HomeMy WebLinkAbout1988-03-17-MCBIC-rpt.pdf :; , MEMORANDUM
c
air
March 17, 988
To: Board of Selectmen and Bikeway Committee
• From: jack Eddison
Subj: Bikeway Progress Report
The Minuteman Commuter Bikeway Advisory Committee to the state
DPW has met four times over the past six weeks. Two of these meetings
have been to review.and comment on the progress of the design work on the
project. The other two meetings have been for the purpose of identifying
artists who can help to incorporate art and artistic design into such com-
ponents of the bikeway as: signs, milestones, gates, bollards, fences, bike
racks, benches, etc.
At one of the meetings with Vollmer Associates, the design consul-
tants, we were given the enclosed materials on: 1 ) "Criteria for Screening
/Fencing" and 2) the projected Construction Cost Breakdown. The scree-
ning criteria were derived in part from those which have been used by the
META. They seem to me to be quite sensible and reasonable.
The cost breakdown total is well above the initial $1.5 million initially
earmarked for the Minuteman Bikeway project. We understand. however,
that an additional $3.5 million has been set aside for bikeways in the current
transportation bonding legislation.
The final design plans will be prepared separately for each town by
Vollmer Associates. Those for Lexington are expected to be ready for
submission to the town on April E. The target date for submission of the
complete plans, specifications and engineering estimates of the entire
Bikeway for review by the Department of Environmental Management (DEM)
is April 27.
The Advisory Committee was introduced to the art dimension of the
project by being asked, through Urban Arts Inc.. to review representative
examples. on color slides, of the work of some 50 area artists who have
expressed an interest in producing "public art". From this array we chose
four finalists whom we interviewed at a subsequent meeting. We were very
favorably impressed with the work of all four of these talented professionals
and found it. difficult to choose a single winner.
We agreed that each of the three that we had ranked the highest
could bring to the project, a particularly desirable talent or point of view.
Since the $5000 which had been included in the budget for art was clearly
not enough to compensate more than one artist. we recommended to the
consultants that they seek additional funding for this purpose. This was
done, and an additional $5000 was obtained from the DEM. With the
expanded sum, it was agreed on Marchll that the project could call on the
services of three artists, Virginia Gunter and Carlos Dorrien of Somerville and
Marty Cain of Cambridge. They were prepared to begin work immediately.
The Advisory Committee was pleased with this outcome and is confident. that
the Bikeway will benefit substantially from this infusion of artistic
imagination and talent.
MINUTEMAN BIKEWAY - CRITERIA FOR SCREENING/FENCING
It is not the intention of the Minuteman Bikeway project to separate the
bikeway frau the adjacent properties or to generally fence or screen the
bikeway frau adjacent properties. Fencing and screening are being
considered in certain areas for two principal landscape reasons:
1. To screen unsafe conditions and undesirable views from bikeway users
to maximize safety and enjoyment of the bikeway.
2. To provide security and/or privacy for certain properties whose
proximity or exposure to the bikeway creates an identifiable need for
such measures.
The following criteria are designed to assist abutters in determining
whether their property might be eligible for fencing or landscape
screening under the second category listed above.
1. The Cwner must show evidence that an issue of safety, security or
privacy is clearly identifiable.
2. Physical interruptions such as existing topography, streams, and
vegetation which separate the bikeway frau the adjacent property will
reduce the likelihood of the property being considered eligible under
this program.
3. Proximity: Small back yards will be given priority over extensive
yards which tend to buffer residences by virtue of distance alone.
4. Upon request, substantiated by evidence of need for assistance, a
preliminary review of individual abutter's circumstances will be made
by Town representatives. Upon passing this preliminary screening, a
review of the site will be conducted by the Architect/Engineer review
team for final approval.
5. Fencing or landscape screening, if approved, will require a 50 percent
Owner participation in the cost of fence and/or landscape materials
and installation.
6. Only the fence, or screen, which separates the R.O.W. from the Owner 's
property shall be considered participatory under this program. If
security is the identified reason for fencing, the sides of the
property must be fenced as well at Owner 's expense.
7. Gates: Providing access frau abutting private property to the bikeway
is considered contrary to the purpose of "safety and security." This
will not be considered eligible under the fencing/screening assistance
program. Gates may be installed, but the Owner must bear all costs of
the gate.
,11152
do. csU e. a�
]] a���
111111
4 • • L!
VOLLMER ASSOCIATES
BOSTON MA
8. Screening for privacy reasons shall be achieved through vegetation
unless the space necessary to produce the desired effect is not
available. If a vegetative buffer is not possible, a solid fence
shall be considered.
9. All fencing considered and approved under this program shall be
subject to availability of funds and shall be prioritized according to
need.
10. No retroactive reimbursement for fences previously built or contracted
for is possible.
Lj
MINUTEMAN COMMUTER BIKEWAY
CONSTRUCTION COST BREAKDOWN
CLEARING AND GRUBBING $ 150, 000
REMOVE TRACKS AND TIES 170, 000
EARTH EXCAVATION 80 , 500
ORDINARY BORROW 115 ,500
GRAVEL BORROW 164 , 000
BOULDERS 50, 000
RUMBLE STRIP 39 , 900
FINE GRADE AND COMPACT. SUBGRADE 116 , 400
EXTEND DRAINAGE STRUCTURES 60, 000
CLASS I BIT. CONC . PAVEMENT TYPE I-1 402 , 000
WOODEN GUARD RAIL 410 , 000
FENCING 106 , 000
GATES 87 ,500
LANDSCAPE SCREENING 741, 720
PLANTABLE SOIL BORROW ON BIKEWAY 134, 000
SEED 36 , 180
ROADWAY SIGNAGE 5 , 060
4" REFL. WHITE LINE (PAINTED) 24 , 500
12" RELF. WHITE LINE (PAINTED) 3 , 750
BRIDGE REHABILITATION 500 , 000
BIKEWAY SIGNAGE 22, 000
BIKEWAY ACCESS ELEMENTS 173 ,500
INTERSECTION LANDSCAPING 121, 520
SPECIALTIES (AMENITIES) 8, 000
SUB TOTAL $3, 722, 030
TRAFFIC SIGNALS $ 77 , 970
TOTAL CONSTRUCTION COST $3, 800, 000