule and within the scope and budget of the Project Funding Agreement. The
MSBA monitors progress throughout to confirm the project stays on track.
LOOKING AHEAD
Module 6 ® Comleting the Pro ect
With the DEP's Superseding Order of Conditions in hand, construction is now underway. The
Project Team is coordinating day-to-day construction with the ongoing design work to keep the
project on schedule and within the scope and budget of the Project Funding Agreement. The
MSBA monitors progress throughout to confirm the project stays on track.
Module 9 — Post Occu2222y Evaluation
2
After the building has been occupied for at least three years, MSBA staff collect data on how
the building and site are performing. These findings are shared to help school districts,
architects, and builders design better schools in the future.
LHS PROJECT RESOURCES
The SBC meets once a month, typically on the third Monday at noon. Community members
are welcome to provide input at every meeting. Agendas, meeting minutes, video recordings,
reports, and presentations are available on our website. For more information about the
project, please visit the Lexington H h School Building Project website.
Additional resources include:
• LHS Project Website
• LFiS Project FAQs
• LHS Virtual Flyover
• 2026 ATM SBC Report
• 2025 Fall Town eetin Presentation
• 2024 Town Summit Presentation
• Existing Conditions Re ort
• Cost Comparison with Other Schools
• Total Project Bud. et
• Tax�a�er Calculator
• High Cost of Doing Nothing
We appreciate your continued support and partnership as we move into the next exciting
phase of this important project that will serve the needs of our children for many years to
come.
Sincerely,
Kathleen Lenihan
Chair, School Building Committee