HomeMy WebLinkAbout2026-08-18-ConCom-min.pdf
Meeting broadcasted by LexMedia
PUBLIC MEETING MINUTES
Conservation Commission
___________________________________________________________________________
AGENDA Tuesday, August 18th, 2026, 6:30 p.m.
This Conservation Commission meeting was held remotely via Zoom, an online meeting
platform. Public participation via calling in or using a computer was encouraged.
Commissioners Present: Kevin Beuttell (Acting Chair), Philip Hamilton, Jason Hnatko, Ruth
Ladd (joined late), Thomas Olivier and Thomas Whelan; Not Present: Hope Dehmlow Dunne
Staff Present: Karen Mullins, Conservation Director, and Megan Guardado, Department
Assistant;
6:30 PM New Business/Pending Matters
MWRA, Maple St Enforcement Update and Restoration Plan Review and issue Amended
Enforcement Order if ready
Mr. Alejandro Alvarez, Construction Coordinator for MWRA, was present for the discussion and
Mr. Anthony Damiano, GZA, presented a proposed mitigation plan including the planting of tree
species, shrubs, and herbaceous plugs. Three trees were removed along the edge of Maple Street
which will be replaced by six trees. In area two on the mitigation plan presented, wetland seed
mix is proposed for installation, and exposed slopes will be restored with erosion control matting
as well. In area three, material is proposed to be pulled back with an excavator and an upland
conservation seed mix and erosion control barrier are both proposed for installation.
Mr. Beuttell asked if MWRA would agree to clean the construction debris within restoration
areas two and three of the plan. Mr. Alvarez stated that MWRA will clean up the debris.
Mr. Olivier asked about the slope of the road which is sloping towards the wetlands and if storm
drains will capture the runoff from these slopes. Mr. Alvarez stated that the road will be brought
back to the road’s original grade prior to the start of work.
Mr. Whelan asked if GZA will oversee the monitoring of the restoration areas. Mr. Damiano
stated that GZA will be monitoring the beginning stages of planting activities and will check in
with MWRA in the future as well. Mr. Damiano also stated that they will not begin planting until
the fall. Mr. Beuttell stated that the Commission has a standard monitoring period of three years.
On a motion by Mr. Hamilton and seconded by Mr. Whelan, the Commission voted 4-0 by roll
call vote to issue an Amended Enforcement Order including the clean up between restoration
areas two and three, the narrow band along the street, erosion control installation on steep slopes,
three years of restoration monitoring, and restoration plantings to begin in Fall 2026.
Record of Vote as Follows:
Kevin Beuttell – Aye
Philip Hamilton – Aye
Jason Hnatko – Aye
Thomas Olivier – Abstain
Thomas Whelan – Aye
25 Maple St Restoration Plan Review and Issue Enforcement Order
Ms. Nicole Ferrara, LEC Environmental, stated that LEC has met onsite with the Commission
and has since submitted a restoration plan for review. Ms. Ferrara presented the additional
restoration plan which includes restoration of the entire portion of the 100-foot buffer zone that
was disturbed. Any invasive species within the footprint of the planting area will be hand pulled
prior to installing restoration plants.
Mr. Beuttell stated that the disturbance area on the town owned parcel appeared to extend
beyond the flags onsite and the plan should be updated accordingly. Ms. Ferrara stated that she
will confirm this update with the surveyor.
Mr. Whelan asked if the fill close to Maple Street is included in the plans presented. Ms. Ferrara
stated that the fill in question is outside of the 100-foot buffer zone and not included on the plan
that was presented. Mr. Hamilton asked if the restoration plan has been superimposed onto the
plan for development. Ms. Ferrara stated that this has not been done yet and that the Notice of
Intent will be submitted within the next month.
On a motion by Mr. Hnatko and seconded by Mr. Hamilton, the Commission voted 6-0 by roll
call vote to issue Enforcement Order with the extension of the area of disturbance on the town-
owned parcel by ten feet.
Record of Vote as Follows:
Kevin Beuttell – Aye
Philip Hamilton – Aye
Jason Hnatko – Aye
Ruth Ladd– Aye
Thomas Olivier – Aye
Thomas Whelan – Aye
231 Bedford St Enforcement Discussion
Ms. Mullins stated that the Commission recently approved a pavement project onsite through an
RDA and work has been ongoing onsite associated with the front steps and a retaining wall. Ms.
Mullins stated that work has stopped on the site. Mr. Beuttell stated that there is an increase in
impervious surface within the 200-foot Riverfront Area which requires stormwater management
if the work results in an increase of over 100 square feet of impervious surface.
Ms. Ladd asked how much impervious surface was added as a result of the removal of one tree
in the front. Mr. Odilon Rodrigues, P&O Realty LLC, stated that the area that was previously
open is less than 100 square feet. Ms. Paula Caico, P&O Realty, stated that the walkway is pre-
existing and that the material is proposed to be changed. Mr. Beuttell stated that under the bylaw,
removing and replacing the materials of the walkway makes this area be considered as new
rather than pre-existing.
Ms. Ladd stated that the Commission approved the repaving of the lot and noted that no other
exterior work should be done onsite without approval from the Commission. Ms. Ladd stated
that an enforcement order should be issued prior to review of the additional work. Ms. Caico
stated that the retaining wall had collapsed and work had begun without approval due to
concerns for safety with the collapsed wall onsite.
Ms. Mullins noted that the owners previously mentioned installing a ramp as well and that they
would wait to begin pavement work until the ramp is installed. Ms. Caico stated that the asphalt
paving needs to be completed sooner due to safety concerns. Ms. Mullins noted that the pre-
construction meeting should be scheduled to permit the paving to begin.
The Commission agreed the front ramp should be included in the approval for the retaining wall
and walkway. Ms. Ladd stated that a surveyed plan would be needed. Mr. Beuttell stated that
engineering details are needed to prove the proposed site work meets the Commission’s
performance standards.
On a motion by Ms. Ladd and seconded by Mr. Olivier, the Commission voted 6-0 by roll call
vote to issue Enforcement Order.
Record of Vote as Follows:
Kevin Beuttell – Aye
Philip Hamilton – Aye
Jason Hnatko – Aye
Ruth Ladd– Aye
Thomas Olivier – Aye
Thomas Whelan – Aye
7:00 PM New Public Meetings/Hearings
Request for Determination of Applicability: 1 Lillian Road
OpenGov Permit# CDOA-26-8
Applicant/Property Owner: Nora O’Keefe, NSTAR Electric dba Eversource Energy (applicant),
Boston Edison Company, c/o Eversource Tax Department (property owner)
Project: The installation of spare autotransformer pads, exploratory test pits and soil borings in
the existing substation, within the 200-foot Riverfront Area and the 100-foot buffer zone to
Bordering Vegetated Wetlands and 100-foot buffer zone from Bordering Land Subject to
Flooding (Local Code).
Documentation Submitted:
⎯ WPA Form 1 – Request for Determination of Applicability; Locus: 1 Lillian Rd,
Lexington, MA; Prepared for: NSTAR Electric d/b/a Eversource Energy; Property
owner: Boston Edison Company, c/o Eversource Tax Dept.; Prepared by: Greg
Hochmuth, Epsilon Associates, Inc.; Date: 7/06/2026
⎯ Sta. 351 Wetland Delineation Plan; Prepared by: Epsilon Associates Inc.; Prepared for:
Eversource Energy; Scale: 1” = 50’; Date: 04/28/2026
⎯ Memorandum: To: Lexington Conservation Commission; From: Greg Hochmuth,
Epsilon Associates, Inc.; Date: 07/07/2026
⎯ Site Photos; Locus: Station 351, 1 Lillian Road, Lexington, MA; Date: 03/26/2026
⎯ Bordering Vegetated Wetland Determinations Forms; Locus: 1 Lillian Rd, Lexington,
MA; Prepared by: Greg Hochmuth and Jonathan Chidekel; Date: 03/26/2026
Mr. Greg Hochmuth, Epsilon Associates, presented and stated that an updated plan has been
submitted with the accurate floodplain elevation of 163.2 and the substation rests at an elevation
of 165. Mr. Hochmuth stated that Eversource is proposing to do exploratory test pits to install
seven concrete paths on top of existing stone and gravel within the fenced portion of the
substation. The paths would store spare auto transformers for emergency use. Vegetation is
proposed to remain as is with no removal. The applicant is requesting a waiver for the
application to be accepted without a new survey and delineation being done as the last survey
was done in 2021. The work results in 833 square feet of new concrete paths and the applicant
has also requested a waiver from drainage calculations requirements. Mr. Hochmuth stated that
there is no grading proposed within the work area
Mr. Beuttell stated that the Commission has not had time to review the updated materials as they
were submitted hours prior to the meeting and the Commission will need time to review the
waiver request prior to discussing. Ms. Mullins stated that the Commission has yet to waive
stormwater management requirements for any applicant.
Mr. Hnatko asked if the transformers would be dry or store oil and what are their plans to
prevent oil spills. Mr. Hochmuth stated the transformers will have oil and there will be oil
barriers placed beneath the transformers.
Ms. Mullins stated that similar projects in the past have been done with trenching and without
detailed drainage. Mr. Hochmuth agreed to consider adding trenching to address stormwater
drainage.
On a motion by Ms. Ladd and seconded by Mr. Whelan, the Commission voted 6-0 by roll call
vote to continue the hearing to 9/8/2026, at the applicant’s request.
Record of Vote as Follows:
Kevin Beuttell – Aye
Philip Hamilton – Aye
Jason Hnatko – Aye
Ruth Ladd– Aye
Thomas Olivier – Aye
Thomas Whelan – Aye
Notice of Intent: 19 Peacock Farm Road
OpenGov Permit# CNOI-26-7, DEP #201-1391
Applicant/Property Owner: Susannah and Mark Castrovini
Project: Construction of an addition, driveway, stormwater management infrastructure, and other
site appurtenances within the 100-foot buffer zone to Bordering Vegetated Wetlands.
Documentation Submitted:
⎯ WPA Form 3 – Notice of Intent; Locus: 19 Peacock Farm Road, Lexington, MA;
Prepared for: Susannah and Mark Castrovinci; Prepared by: Nathanial Cataldo, Stamski
and McNary, Inc.; Date: 06/22/2026
⎯ Notice of Intent Packet; Locus: 19 Peacock Farm Rd, Lexington, MA; Prepared for:
Susannah and Mark Castrovinci; Prepared by: Stamski and McNary, Inc.; Date:
07/06/2026
⎯ Plan Set: Sheet 1, “Stormwater Management Plan”, Sheet 2, “Construction Details”;
Locus: 19 Peacock Farm Rd, Lexington, MA; Prepared for: Susannah Ford Castrovinci;
Prepared by: Stamski and McNary, Inc.; Signed and Stamped by: George Dimakarakos,
Civil PE No. 41281; Scale: 1” = 10’; Date: 07/06/2026
⎯ Stormwater Management Report; Locus: 19 Peacock Farm Road, Lexington, MA;
Prepared for: Susannah Castrovinci; Prepared by: Stamski and McNary, Inc.; Signed and
Stamped by: George Dimakarakos, Civil PE No. 41281; Date: 07/06/2026; Revised:
08/06/2026
⎯ Bordering Vegetated Wetlands Determination Form; Locus: 19 Peacock Farm Rd,
Lexington, MA; Prepared by: David Crossman, B&C Associates, inc.; Date: 04/09/2026
Mr. Paul Kirchner, Stamski and McNary, presented the site plans and stated that there is current
disturbance within the 100-foot buffer zone including portions of the existing dwelling, existing
patio, shed and lawn area. Mr. Kirchner stated that the addition is proposed to create a garage
space and additional living area. A subsurface chamber area is proposed for capturing and
treating stormwater.
Ms. Ladd noted that there is a swing set currently within the wetlands onsite and asked that the
plan be updated to include all of the trees proposed for removal. Ms. Ladd also noted that the
limit of work line proposed could be reduced.
Ms. Mullin noted that the test pit done closer to the road onsite was one foot higher than the test
pits near the wetlands. Ms. Mullins also asked if the subsurface infiltration system could be
relocated further from the wetlands and if the existing patio would be reconstructed. Ms. Mullins
noted that the Tree Bylaw would be applicable to this project. Mr. Kirchner stated that the patio
is proposed to remain as is.
On a motion by Mr. Hamilton and seconded by Mr. Hnatko, the Commission voted 6-0 by roll
call vote to continue the hearing to 9/8/2026, at the applicant’s request.
Record of Vote as Follows:
Kevin Beuttell – Aye
Philip Hamilton – Aye
Jason Hnatko – Aye
Ruth Ladd– Aye
Thomas Olivier – Aye
Thomas Whelan – Aye
Notice of Intent: 46 Turning Mill Road
OpenGov Permit# CNOI-26-8, DEP #201-1396
Applicant/Property Owner: Vivian Wu (applicant), Sara Curley, Trustee of Forty-Six TMR
Realty Trust (property owner)
Project: Removal of invasive species and installation of native restoration plantings, within a
Bordering Vegetated Wetland and within the 100-foot Buffer Zone to Bordering Vegetated
Wetlands.
Documentation Submitted:
⎯ WPA Form 3 – Notice of Intent; Locus: 46 Turning Mill Rd, Lexington, MA; Prepared
for: Vivian Wu; Property Owner: Sara Curley, Trustee of Forty-Six TMR Realty Trust;
Prepared by: Daniel Bender. Wilderscaping LLC; Date: 07/02/2026
⎯ Resource Area Enhancement Plan; Locus: 46 Turning Mill Rd, Lexington, MA; Prepared
for: Vivian Wu; Prepared by: Goddard Consulting, LLC; Date: 05/01/2026
⎯ Resource Area Enhancement Planting Plan; Locus: 46 Turning Mill Rd, Lexington, MA;
Prepared by: Goddard Consulting; Date: 05/01/2026
⎯ Proposed Site Plan; Locus: 46 Turning Mill Rd, Lexington, MA; Prepared by: LeBlanc
Survey Associates, Inc.; Signed and Stamped by: Vernon J. LeBlanc, PLS no. 33600;
Date: 08/26/2021
⎯ Notice of Intent to Initiate an Ecological Restoration Limited Project; To: Environmental
Monitor; From: Wilderscaping, LLC; Date: 05/29/2026
⎯ Addendum to Notice of Intent; Date: 08/14/2026
Mr. Anthony Gee, Goddard Consulting, Mr. Dan Bender, Wilderscaping, and Ms. Vivian Wu,
owner of 46 Turning Mill Road, were all present for the hearing. Mr. Gee stated that the
homeowner is seeking approval for restoration work onsite and management of invasive species
on site. There are eleven total species of invasives onsite are proposed to be managed through
hand pulling or herbicides. Mr. Gee stated that the applicant is proposing to plant 41 native
shrubs and 19 native trees. Mr. Bender noted that smaller stems may be extracted and cut stem
applications is proposed on larger stems to reduce disturbance to the buffer zone. The
Commission had no questions, and Mr. Beuttell noted the Commission is in favor of ecological
restoration work.
On a motion by Mr. Hamilton and seconded by Mr. Hnatko, the Commission voted 6-0 by roll
call vote to close the hearing.
Record of Vote as Follows:
Kevin Beuttell – Aye
Philip Hamilton – Aye
Jason Hnatko – Aye
Ruth Ladd– Aye
Thomas Olivier – Aye
Thomas Whelan – Aye
Notice of Intent: 55 Ivan Street
OpenGov Permit# CNOI-26-9, DEP #201-1393
Applicant/Property Owner: Fernando Dalfior, 55 Ivan Street LLC
Project: Raze and rebuild of a single-family dwelling and associated site appurtenances within
the 100-foot Buffer Zone to a Bordering Vegetated Wetland and an Isolated Vegetated Wetland
(Local Code).
Documentation Submitted:
⎯ WPA Form 3 – Notice of Intent; Locus: 55 Ivan St, Lexington, MA; Prepared for:
Fernando Dalfior, 55 Ivan Street LLC; Prepared by: Nicole Ferrara, LEC Environmental
Consultants, Inc.; Date: 07/27/2026
⎯ Notice of Intent Application and Wetland Resource Area Analysis; Locus: 55 Ivan St,
Lexington, MA; Prepared for: Fernando Dalfior, 55 Ivan Street LLC; Prepared by: LEC
Environmental Consultants, Inc.; Date: 07/28/2026
⎯ Stormwater Analysis and Calculations; Locus: 55 Ivan St, Lexington, MA; Prepared by:
Patriot Engineering; Signed and Stamped by: Michael J. Novak, Civil PE no. 50696;
Date: 07/17/2026
⎯ Operation and Maintenance Plan; Locus: 55 Ivan St, Lexington, MA; Prepared by: Patriot
Engineering; Date: 07/17/2026
⎯ Wetland & Buffer Zone Restoration Planting Plan; Locus: 55 Ivan St, Lexington, MA;
Prepared by: LEC Environmental Consultants, Inc.; Date: 07/23/2026
⎯ Site Plans: Sheet 1, “Proposed Site Plan”, Sheet 2, “Site Details”; Locus: 55 Ivan St,
Lexington, MA; Prepared for: Dalfior Development; Prepared by: Patriot Engineering;
Signed and Stamped by: Michael J. Novak, Civil PE no. 50696; Date: 07/17/2026
⎯ Drain Area Map; Locus: 55 Ivan St, Lexington, MA; Prepared for: Dalfior Development;
Prepared by: Patriot Engineering; Date: 07/17/2026
⎯ Engineering Comments; Date: 08/13/2026
Ms. Nicole Ferrara, LEC Environmental Consultants, presented the site’s existing conditions and
stated that the proposal includes razing and rebuilding a single-family dwelling. The amount of
impervious surface within the 50-foot buffer zone is proposed to decrease by 7 square feet and
the proposed dwelling will be 14.4 feet further from the wetlands than the existing dwelling. Ms.
Ferrara noted there will be a temporary disturbance of grading within the 25-foot buffer zone.
Ms. Ferrara also stated that the entire 25-foot buffer zone is proposed to be restored with native
vegetation.
Mr. Beuttell stated that the slope of the pervious paver driveway is over 6% and asked the project
engineer to speak to this and the subgrade work. Mr. Mike Novak, Patriot Engineering, stated
that the driveway could be terraced. Mr. Beuttell asked how the engineer verifies that the
infiltration system has been installed correctly. Mr. Novak stated that he observes the installation
of subsurface systems and that he runs a water test after installation. Mr. Beuttell asked for
photographic documentation of the installation.
Mr. Olivier asked if alternatives were explored to build outside of the 50-foot no build zone and
why they were deemed impracticable. Ms. Ferrara stated that much of the buildable portion of
the lot falls within the 50-foot buffer zone. Mr. Novak stated that the required minimum front
yard setback is 30 feet.
Ms. Meng Yang, 60 Ivan Street, asked for clarification on the direction in which stormwater
runoff is directed as the Stormwater Narrative states the existing runoff is towards the northern
property line and the HydroCAD analysis shows the direction as the southern property line. Ms.
Yang also asked the applicant to clarify if work is proposed within the 25-foot buffer zone. Mr.
Novak stated that the discrepancy regarding stormwater runoff direction was a writing error and
that the Isolated Wetland in the northern portion of the lot was captured as the design point. Mr.
Novak also stated that the infiltration system proposed does not have an overflow and that
emergency overflow is proposed at one of the downspouts. Ms. Ferrara stated that there will be
temporary work in the 25-foot buffer zone, which is site grading, that will be restored and that
the 25-foot buffer zone area will be protected in perpetuity and restored with native vegetation.
Mr. Fernando Dalfior, Dalfior Development, stated that the proposed plans were modified after
learning about the wetlands onsite. Mr. Dalfior stated that the width of the proposed house is 47
feet, which is considered narrow for new construction.
Mr. Paul O’Shaughnessy, 61 Ivan Street, expressed concern for silt going into the Isolated
Wetland during construction and concern that water will be redirected towards neighboring
properties including his own. Mr. O’Shaughnessy noted the Isolated Wetland fills with water in
the spring. Ms. Ferrara stated that erosion control measures are proposed including a compost
filled sock that would prevent sediment runoff.
On a motion by Mr. Hamilton and seconded by Ms. Ladd, the Commission voted 6-0 by roll call
vote to close the hearing.
Record of Vote as Follows:
Kevin Beuttell – Aye
Philip Hamilton – Aye
Jason Hnatko – Aye
Ruth Ladd– Aye
Thomas Olivier – Aye
Thomas Whelan – Aye
Notice of Intent: 162 Grove Street
OpenGov Permit# CNOI-26-10, DEP #201-1395
Applicant/Property Owner: Charlie Minasian, Minasian Investments
Project: Raze and rebuild of a single-family dwelling and associated site appurtenances within
the 100-foot Buffer Zone to Bordering Vegetated Wetlands.
Documentation Submitted:
⎯ WPA Form 3 – Notice of Intent; Locus: 162 Grove St, Lexington, MA; Prepared for:
Charlie Minasian, Minasian Investments; Prepared by: Nicole Ferrara, LEC
Environmental Consultants; Date: 07/27/2026
⎯ Notice of Intent Application and Wetland Resource Area Analysis; Locus: 162 Grove St,
Lexington, MA; Prepared for: Charlie Minasian, Minasian Investments; Prepared by:
LEC Environmental Consultants, Inc.; Date: 07/28/2026
⎯ Stormwater Analysis and Calculations; Locus: 162 Grove St, Lexington, MA; Prepared
by: Patriot Engineering; Signed and Stamped by: Michael J. Novak, Civil PE no. 50696;
Date: 07/20/2026
⎯ Operation and Maintenance Plan; Locus: 162 Grove St, Lexington, MA; Prepared by:
Patriot Engineering; Date: 07/20/2026
⎯ Wetland & Buffer Zone Restoration Planting Plan; Locus: 162 Grove St, Lexington, MA;
Prepared by: LEC Environmental Consultants, Inc.; Date: 07/24/2026; Revised:
08/11/2026
⎯ Site Plans: Sheet 1, “Proposed Site Plan”, Sheet 2, “Site Details”; Locus: 162 Grove St,
Lexington, MA; Prepared for: Minasian Investments; Prepared by: Patriot Engineering;
Signed and Stamped by: Michael J. Novak, Civil PE no. 50696; Date: 07/20/2026;
Revised: 8/7/2026
⎯ Drain Area Map; Locus: 162 Grove St, Lexington, MA; Prepared for: Minasian
Investments; Prepared by: Patriot Engineering; Date: 07/20/2026
⎯ Engineering Comments; Date: 08/13/2026
Ms. Nicole Ferrara, LEC Environmental Consultants, presented and stated that there is a forested
wetland on the parcel that continues offsite onto town owned land. The applicant is proposing a
raze and rebuild of a single-family home, a paved driveway with a pervious paver edge, a
pervious patio, and a three-foot high retaining wall with a set of stairs. Ms. Ferrara also noted
that the existing shed within the 25-foot buffer zone will be removed. The proposed dwelling is
located outside of the 50-foot buffer zone, and two trees are proposed for removal. Ms. Ferrara
stated that 1,960 square feet of lawn is proposed to be restored to native plantings and removal of
the Japanese knotweed onsite prior to restoration plantings is also proposed.
Mr. Beuttell asked for clarity on the proposed design of the retaining wall. Mr. Mike Novak,
Patriot Engineering stated that detail was not included in the plan submitted, the existing stone
wall will be left as is and the proposed wall is anticipated to be a landscaping wall.
Ms. Ladd asked what the proposed method of removal for the invasive species is. Ms. Ferrara
stated that they have proposed a few methods including cut and stem treatment, if necessary,
along with herbicide treatment. Mr. Whelan stated that foliar cut stem herbicides are most
effective and will require multiple applications.
Mr. Olivier asked for clarity on what the area labeled “stone area below drive” on the plan is
referring to. Mr. Novak stated that this section will be the stone that is mitigating the driveway.
Mr. Beuttell expressed concerns for the design of the drive and stated that he would like to see
porous surface over the stone area. Mr. Novak stated that the stone area can be made porous as
well.
On a motion by Mr. Olivier and seconded by Mr. Hnatko, the Commission voted 6-0 by roll call
vote to close the hearing.
Record of Vote as Follows:
Kevin Beuttell – Aye
Philip Hamilton – Aye
Jason Hnatko – Aye
Ruth Ladd– Aye
Thomas Olivier – Aye
Thomas Whelan – Aye
Notice of Intent: 21 Valleyfield Street
OpenGov Permit# CNOI-26-11, DEP #201-1392
Applicant/Property Owner: Nazar Vincent, Avatar Design & Construction (applicant), Joshua
and Rachel Riojas (property owners)
Project: Raze and rebuild of a single-family dwelling and associated site appurtenances within
the 100-foot Buffer Zone to Bordering Vegetated Wetlands.
Documentation Submitted:
⎯ WPA Form 3 – Notice of Intent; Locus: 21 Valleyfield St, Lexington, MA; Prepared for:
Nazar Vincent, Avatar Design & Construction; Property Owner: Joshua and Rachel
Riojas; Prepared by: Nicole Ferrara, LEC Environmental Consultants; Date: 07/27/2026
⎯ Notice of Intent Application and Wetland Resource Area Analysis; Locus: 21 Valleyfield
St, Lexington, MA; Prepared for: Nazar Vincent, Avatar Design & Construction;
Owners: Joshua and Rachel Riojas; Prepared by: LEC Environmental Consultants, Inc.;
Date: 07/28/2026
⎯ Stormwater Report; Locus: 21 Valleyfield St, Lexington, MA; Prepared for: Avatar
Construction; Prepared by: FODERA Engineering; Signed and Stamped by: Patrick F.
O’Reilly IV, Civil PE no. 60003; Date: 07/27/2026
⎯ Operation and Maintenance Plan; Locus: 21 Valleyfield St, Lexington, MA; Prepared by:
Fodera Engineering; Date: 07/23/2026
⎯ Buffer Zone Restoration & Enhancement Planting Plan; Locus: 21 Valleyfield St,
Lexington, MA; Prepared by: LEC Environmental Consultants, Inc.; Date: 07/27/2026;
Revised: 08/11/2026
⎯ Site Plan Set: Sheet C-1, “Existing Conditions Plan”, Sheet C-2, “Proposed Site Plan”,
Sheet C-3, “Details”; Locus: 21 Valleyfield St, Lexington, MA; Prepared for: Avatar
Design & Construction; Prepared by: Fodera Engineering; Signed and Stamped by:
David Philip Terenzoni, Civil PE no. 38720; Date: 07/27/2026; Revised: 08/10/2026
Ms. Nicole Ferrara, LEC Environmental Consultants, presented the existing and proposed site
conditions and stated that the existing lawn edge extends into the wetlands, and the existing
dwelling is within the 50-foot buffer zone. Ms. Ferrara stated that the proposal includes
demolition of the existing dwelling, construction of a new dwelling, and removal of all
impervious surface within the 25-foot buffer zone. The applicant proposes to increase the area of
natural vegetation within the wetland buffer zone.
Mr. Beuttell asked for clarity on the total square footage of the existing natural vegetation within
the wetland buffer. Ms. Ferrara stated that she will verify how this area was calculated and
confirm the total square footage of existing natural vegetation.
Ms. Ferrara stated that the Engineering Department has provided comments regarding the
location of the three geothermal wells proposed and the applicant will be following up with a
revised plan. A restoration planting plan has been provided which includes restoration of all
existing lawn within the wetland and the 25-foot buffer zone with native shrubs and native seed
mix.
Mr. Beuttell expressed concern for the total amount of impervious surface due to driveway
paving proposed within the 50-foot buffer zone.
Mr. Olivier stated that based on the size and shape of the lot, it would be impracticable to move
the dwelling outside of the 50-foot buffer zone. Mr. Olivier also asked for clarity on the roof
overhang and gutter width proposed. Mr. Patrick O’Reilly, Fodera Engineering, stated that the
question of the gutter width would need to be addressed by the architect. Mr. Nazar Vincent,
Avatar Construction, stated that the town requirement is five inches for the gutter width.
Ms. Mullins stated the engineer should research the guidance for deep well requirements as she
believes the set back is ten feet per state regulations rather than the proposed five feet.
On a motion by Mr. Hamilton and seconded by Mr. Whelan, the Commission voted 5-0 by roll
call vote to continue the hearing to 9/8/2026, at the applicant’s request.
Record of Vote as Follows:
Kevin Beuttell – Aye
Philip Hamilton – Aye
Jason Hnatko – Aye
Thomas Olivier – Aye
Thomas Whelan – Aye
*Commissioner Ruth Ladd left the meeting during this hearing and did not vote.
Notice of Intent: 14 Barberry Road
OpenGov Permit# CNOI-26-12, DEP #201-1394
Applicant/Property Owner: Roseanna Loring and Joseph Elias
Project: Construction of a carport, deck, and patios, and associated site appurtenances within the
100-foot Buffer Zone to Bordering Vegetated Wetlands.
Documentation Submitted:
⎯ WPA Form 3 – Notice of Intent; Locus: 14 Barberry Road, Lexington, MA; Prepared for:
Roseanna Loring and Joseph Elias; Prepared by: Nicole Ferrara, LEC Environmental
Consultants; Date: 07/28/2026
⎯ Notice of Intent Application and Wetland Resource Area Analysis; Locus: 14 Barberry
Road, Lexington, MA; Prepared for: Roseanna Loring and Joseph Elias; Prepared by:
LEC Environmental Consultants, Inc.; Date: 07/28/2026
⎯ Engineering Drainage Calculations; Locus: 14 Barberry Road, Lexington, MA; Prepared
by: Gala Simon Associates, Inc.; Signed and Stamped by: Alberto M. Gala, Civil PE No.
36434; Date: 07/15/2026
⎯ Operation and Management of Drainage Systems; Locus: 14 Barberry Road, Lexington,
MA; Site Operator: Roseanna Loring; Prepared by: Gala Simon Associates, Inc.; Date:
07/15/2026
⎯ Buffer Zone Restoration & Enhancement Planting Plan; Locus: 14 Barberry Road,
Lexington, MA; Prepared by: LEC Environmental Consultants, Inc.; Date: 07/24/2026
⎯ Drainage Plan; Locus: 14 Barberry Road, Lexington, MA; Prepared by: Gala Simon
Associates Inc.; Signed and Stamped by: Alberto M. Gala, Civil PE No. 36434; Date:
07/28/2026
⎯ Engineering Comments; Date: 08/14/2026
Ms. Nicole Ferrara, LEC Environmental Consultants, presented the existing conditions and
stated that an additional flag has been added to the plan and the buffer zones have been revised
accordingly. The proposal includes a carport to be constructed on concrete slab and the
expansion of the driveway to extend to the carport. Ms. Ferrara also stated that a second-story
deck is proposed off the rear of the garage and that existing deck will be removed and replaced
with a spiral staircase. Nine pine trees are proposed for removal and tree replacement is proposed
within the mitigation planting plan. There are two infiltration systems proposed to provide
stormwater management
Mr. Beuttell asked for clarity on the reasoning for driveway pavement past the proposed carport.
Mr. Lee Dykxhoorn, project architect, stated that the pavement past the carport is to serve as a
turnaround point for cars. Mr. Beuttell stated that the turnaround extends roughly 30 feet past the
carport, which exceeds the area needed for a turnaround. Mr. Dykxhoorn stated that the extended
pavement is pre-existing and they could review this to make changes to the plan. Mr. Beuttell
also stated that deep well injection regulations apply to this property as well and there should be
a 10-foot offset from structures and that tree protection should be revised on the plan to comply
with the Tree Bylaw.
Mr. Olivier stated the proposed deck being extended into the no-build zone does not meet the
Commission’s regulations. Ms. Ferrara stated the applicant is requesting a waiver for the deck to
be built within the no-build buffer zone including extensive restoration work and that the
alternatives are limited for the purposes of a deck.
On a motion by Mr. Hnatko and seconded by Mr. Whelan, the Commission voted 5-0 by roll call
vote to continue the hearing to 9/8/2026, at the applicant’s request.
Record of Vote as Follows:
Kevin Beuttell – Aye
Philip Hamilton – Aye
Jason Hnatko – Aye
Thomas Olivier – Aye
Thomas Whelan – Aye
Continued Public Meetings/Hearings
Notice of Intent: 114 Wood Street
OpenGov Permit# CNOI-26-5, DEP #201-1389
Applicant/Property Owner: Scott Seaver, Seaver Construction / Angelo and Marianne Tortola
Project: Demolition of a single-family dwelling and associated site appurtenances, the
construction of a multi-family residential development and associated access road, parking,
utilities, grading, and other site appurtenances within the 100-foot buffer zone to Bordering
Vegetated Wetlands, an Isolated Vegetated Wetland, Isolated Land Subject to Flooding, and
Vernal Pool Habitat.
Previous Hearing Dates: 4/14/2026, 4/28/2026 (no testimony), 5/19/2026 (no testimony),
6/9/2026, 7/14/2026, 7/28/2026 (no testimony)
Supplemental Documentation Submitted:
⎯ Shallow UIC Class V Injection Well to Water Supply Line Setback Requirements Email;
To: Karen Mullins; From: Michael Carter; Date: 07/15/2026
⎯ Standard Design Guidelines for Shallow UIC Class V Injection Wells; Prepared by: The
Executive Office of Energy and Environmental Affairs; Date: 04/06/2016
⎯ Memorandum: To: Water Division Directors, Regions 1-10; From: Linda Boornazian,
Director, Water Permits Division (MC 4203M), and Steve Heare, Director, Drinking
Water Protection Division (MC 4606M); Subject: Clarification on which stormwater
infiltration practices/technologies have the potential to be regulated as “Class V” wells by
the Underground Injection Control Program; Date: 06/13/2008
⎯ Offsite Stormwater Analysis; Locus: 114 Wood St, Lexington, MA; Prepared by:
Frederick W. Russell, Jr, Civil PE No. 36713; Date: 07/21/2026
⎯ 114 Wood Street Special Residential Development Plans: Sheet 1, “Locus Context Plan:,
Sheet 2, “Existing Conditions”, Sheet 3, “Site Analysis Map”, Sheet 4, “Erosion Control
Plan”, Sheet 5, “Property Rights Plan”, Sheet 6, “Proposed Site Layout”, Sheet 7, “Site
Construction Plan”, Sheet 8, “Site Construction Plan I”, Sheet 9, “Site Construction Plan
II”, Sheet 10, “Utilities Plan & Profile”, Sheet 11, “Construction Details I”, and Sheet 12,
“Construction Details II”; Locus: 114 Wood St, Lexington, MA; Prepared for: Seaver
Construction; Prepared by: Keenan Survey; Signed and Stamped by: Frederick W.
Russell, Jr, Civil PE No. 36713; Date: 03/12/2026; Revised: 06/30/2026, 07/21/2026, and
08/08/2026
⎯ Landscaping Plan Set: Sheet 9, “Landscape Plan I”, Sheet 10, “Landscape Plan II”, Sheet
11, “Landscape Details”; Prepared for: Seaver Properties LLC; Prepared by: Laurie Tarr
Ellsworth, Landscape Architecture, LLC; Date: 08/26/2025; Revised: 07/12/2026 and
07/21/2026
⎯ Buffer Zone Mitigation & Restoration Planting Plan; Locus: 114 Wood St, Lexington,
MA; Prepared by: LEC Environmental Consultants, Inc.; Date: 07/22/2026; Revised:
08/07/2026
⎯ Steep Slopes Package Memorandum: To: Karen Mullins; From: Fred Russell; Subject:
114 Wood Street -steep slopes; Date: 06/30/2026
⎯ 114 Wood Street, Special Residential Development – Work in Steep Slopes: Final
Memorandum: To: Karen Mullins; From; Frederick W. Russell, PE; Date: 08/06/2026
⎯ 2nd Peer Review Memorandum: To: Abby McCabe, Planning Director; From: Michael J.
Carter, GCG Associates, Inc.; Subject: 114 Wood Street, Special Residential
Development, Lexington, Massachusetts, Planning Board Site Plan & Wetlands
Protection 2nd. Peer Review.; Date: 08/07/2026
Mr. Rich Kirby, LEC Environmental Consultants, presented and stated that information
regarding steep slope onsite has been prepared by the project engineer and provided to the
Commission. The planting plan has been revised to eliminate plantings within the vernal pool
buffer zone that is not currently compost piled. Mr. Kirby also noted that an additional page has
been added to the planting plan regarding management of invasive species onsite by hand and
the cut and stem method. The applicant expressed intent to continue the hearing until after the
Planning Board closes their hearing for this project to ensure no additional plan changes are
requested.
Mr. Beuttell asked if there is an alternative to pesticide use within the vernal pool habitat buffer
zone and what the potential risks are with the proposed targeted herbicide use. Mr. Kirby stated
that Roundup would be the most beneficial to the invasives removal efforts onsite, but the
applicant can remove this from the proposal if requested by the Commission. Mr. Kirby stated
that it is his understanding that the herbicide would be applied by paintbrush during dry weather
conditions and any material that could run off would bind chemically with the soil and become
inert.
Mr. Beuttell stated that the project engineer’s steep slopes letter only addressed one of the two
steep slopes onsite and did not address the steep slope in the entrance area. Mr. Fred Russell
stated that there was a man-made mound at the entrance that the applicant plans to flatten.
A certified herbicide applicator will do the targeted herbicide treatment. Mr. Whelan stated that
Conservation Department of the Native Plant Trust recommends the cut stem method with
herbicide treatment and does not recommend mechanical methods for long-term success. Mr.
Olivier asked if herbicide use is being proposed near the vernal pool. Mr. Kirby presented the
restoration plan and the area in which invasives removal is proposed within the vernal pool
habitat.
Ms. Margie Brown, Minuteman National Historical Park, expressed concern that a letter dated
July 27th is not visible in the record. Ms. Mullins stated that public comments cannot be deleted
from the record and this comment letter is within the Commission’s records for this application.
Ms. Mullins noted that the letter appears not to be in the OpenGov system at the time of this
meeting but is included in the records of this application. Ms. Brown expressed concern for the
inclusion of a trail on the proposed plans. Ms. Mullins stated that the trail connection has been on
the West Lexington Master Plan that started in 2009 with the purpose of connecting all of the
town resource north to south. Ms. Mullins also noted that the path can stay off of the National
Park Service property and the details of the layout of the trail can be completed as a requirement
of the Order of Conditions. The applicant will keep the National Park Service informed to final
plans for the trail.
Ms. Janet Lane, 21 Hayward Avenue, expressed concern that the path along the stonewall onsite
is unsafe and stated that the “no trespassing” signs were put up during the Covid-19 Pandemic by
the landowner. Ms. Lane also noted that the distance from the stone wall to the water varies
depending on weather conditions.
Mr. Ohmart stated that revised version of the proposed path was submitted to go underneath the
easement. The details of the path will be determined in the future with the consideration of the
National Park Services as well.
On a motion by Mr. Hamilton and seconded by Mr. Hnatko, the Commission voted 5-0 by roll
call vote to continue the hearing to 10/20/2026, at the applicant’s request.
Record of Vote as Follows:
Kevin Beuttell – Aye
Philip Hamilton – Aye
Jason Hnatko – Aye
Thomas Olivier – Aye
Thomas Whelan – Aye
New Business/Pending Matters, Continued
Comments on City of Waltham ZBA Petition for Variance: 50 Wimbledon Circle
Ms. Mullins stated that the city of Waltham Zoning Board of Appeals (ZBA) received a variance
request for a property directly abutting land owned by Lexington Conservation. There has been
an encroachment onto the conservation owned land in the form of maintenance as lawn. Ms.
Mullins recommended the Commission submit comments to the Waltham ZBA regarding the
encroachment and that they include a condition of approval to cease encroachment and
maintenance of conservation property. Mr. Olivier asked if the Commission would ask for
fencing or any form of demarcation. Ms. Mullins suggested requesting Feno bounds be installed
on the property line.
Approve Minutes: 6/23/2026 and 7/14/2026
On a motion by Mr. Hamilton and seconded by Mr. Whelan, the Commission voted 5-0 by roll
call vote to approve the 6/23/2026 minutes.
Record of Vote as Follows:
Kevin Beuttell – Aye
Philip Hamilton – Aye
Jason Hnatko – Aye
Thomas Olivier – Aye
Thomas Whelan – Aye
On a motion by Mr. Hnatko and seconded by Mr. Hamilton, the Commission voted 5-0 by roll
call vote to approve the 7/14/2026 minutes.
Record of Vote as Follows:
Kevin Beuttell – Aye
Philip Hamilton – Aye
Jason Hnatko – Aye
Thomas Olivier – Aye
Thomas Whelan – Aye
Vote to Issue Order of Conditions: 18 Saddle Club Rd, DEP #201-1390, OpenGov CNOI-26-6
Mr. Beuttell stated that this project involves restoration plantings and the order will include
standard conditions of a required three-year monitoring period for survivability. Ms. Mullins
noted the order should include standard conditions regarding stormwater as well.
On a motion by Mr. Hamilton and seconded by Mr. Whelan, the Commission voted 4-0 by roll
call vote to issue the Order of Conditions.
Record of Vote as Follows:
Kevin Beuttell – Aye
Philip Hamilton – Aye
Jason Hnatko – Aye
Thomas Olivier – Abstain
Thomas Whelan – Aye
Schedule site visits: 9/8/2026 Meeting
The site visits will be scheduled for Tuesday September 1st, 2026, starting at 5:30pm.
Reports: Bike Advisory, Community Gardens, Community Preservation Committee,
Enforcement Updates, Greenway Corridor Committee, Land Acquisition, Land Management,
Land Steward Directors, Tree Committee
None.
On a motion by Mr. Hnatko and seconded by Mr. Olivier, the Commission voted 5-0 by roll call
vote to adjourn the meeting.
Record of Vote as Follows:
Kevin Beuttell – Aye
Philip Hamilton – Aye
Jason Hnatko – Aye
Thomas Olivier – Aye
Thomas Whelan – Aye
10:20pm
Respectfully Submitted,
Megan Guardado
LUHD Department Assistant