HomeMy WebLinkAbout2026-02-26-ZBA-min.pdf
Meeting Minutes of the Lexington Board of Appeals
Conducted Virtually, Via Zoom
February 26th, 2026, 7:00 p.m.
Board Members: Chair – Ralph D. Clifford, Norman P. Cohen, Nyles N. Barnert, and Associate
Members Scott E. Cooper and Thomas Shiple
Alternate Member: Jeanne K. Krieger
Administrative Staff: Jim Kelly, Building Commissioner, Olivia Lawler, Zoning Administrator,
and EmmaJean Anjoorian, Department Assistant
Address: 300 Shire Way (ZBA-26-3)
The petitioner is requesting a SPECIAL PERMIT MODIFICATION in accordance with the Zoning
By-Law (Chapter 135 of the Code of Lexington) section(s) 135-9.4 and 135-7.3.3 (see 135-
7.3.5(8) & 135-9.4 of the Zoning Bylaw in effect on 1 January 2016, and 135-42F(4) & 135-12 of
the 2009 Zoning Bylaw) to allow modification of a Special Permit with Site Plan Review dated
January 24th, 2008, and amended on November 22nd, 2010.
The petitioner submitted the following information with the application: Nature and Justification,
Plot Plan, ZBA Special Permit dated January 24th, 2008, ZBA Special Permit dated October 14th,
2010, Noise Evaluation Report, Supplemental Information about the Penthouse Addition, Site
Plans, and Definitive Site Development and Use Plan.
Prior to the meeting, the petitions and supporting data were reviewed by the Building
Commissioner, the Conservation Director, the Town Engineer, the Select Board, the Planning
Director, the Historic District Commission Clerk, the Historical Commission, Economic
Development, and the Zoning Administrator. Comments were received from the Zoning
Administrator and the Building Commissioner.
At 7:03 p.m., the Hearing opened.
Petitioner: John Hart on behalf of Takeda Pharmaceuticals
Mr. John Hart, civil engineer with SSMA, represented Takeda and began his presentation by
introducing Mr. Mike Gray, site capital lead at Takeda, 300 Shire Way. Mr. Gray stated that they
have requested a penthouse expansion for their facility. Mr. Gray then explained that Takeda
takes their role in the community seriously and noted Lexington’s sustainability efforts. Mr. Gray
further explained that the Town has emphasized energy conservation, electrification, and long-
term resilience, and stated that their project aligns with these priorities. Mr. Gray stated that in
2022, Takeda set a goal to reach net zero greenhouse gas emissions by 2035, and that this
project will help achieve that. Mr. Gray explained that the penthouse will allow Takeda to retire
two mechanical systems and replace them with modern, high efficiency, water-cooled chillers
paired with heat recovery heat pumps. Mr. Gray further explained that the upgrades will reduce
Takeda’s CO2 emissions and that they plan to consolidate the equipment away from Shade
Street to reduce visual impact, improve acoustics, and modernize critical infrastructure without
increasing occupancy, traffic, or creating new impacts to their neighbors. Mr. Gray concluded by
noting that the penthouse addition fully complies with the zoning requirements for the site
Mr. Hart reiterated that they have requested a penthouse expansion for equipment upgrades
and some limited site improvements. Mr. Hart then introduced his team which included Dave
Simon, Takeda Project Manager, Michael Bahtiarian, Acentech, Todd Kosterman, R.G.
Vanderweil, Steve Mahler, Ellenzweig, Eric Mitchell, Ellenzweig, Brian Lawlor, SMMA, and
Katrina Correa, SMMA. Mr. Hart then showed a rendering of the site and stated that the dark
blue areas indicate the two penthouse areas that they plan to add. Regarding zoning, Mr. Hart
explained that 300 Shire Way resides in the Planned Commercial District, CD-10, which has its
own zoning, and stated that the development, the building, and the addition to the roof lines fall
within the development envelope and within the limits of the 300 Shire Way building. Mr. Hart
noted that the project will not add to the gross floor area since penthouses will have mechanical
equipment. Regarding the building heigh, Mr. Hart stated that penthouses can reside twenty-five
(25) feet over the roof line of the building and can occupy sixty percent (60%) of the roof area,
which the project falls within. Mr. Hart the noted that a provision exists for three percent (3%) of
the roof area to extend above the twenty-five (25) feet to thirty-five (35) feet and stated that he
will explain how the project complies with that. Regarding the impervious area and limited site
work, Mr. Hart explained that the project will entail a twenty (20) square foot decrease of
impervious surface and the removal of three (3) parking spaces near the electric yard. Mr. Hart
noted that the project will not increase traffic demand or impact, will have no new gross floor
area, and will not need new employees. Mr. Hart further noted that the project will have no
increase on the sound levels, as shown in the sound study. Mr. Hart then showed a depiction of
the screen walls that go around the south, east, and west side of the building and stated that the
larger penthouse will contain the chillers and that the smaller penthouse will contain the
electrical equipment. Mr. Hart showed another depiction of the penthouse and stated that they
plan to have a second project take place within the next year that will also help to reach the
carbon emissions goal. Mr. Hart then showed a perspective of the new metal panel screen that
will run around the south side and extend above the roof and then the penthouse and then
showed some ground views of the proposed project. Mr. Hart reiterated that all the equipment
would reside on the south side of the building and then showed some of the proposed project’s
elevations. Mr. Hart stated that the screen wall will reside twenty-one (21) feet over the roof
deck, which sits below the twenty-five (25) feet allowed by zoning. Mr. Hart reiterated that sixty
percent (60%) of the roof can contain penthouses and stated that the project will cover 7,200
square feet while leaving 60,980 square feet of the roof remaining. Mr. Hart then showed
another rendering of the elevations and after showed the site plans. Mr. Hart noted that the
limited site work serves as an essential part for the electric infrastructure. Mr. Hart then showed
the existing conditions and the proposed conditions for the electric yard and reiterated that the
project will remove three (3) parking spaces. Mr. Hart further stated that they plan to restore the
sidewalks, repave the area, and replace trees, and concluded by stating that they will meet the
parking requirements with the loss of the three (3) parking spaces.
Mr. Barnert asked Mr. Hart what three parking spaces the project will remove and why. Mr. Hart
stated that they need to expand the electric yard to accommodate two transformers and that
they need to remove three parking spaces near the electric yard to achieve that. Mr. Barnert
then clarified that they do not plan to do any screening on the north side and stated that screen
would improve any sound that would go to Shade St. Mr. Barnert then asked why they do not
plan to put screening on the north side. Mr. Hart noted that the north side of the electric yard has
a six (6) foot wall and that the electric yard sinks down about six (6) feet, and stated that the
electric yard will not make any noise.
Mr. Cooper asked about the height of the building, after adding the penthouse and the
screening, relative to the building at 400 Shire Way. Mr. Hart responded that 300 Shire Way will
stand as a shorter building to 400 Shire Way and then showed a rendering of 200 Shire Way,
300 Shire Way, and 400 Shire Way.
Mr. Clifford clarified with Mr. Hart that the project will remove three parking spots and then asked
if Takeda experiences parking problems. Mr. Hart responded that Takeda does not have parking
problems and noted that Takeda monitors the parking. Mr. Gray stated that the campus has no
parking issues. Mr. Clifford then stated that he had reviewed the noise study and stated that as
he understands it, the upgrades will produce less noise than the existing conditions. Mr. Hart
confirmed that that would happen, and Mr. Michael Bahtiarian, Acentech, stated that the change
from the existing conditions will range anywhere from zero, meaning no change, to minus two
(2) decibels, indicating a reduction in sound. Mr. Bahtiarian noted that Takeda had committed to
have zero reduction or less and stated that this project complies with that. Mr. Bahtiarian further
explained that the project entails removing some big pieces of equipment and adding quieter
equipment. Mr. Clifford asked if that will continue with the next phase of the project, to which Mr.
Bahtiarian stated that he did not know since he does not know the specific equipment for the
second phase but stated that they will consider that goal. Mr. Bahtiarian stated that Takeda
purposefully places the mechanical equipment near Route 2 to keep the equipment away from
the residential side and stated that the other project would likely do the same.
No further questions from the Board.
No further comments or questions from the Public.
No further questions from the Board.
Mr. Hart thanked the Board for the opportunity to present.
At 7:28 p.m. Mr. Clifford moved to close the Hearing.
At 7:28 p.m., multiple Board Members second Mr. Clifford.
At 7:28 p.m., the hearing closed (a roll call vote took place: Ralph D. Clifford – Yes, Norman P.
Cohen – Yes, Nyles N. Barnert – Yes, Scott E. Cooper – Yes, and Thomas Shiple – Yes).
Mr. Barnert asked about putting a condition on the occupancy that stated that the sound must
remain lower, not higher. Mr. Clifford stated that the Board could and noted that the application
stated that the sound level will drop. Mr. Barnert stated that the sound study relies on estimate
and that the Board does not know the effects of the project. Mr. Clifford asked Mr. Jim Kelly,
Lexington Building Commissioner, if the permitting process would address that. Mr. Kelly stated
that he has worked with the applicant to have a consultant on behalf of the Town review
Takeda’s documents, to review Takeda’s as-builts, and to test the equipment. Mr. Kelly stated
that he will have good control of the project and that he has good cooperation with Takeda’s
team. Mr. Kelly then stated that he could manage and confirm the sound reduction prior to any
certificate of occupancy and final inspections. Mr. Clifford then stated that the Board can decide
whether they want to put a condition on the special permit, delay the process since the Town’s
report has not come in yet, or stay with the current noise limitations. Mr. Barnert stated that he
did not want to delay the process but stated that the certificate of occupancy should address the
noise matter. Mr. Shiple asked Mr. Clifford if the original special permit would allow a higher
decibel than what the application describes, to which Mr. Clifford stated that the application
seems to suggest that the proposed project will have a lower decibel level. Mr. Clifford then
stated that the Board needs to decide whether they want to leave that discretion to the building
permit process or whether the Board wants to take a more serious look at the sound. Mr. Clifford
noted that the Town has an engineer that with work with the Town and the applicant to ensure
that the project has no noise issues. Mr. Shiple expressed his content for letting the Building
Department manage the noise aspect of the project. Mr. Cohen stated that he did not want to
delay the project but noted that Takeda had had some noise complaints in the past. Mr. Cohen
also noted that no residents had shown up to the meeting and that he does not think that the
Board should lock Takeda in to having less noise than they have now. Mr. Clifford agreed with
Mr. Cohen.
No further discussion from the Board.
At 7:33 p.m., Mr. Clifford moved to approve the petition.
At 7:34 p.m., Mr. Barnert second Mr. Clifford.
At 7:34 p.m., the Board of Appeals voted five (5) in favor, zero (0) opposed, and zero (0) in
abstention to grant a SPECIAL PERMIT MODIFICATION in accordance with the Zoning By-Law
(Chapter 135 of the Code of Lexington) section(s) 135-9.4 and 135-7.3.3 (see 135-7.3.5(8) &
135-9.4 of the Zoning Bylaw in effect on 1 January 2016, and 135-42F(4) & 135-12 of the 2009
Zoning Bylaw) to allow modification of a Special Permit with Site Plan Review dated January
24th, 2008, and amended on November 22nd, 2010 (a roll call vote took place: Ralph D. Clifford –
Yes, Norman P. Cohen – Yes, Nyles N. Barnert – Yes, Scott E. Cooper – Yes, and Thomas
Shiple – Yes).
Meeting Minutes of the Lexington Board of Appeals
Conducted Virtually, Via Zoom
February 26th, 2026, 7:00 p.m.
Board Members: Chair – Ralph D. Clifford, Norman P. Cohen, Nyles N. Barnert, and Associate
Members Scott E. Cooper and Thomas Shiple
Alternate Member: Jeanne K. Krieger
Administrative Staff: Jim Kelly, Building Commissioner, Olivia Lawler, Zoning Administrator,
and EmmaJean Anjoorian, Department Assistant
Other Business:
1. Minutes from the February 12th, 2026 Meeting
At 7:34 p.m., Mr. Clifford moved to approve the minutes.
At 7:34 p.m., Mr. Cohen second Mr. Clifford.
At 7:35 p.m., the Board of Appeals voted four (4) in favor, zero (0) opposed, and one (1) in
abstention to approve the minutes from February 26th, 2026, Hearing (a roll call vote took place:
Ralph D. Clifford – Yes, Norman P. Cohen – Yes, Nyles N. Barnert – Yes, Scott E. Cooper – Yes,
and Thomas Shiple – Abstain).
At 7:35 p.m., Mr. Clifford moved to adjourn the meeting.
At 7:35 p.m., multiple Board Members second Mr. Clifford.
At 7:35 p.m., the Board voted to Adjourn (a roll call vote took place: Ralph D. Clifford – Yes,
Norman P. Cohen – Yes, Nyles N. Barnert – Yes, Scott E. Cooper – Yes, and Thomas Shiple –
Yes).