HomeMy WebLinkAbout2026-04-09-PBC-minTOWN OF LEXINGTON
Permanent Building Committee
Permanent Members
Jon Himmel, Co -Chairman, Charles Favazzo, Co -Chairman,
Peter Johnson, Celis Brisbin, Elizabeth Giersbach, Frederick Merrill, Ian Adamson
Police Station Members: Semoon Oh, Wendy Krum
Associate Members: Curt Barrentine, Henrietta Mei
PBC Minutes for the meeting held on: 4-09-2026
Meeting was held hybrid via Zoom
PBC Members Present:
Jon Himmel, Chuck Favazzo, Celis Brisbin, Peter Johnson, Fred Merrill, Lisa Giersbach, Ian Adamson, Wendy
Krum, Henrietta Mei
Others Present:
SMMA: Brian Black, Andy Elliott, Anoush Krafian
D&W: Mike Burton, Jacob Greco, Christina DellAngelo, Kyle Leone
Turner: Kate Cassen, Jamie Meiser
Other:, Mark Sandeen, Debra Hankins, Kathleen Lenihan, Robert Pressman, Manaj H. Cindy Arens, Tom Shiple
The PBC meeting was called to order at 6:04 p.m.
Approve Meeting Minutes
Motion made by Chuck Fazzo and seconded by Fred Merrill to approve the March 26, 2026, meeting minutes, all
approved.
High School Project Update
Discuss Lexington Youth Comm Feature Site Items:
Andy Elliott (SMMA) provided updates on the Lexington Youth Commission Stewardship area. He presented a
picture of the existing garden and reported that it was 4,000 square feet, with 460 square feet of planting. There
were three options in total reviewed for relocation. Option A was the previous option presented and was adjacent to
the skate park. It was slightly limited in size and would prevent a lot of future expansion. Option B was near the
playground and required minor site modifications. Option C was near the path of travel and a little further from the
skate park. Option C was the recommendation due to the existing surrounding trees and the room for growth.
Debra Hankins agreed with the recommendation of Option C.
There was a general consensus in support of Option C.
Lisa Giersbach agreed that Option C was the best and asked whether there were plantings around the bird bath and
tree. Andy Elliott reported that there were some plantings, and sometimes roots necessitated mounding plants. Lisa
Giersbach asked if the hedge would need ongoing maintenance. Andy Elliott reported that it was not the intention to
require extensive maintenance.
The warranty and maintenance of the garden area was discussed. It was explained that the warranty was generally
one year, and that watering and maintenance were covered during that time. Mike Cronin noted that DPW would
handle maintenance of the island area. It was decided that it would be best to have the basic one-year maintenance
and warranty plan and then hand it over to DPW.
Discuss 50% Design Development Estimate & Recommendation:
The Design Development (DD) timeline was reviewed. The variance between to estimates started at 1.05% and after
the reconciliation stood at 0.5%. The target budget remained at S659.7 million. Based on the baseline scope, it was
trending S3.7 million under budget. Some additional considerations came up throughout DD, including the lowered
mechanical room floor, the building height issue, off-site improvements to traffic signals, and the optional banked
track at the field house. To recover some savings, the light fixture allowance could be reduced; the second air
handler was not needed for the field house; and the additional work would be done as the Target Value Design (TVD)
process continued. The S3.7 million would return to contingency.
The line items were reviewed, and the overage on interiors was asked about. Kate Cassen explained that the interior
door costs and allowances held at SD for specialties were now quantified. Some of the acoustical and sound items,
as well as the door items, would be reviewed further during TVD.
Chuck Favazzo asked about the overage on stairs. Kate Cassen reported that the stairs had not yet been broken
out.
Chuck Favazzo asked about other overages. Plumbing at SD had no distribution piping drawn, which resulted in an
increase. At SD, the fixture types had not yet been chosen, which also led to increases. Roughly half of the HVAC
delta was due to an increase in pounds of ductwork. There were also changes in pump pricing. The lighting
allowance would be worked through during TVD. There was a larger switchboard change, and there were some
increases due to carrying the costs on a per -square -foot basis. The difference in hazardous abatement was due to
the consultant's increased abatement allowance. It was asked if it would increase the unit cost. Katen Cassen stated
that she would research to confirm whether it was just a change in unit cost.
There were additional on-site costs due to a revision of the porous pavement, the terrace roof fit -out, and drainage
and protection boards.
In the electrical section, there was an increase in market costs for transformers and switchboards. There were also
previous assumptions about pile locations and caps, and there were additional piles, increases in the caps, tonnage
increases, and required galvanized framing.
Chuck Favazzo discussed that direct costs were over by S23 million and corrected by using the design and pricing
contingencies of S15, but there were opportunities in the overage in the direct lines to reduce the cost in the TVD
process. He also raised concerns about using the S9.6 million escalation contingency line item to zero out the
overage. Kate Cassen explained that she used the same method she used during SD for escalation. Chuck Favazzo
asked that the escalation remain separate and not serve as a mechanism to zero out the overage. It was explained
why the escalation should remain as it was, and the intention to protect the final bid. The work would continue
throughout TVD.
Jon Himmel asked for clarification on the furnishing line item. Jon Himmel commented on the need for more line
items to break down the skate park. It was discussed that the MSBA likely would not have an opinion on the source
of funds for the skate park, but SMMA was looking into the requirements for using CPA funds. It was noted that the
skate park pad was part of the early release package one (ERP 1).
Chuck Favazzo recommended keeping the escalation contingency as is and explained that it was due to uncertainty
about the state of the world, but the next round would show decreased direct and increased contingency.
Mark Sandeen asked when the escalation contingency was set. It was reported to be six to nine months ago. Mark
Sandeen asked if they were in an environment that needed more or less of a contingency. Kate Cassen noted that
the environment was similar and that tariff conversations had decreased, except for steel, aluminum, and copper.
Mark Sandeen discussed that it seemed that more contingency would be needed given the current environment. He
asked what the recommended metric for triggering digging into a line item was, asked how much of the courtyard
was part of the site work, and asked where the Eversource line was.
Kate Cassen reported that the courtyard was S700,000. The team would review all the deltas to determine the
impact and then bring them back to the PBC. The Eversource fee was included in the utility company fees.
Chuck Favazzo commented that they would review all items during the TVD. Brian Black stated that they would look
into all items during TVD, which would start next week. The CD 60% estimate date was August 10, 2026.
The field house's size, the roof load and the need to go through the building inspectors were asked about. Brian
Black reported that their structural engineer created a model and was testing it, along with getting a handle on the
weights added to the roof. There may need to be reinforcement, but not a full overhaul.
Dashboard Recommendation to SBCFC:
The dashboard for the Lexington High School project was presented. DD will be submitted on April 13, and then the
dashboard will go live.
It was commented that the high-level information was helpful. Having a hierarchy with multiple levels of information
was discussed. It was asked if it was only a financial dashboard or provided other information. It was discussed that
the dashboard was primarily for financials, with other information on the website, and that announcements could be
included in the monthly highlights.
Jacob Greco noted that he was looking into adding a watermark or stamp indicating that the dashboard was under
development or a draft.
Chuck Favazzo asked if change management was included in the dashboard. It was reported that information would
be added to the contingency and reserves section.
The amount of detail to provide on the dashboard was discussed. There was a desire to be transparent, but every
detail could not be provided. It was noted that they were also working to avoid any phishing scams.
Mark Sandeen recommended adding spending broken down by category and the amount completed for each
category. It was explained that the progress bar would indicate both the amount completed and the amount of
money spent.
Change Order Processing:
The step-by-step process for owner -directed changes over S500,000 was presented. Before all of the steps were
worked through, there would also be initial conversations to determine if the change was necessary.
Having different contingency levels for each group was discussed. It was suggested that Facilities handle up to
S250,000 and that the PBC handle up to S500,000.
The construction manager -driven change order process was very similar, except that contingency relied on DPF
approval.
The construction invoice review process was presented. Ultimately, the goal was to pay invoices during the first
week of each month. There were over 30 people engaged throughout the process. Jon Himmel commented that the
detailed review seemed like when most of the work was done.
It was noted that the MSBA had its own audit process. If the MSBA found anything wrong, they would make an
adjustment as needed.
Mike Burton discussed that the project team, including Dore & Whittier, SMMA, and Turner, the Department of
Public Facilities, the PBC and SBC, and MSBA, all provided financial oversight.
PBC Discussion on ATM Article 26 (Recommendation to ATM):
Kathleen Lenihan requested to present the slide that showed the layers of financial oversight at the town meeting
regarding Article 26. She reported that they had a written report and a video for the meeting. The moderator will play
the video of the report, and then Articles 26 and 27 will be reviewed. She stated that she could present the slide
during the discussion.
It was commented that the oversight was time -sensitive each month. Kathleen Lenihan stated that she anticipated
many questions from citizens, and various individuals would be available to respond.
Mike Burton noted that he would send the updated slide about who was providing financial oversight.
Mark Sandeen commented that most people had made up their minds on an issue before attending a town meeting
and recommended responding in advance to the most commonly asked questions so that they could read them in
advance.
Kathleen Lenihan stated that only a vote from the PBC was needed on its position on Articles 26 and 27, and that it
should then include a brief explanation of why. She offered to help with writing the explanation to go with the vote in
opposition. Henrietta Mei recommended adding a note that 24 people were already involved in the review. Mark
Sandeen recommended adding the cost and schedule risk.
The PBC's recommendation and vote were discussed. The PBC has reviewed and approved OPM's presentation,
created in conjunction with the architect, OPM, and DPF, on the requisition review process across multiple levels,
including certifications. The process, as discussed, is carefully choreographed, and the review period is limited to five
days. It was commented that the PBC does not recommend further consideration as presented in Articles 26 and 27.
Mark Sandeen also recommended that Chairs be authorized to write statements for the town meeting.
Jon Himmel said he was not sure they wanted a position on Article 27, since it seemed to relate to citizens being able
to see how money was being spent, and there was general consensus with his comment.
Motion by Jon Himmel to state that the PBC reviewed the information and recommended against Article 26, all
approved.
Mark Sandeen discussed why citizens were pushing for Articles 26 and 27. He stated that they were looking for tools
that would issue warnings when anything needed to be addressed. He asked how people would know if there were
any concerns by looking at the dashboard. He commented that if they could tell citizens that, they would likely
address most of the concerns.
Mike Burton stated that it was the intent of the dashboard. The dashboard would address financial and contingency
problems. Mark Sandeen stated that they would need to help everyone understand how the dashboard would
provide the necessary alerts. Mike Burton discussed that it was hard to see what it would do until they got into the
construction, but they could do a simulation. Mark Sandeen requested a short explanation. Mike Burton confirmed
that they could create a short explanation.
Public Comment
Robert Pressman stated that when he voted yes, he was under the assumption that the budget put forward included
the cost of replacing the fields. He discussed concerns about using CPA funds.
Manaj H. expressed surprise at the increase in costs for the structure and foundation. He proposed a simpler
approach for the foundation and asked if the full document for DD would be available. Chuck Favazzo discussed that
it would continue to be discussed during TVD. Manaj H. asked how the design was showing the most efficient
system. It was confirmed that it was on the TVD list to look at. Manaj H. requested a set of drawings. Mike Burton
stated that they would send some information.
Urgent Business
There was no further business.
Motion to adjourn PBC, all approved.