HomeMy WebLinkAbout2025-04-23-SBC-min (High School and Center Recreation Working Group) MEETING NOTES
Meeting Date: April 23, 2024
Project Name: Lexington High School
Project Number:
Subject: High School and Center Recreation Area Working Group Meeting
Attendees:
Mike Burton DWMP - Project Director
Christina Dell Angelo DWMP - Project Manager
Jacob Greco DWMP -Assistant Project Manager
Lorraine Finnegan SMMA- Project Manager, Principal in Charge
Erin Prestileo SMMA- Civil Engineer
Will Park SMMA- Civil Engineer
Jim Malloy-Town Manager
Kelly Axtell - Deputy Town Manager
Carolyn Kosnoff-Assistant Town Manager for Finance
Mike Cronin - DPF Facilities Director
Mark Barrett- LHS Public Facilities Project Manager
Suzie Barry- Select Board Vice Chair
Doug Lucente - Select Board
Charles Lamb - Capital Expenditures Committee
Rick DeAngelis - Director of Recreation Programs
Melissa Battite - Director of Recreation and Community
Karen Mullins - Conservation Director
Christian Boutwell - Public Facilities
Alan Levine -Appropriation Committee
Deepika Sawhney- School Committee
VeIf'IYlf'14'nt MassadhUsetts www,doii eaII"lid" +IIiIIn IIeII Q Q01n"
Agenda Description
Item
1. Introduction: Refer to attendees list.
2. Article 97 Update:
Please see pages 6-8 for referenced attachments
• Interim meeting to discuss Article 97
o Monthly meetings will start taking place in June
• Spring of 2025 town meeting will be the motion to send it to Article 97
• L.Finnegan noted we are still in the PDP phase.
o This is for conforming to the Design Program and not to create actual designs
o Everything produced is subject to change
o The PDP is looking to show how the Program can work and fit with various buildings
o The PDP will be submitted on June 4th to the MSBA
• The MSBA will provide feedback on the program and not the designs
• L.Finnegan noted that the next phase, PSR (will go from June to December), will have to have one
design chosen by the end of it.
• L.Finnegan noted that after the PSR the actual design of one (1) building will start to take place
Schematic Design starting in January 2025) and show details such as classroom locations and
entryways and roughly 50 pages of specs.
o The Construction Documents will have much more
• L.Finnegan stated that MSBA will not issue reimbursement if there is an open Permit for wetland
relocation. MEPA approval is required.The provided schedule shows the worst-case scenario for
reimbursement.
• L.Finnegan noted that the current (13) alternatives being priced will replace all fields and associated
surroundings as part of the high school project.
• L.Finnegan noted that the wetlands on site have been flagged but more study and research will take
place.
• W.Park reviewed the provided schedule
o Design Phase
• PDP Phase: At this phase all site options should be presented with potential
development restrictions identified
• January 2024 to July 2024
• PSR Phase:The MSBA requires a summary of the process undertaken to identify all
potential issues and steps that are to be taken to resolve them. An updated
schedule that includes dates of anticipated approvals (e.g. Article 97).
• July 2024 to January 2025
• MSBA Approves Feasibility Study
• February 2025
• Schematic Design Phase: Upon submission of the District's SD Submittal, it is
preferred that the district have ownership, full control, and access of the site.
However, if there are any prevailing issues that are mapped out to the satisfaction
of the MSBA, staff will forward a conditional budget and project scope
recommendation to MSBA Board of Directors.
• December 2024 to August 2025
• MSBA Approves SD *Conditional See Advisory 45
• October 2025
• Town meeting& debt exclusion to approve project and funding
■ November/December 2025
• Worst case for MSBA reimbursement to commence
• September 2026
o There is one section that includes all things Article 97& MEPA.
Page 2 of 5
• We are currently progressing through the initial Article 97 local groundwork and
introduction Meeting with MEPA.
• January 2024 to January 2026
• Project introduction meeting with MSBA
• January 2024
• PLPA initial call
• February 2024
• PLPA waiver submission with alternatives (if applicable)
• March 2024 to July 2024
• Advance alternatives from MSBA level to level suitable for EEA
• July 2024 to March 2025
• PLPA portal notification (if necessary)
• October 2024 to April 2025
• Town meeting Approval of Land Swap
• May 2025
• State Legislative approval of Article 97 Bill -Prep& Filing
• January 2025 to March 2026
• State Legislative Approval of Article 97 Bill
• March 2026 to September 2026
• Engage M EPA Consultants and start Traffic Report
• October 2024 to January 2026
• File and gain MEPA approval for ENF, DEIR, and FEIR
• January 2025 to January 2026
o Wetlands
• The risk of associated with this timeline is the challenge of permitting over 5,OOOsf
of wetlands
• It should be stressed that with this timeline"the Commissioner may waive the
application of one or more of the regulations on the basis of overriding public
benefit is intended to be employed only in rare and unusual cases.The provision
authorizing a variance request directly to the Commissioner for projects on land
within more than one city or town is intended to apply to projects that involve
functionally related work in several contiguous towns (e.g., transportation and
energy transmission facilities) and to provide for a single uniform determination
concerning alternative locations and the other variance criteria."
o Questions
• A.Levine asked that it is true if the MSBA will not sign a PFA if all Article 97& MEPA
issues are not solved
• L.Finnegan stated that the MSBA board will approve the SD and project but
will not start reimbursement until it is approved
• M.Battite asked what the waiver process is
• W.Park stated that using the waiver process will allows the project to go
through the Article 97 process while avoiding MEPA
• L.Finnegan noted the waiver takes out one step of the process but does not
get rid of the Article 97 process
• M.Burton asked how confident the team is in the 6-month legislation review time
span
• L.Finnegan noted that the time span is actually one year but if the correct
leg work(such as this meeting) is done correctly the timeline is often
reduced down to 6-months.
• L.Finnegan noted that simply filling the wetlands is not a simple task as described above, especially
when keeping the student population,the ability to continue their education.
Page 3 of 5
• L.Finnegan noted that avoiding the wetlands entirely will severely disrupt the current education due
to phasing the project as Arlington did.There will have to be use of a large number of modulars.
• L.Finnegan stated that it will be very difficult to find a feasible option that stays entirely off Article
97 land
• E.Prestileo described the two (2)figures provided, Figure A& B. Please see the attached figures
under the presentation
o L.Finnegan noted it is clear that the Town of Lexington owns this land, but it is used by
multiple groups
• D.Lucente asked if the parcel along Worthen Road can be included in the land use figures
• J.Malloy stated that when SMMA is ready monthly meetings will be conducted in starting in June as
many members of this working group are not included in the SBC.
• C.Lamb said that in the 41-40 public plot is has been discussed that if this plot was not intended on
being used it should be left off the plot to not stir up any issues. If it is planned on being used it
should be added to start the conversation now.
• D.Lucente asked if the building on plot B (Figure B) used the wavier process to build this on park
land?
o A.Levine stated that it was built prior to the adoption of Article 97 in the Massachusetts
Constitution
• J.Hackett commented that while being mindful of how this process works having been through an
Add/Reno to a high school it was one of the most difficult experiences and was very disruptive to
their education. Having already gone through disruptions within the pandemic this should be kept
in mind.
Public Comment
• P.Kelley noted that is absolutely essential that the recreational fields are not disrupted. Kelley has
presented something prior in a rough way but would like a serious look into how to accomplish the
project goal without cutting the fields in half and using Article 97 land.
o R.DeAngelis followed up P.Kelley's comment by stating that in the Boston High Rise
buildings they do not use large laydown areas. DeAngelis suggested using the nearby landfill
area and trucking the resources to the job site. If they must be taken it should be as late as
possible
• J.Hackett asked if there was a verbal commitment that plot 41-40 will not be used in the project
o C.Lamb stated that it was said by M.Cronin it was "not in the cards" currently
3. Close
Working group meetings will start again in June 2024 for monthly meetings.The website will be updated
with meeting information on a weekly basis.
Sincerely,
III:� III''°�IIII °�Wllh°°i III""111""""111""1111111 III'°�
Christina Dell Angelo
Project Manager
Page 4 of 5
Cc:Attendees, File
The above is my summation of our meeting. If you have any additions and/or corrections, please contact me
for incorporation into these minutes.
Page 5 of 5
� o
� z
E
aEQ
min -
o=
oE� -
o-
E - E
- v 3 - E E 3 s m - - ➢ `p E p E - v 3 _ E
f
o
p w �n - � z a x ¢ w Q r - u � w m n o3 � a Q 3 v +• - v � v
M
r
r
i
4 �
/i/// �%�i �/ ✓� �%err/�// /� //
LEGEND '��
PLAYGROUND 0.08 AC
WOODED 2.31 AC
WETLAND 3.20 AC
PEDESTRIAN CIRCULATION 1.06 AC
VEHICULAR CIRCULATION 2.30 AC
PARKING 0.62 AC
BUILDING 0.61 AC
OTHER 3.28 AC
o ARTICLE 97 LAND 24.20 AC
' INFORMATION BASED OFF GIS AERIAL PHOT
AND DRAFT SURVEY DATA.SOME AREAS ARE APPROXIMATE
DATE: 311412024 LEXINGTON HIGH SCHOOL � SMMA
Figure ISSUE:
SCALE: 1"=400'
251 WALTHAM STREET
REF: LEXINGTON, MA 02421 SYMMES MAINI3 M.KEE ASSOCIATES
ARTICLE 97 AREAS 1000 Mal 1�3 s0huseAvenue
DR BY: LCF ce�na��dge,moss 7husetts W 113
F:617,547.5400 F:617.648.4920
CK BY: JOB NO.:23090
PARCEL#/ID OWNERSHIP RESTRICTION NOTED IN DEED CURRENT USE
m, r1G1 ) 1:1 A Town of Lexington None Public Park/Open Space
B Town of Lexington Public playground, may revert to Public Park/Open Space
grantor with consent, may be used
1 r ,
for education structures
(Bk625/Pg543)
C Town of Lexington Public park and playground Public Park/Open Space
D Town of Lexington School purposes High School
E Town of Lexington None Public Park/Open Space
F Town of Lexington None Public Park/OPen Space
G Town of Lexington None High School
PROPERTY- LEXINGTON ASSESSORS ID 49-90
r/t
r
//; %�!� ' „y�. � ^��✓ �� Ji, 0 rr l�'d ii � ,:.� df//,,y�/�/ ur��'� -' �� � �' �,.i��/li�i r
G
i
i
,
Vr oofii i
P iip
o
r, d
i r
FureDATE: 4/18/2024 LEXINGTON HIGH SCHOOL � SMMA
ig
ISSUE:
SCALE: 1"=400'
251 WALTHAM STREET
REF: LEXINGTON, MA 02421 SYMME6 MAN &M.KEE ASSOCIATES
AREA USE RESTRICTIONS 1000 Ma achuseM Avenue
DR BY: LCF Cambridge,Wssachusetts W 11
8617,647.5400 F:617.648.4920
CK BY: JOB NO.:23090