HomeMy WebLinkAbout1980-SWAC-rpt.pdf 9 DRAFT
`�\�� REPORT OF THE SOLID WASTE ADVISORY COMMIXJ/ \,./J
Line Items
Town Meeting Articles 27 (Curbside Collection & Disposal)
28 (Transfer. Station & Disposal)
29 (NESWC)
Line Items - 4900 DPW Collective Bargaining; 5800 Garbage Collection
Contract, 5850 Sanitary Landfill
INTRODUCTION
The Town of Lexington has committed to the State the closure of the Hartwell
Ave Sanitary Landfill for general public use by July 1981. This date leaves
only fifteen (15) months of operation remaining at the writing of this report.
During the past year, at the instructions of the 1979 Town Meeting and the
Board of Selectmen, the Solid Waste Advisory Committee has investigated short-
term solutions (less than or equal to 5 year commitment) to our waste disposal
problem, and also possible long-term solutions other than the NESWC and
128 WRRC plans discussed last year
This report recommends a short-term refuse disposal plan (3 year duration) with
immediate startup and reaffirms the NESWC recommendation for a long-term solution.
NEAR TERM SOLID WASTE DISPOSAL OPTIONS
Since the discussions of solid waste disposal at the 1979 Town Meeting, only
small amounts of progress have been made toward the initiation of construction
of either the NESWC or 128 West (128 WRRC) disposal plants This fact has
underscored the Town's requirement for an economic near-term solid waste disposal
option.
Over the period July 1979-Jan./Feb 1980, the Solid Waste Advisory Committee
met approximately every 2 to 3 weeks with proponents of solid waste disposal
schemes Some schemes were analyzed only once, other concepts were asked back
for clarification and further questioning By the September/October time frame
it became clear that since there were so many options open, the only fair and
realistic approach to choosing a near-term option was to advertise for bids
which called for
1) Formally listed the Town's overall requirements for solid waste disposal.
2) Allowed the bidder to use either the existing landfill or one of his own
choosing for final disposal
3) Provided a recycling component
4) Included, either as options or as combinations, waste from private
homes, schools, condominiums and municipal buildings.
5) Provided for town-wide curbside pickup
In addition, the Committee recognized that townwide curbside pickup itself is an
issue in Lexington, and so also recommended the issuance (again through D.P W )
of a second RFP dealing with a transfer station located at the Hartwell Ave
facility Note that the location of a transfer station at Hartwell Avenue was
accepted by Town Meeting two or three years ago
Such a transfer station would allow for 1) a Town Meeting Article
centering around curbside pickup, the allowance of private and individual hauling
to the site at Hartwell Ave The refuse would thus be hauled to another
disposal site for final (out-of-town) disposition.
-2-
Each of the proposals and their responses will be discussed below
BIn #1 - TOWNWIDE COLT.FCTION AND DISPOSAL
Table I shows the options presented to potential bidders for townwide collection
and disposal Table II is a summary of those options
As one can see from Tables I and II, the options were structured so as to enable
the Town to get the incremental cost estimates for such areas as separate
recyclable collection, the cost of school refuse pickup, the added cost of
apartment and condominium refuse pickup, etc
This bid was similar to the Townwide Collection and Disposal bid issued by the
D P W in 1979
Table III shows the low-bid comparison for 1979 and 1980, option by option.
It is immediately obvious that
1) For any given option, the costs have risen by 33% - 57%
2) Once the contract is let, the contract allows costs to rise by
approximately 4%
3) That while the "A" options are less expensive than the "B" options, they
are really for comparison purposes only, since the "A" options in-
volve disposal at the Hartwell Ave Sanitary Landfill.
The Town D.P W has, this year obtained estimates of the solid waste tonnage
generated by private homes in Lexington The 18,000 to 20,000 tons per year
figure used by the Town still seems to be accurate
Hence the Townwide collection, haul, and out-of-town disposal costs appear to
be on the order of $25.50 to $28.00/ton, which is substantially cheaper than
the present combination of private contractor, individual haul and Sanitary
Landfill costs, even at last year salary and energy costs (estimated to be
$38/ton for FY '79 in last year's $ W A.0 report)
The possibility of townwide pickup with disposal at Hartwell in FY '81 was
discussed, and then switch to out-of-town disposal in FY $2 and FY '83 Table IV
shows that the apparent "savings" to the Town of $154,000 (Table III Options lA vs.
1B) is more than consumed by the extra $170,000 cost incurred by D.P W operation
of the Hartwell Ave facility as a landfill (Table IV) rather than closing it
In summary, we find that
1) Townwide Collection and out-of-town disposal is far less expensive
($25 - $28/ton) than even last year's estimates of the real cost to
the townspeople for solid waste disposal ($38 - $41/ton) .
2) Possible combinations of Townwide collection with 1st year Hartwell Ave
disposal and 2nd and 3rd year out-of-town disposal show no savings over
the simple plan proposed (townwide collection and out-of-town disposal)
TABLE I
SUMMARY OD ALTERNATIVES
COLLECTION AND DISPOSAL OF SOLID WASTE AND
RECYCLABLE MATERIALS
CONTRACT #80-6-E
Alternative la For weekly collection of combined refuse, and
disposal of the refuse inside Lexington at the
Hartwell Avenue Transfer Station..
Alternative lb For weekly collection of combined refuse, and
disposal of the refuse outside of Lexington.
Alternative 2a For weekly collection of combined refuse, ex-
cluding recyclables, and disposal of the refuse
inside Lexington at the Hartwell Avenue Transfer
Station.
Alternative 2b For weekly collection of combined refuse, ex-
cluding recyclables, and disposal of the refuse
outside of Lexington
Alternative 3a For weekly collection of recyclable materials,
and disposal of the recyclable material inside
Lexington at the Hartwell Avenue Transfer Station.
Alternative 3b For weekly collection of recyclable materials,
and disposal of the recyclable material outside
of Lexington.
Alternative 4a For daily collection of refuse from school buildings,
and disposal of the refuse inside Lexington at the
Hartwell Avenue Transfer Station.
Alternative 4b For daily collection of refuse from school buildings,
and disposal of the refuse outside of Lexington.
Alternative 5a. For weekly collection of combined refuse from
apartment houses and condominiums, and disposal of
the refuse inside Lexington at the Hartwell Avenue
Transfer Station.
Alternative 5b For weekly collection of combined refuse from
apartment houses and condominiums, and disposal of
the refuse outside Lexington.
Alternative 6a. For the collection and disposal of a combination
of solid wastes as described under Alternatives la,
2a, 3a, 4a and 5a
Alternative 6b For the collection and disposal of a combination
of solid wastes as described under Alternatives lb,
2b,3b, 4b and 5b
4
TABLE II
SUMMARY OF BID OPTIONS
CONTRACT #80-6-E
FEBRUARY 1980
RFP Homes & Apts &
Alternatives Trash Garbage Recyclables Munic. Bldgs. Condos. School Disposal Site
lA x x x x Hartwell
1B x x x x Out-of-Town
2A x x x Hartwell
2B x x x Out-of-Town
3A x x Hartwell
3B x x Out-of-Town
4A x x x Hartwell
4B x x x Out-of-Town
5A x x x x Hartwell
5B x x x x Out-of-Town
Combination Bids
6A (A's above) x x x x x x Hartwell
6B (B's above) x x x x x x Out-of-Town
-3-
RECYCLABLES
For the next three year period, the Committee favors the combined collection of
all solid waste (cans, bottles, paper, garbage, solid waste)for economic reasons
(See Tables V and VI)
However, we point out that the long-term solutions recommended and under continued
study (NESWC, 128 WRRC) both extract material and energy from the waste stream.
Here recycling makes sense both at the energy production facility (by making
electricity, selling scrap iron and aluminum) and before the material is sent
there (fewer tons to haul the 30 to 50 miles to the plant, smaller transfer
stations, lower "tipping" charges)
To encourage the retention of the recycling effort, recommend the placing of
recycling bins at either
1) Hartwell Ave. (opened 1 or 2 days/week for recycling only) , or
2) D.P W building (open 5 days per week)
RFP #2 - TRANSFER STATION AND FINAL DISPOSAL
The RFP recommended by S W.A.0 was issued by the D P W Its elements
are listed in Table VII
The purpose of this RFP was to assess the cost to the Town if the Townwide curbside
pickup and out-of-town disposal option were not favored by the Town.
All three bidders (BFI, RESCO, ROKETENETZ) came in with first year costs of
approximately $30 to $32/ton for construction and operation of a transfer station,
hauling to the final disposal site,and disposal there Cost increases after this
first year estimate were
1) Roketenetz - Increase $1/ton per year for a 5 year contract.
- Escalator for increased fuel charges --a--
- $1.00/ton rebate for out-of-town tonnage
2) BFI - Increases tied to Boston Consumer Price Index
- $0 50/ton rebate for out-of-town tonnage in a
500 ton/day facility (Lexington generates
approximately 60 tons/day)
3) Resco - Increases tied to Boston Area Wage Index, Real Estate
Tax (Saugus)
- $2 50/ton rebate for all tonnage (including Lexington)
delivered to transfer station.
We find these costs much higher than the costs for Townwide collection and direct
out-of-town disposal even when private hauling costs to the transfer station are
not included All of the transfer station proposals call for long-term commitments
by the Town which effectively lock us in to proposals that are not in the best
interest's of the Town We do not recommend the Transfer Station option.
h
TABLE III
LOW BID COMPARISONS
Town-wide curbside collection and disposal - first year of a three
year contract
1979 1980
Low Bidder Low Bidder
First Year First Year
lA $245,000 $356,000
18 $382,000 $510,000
2A $225,000 $355,000
2B $343,000 $510,000
3A $ 52,000 $76,000
3B $ 58,000 $ 90,000
4A $ 14,000 No bid
4B $ 18,000 $ 10,000
5A No bid No bid
5B No bid included in 18
Cost Growth 2nd year (proposed) 2%-6% 4% ($530,000)
Cost Growth 3rd year (proposed) 2%-6% 4% ($550,000)
TABLE IV
DPW Landfill Operation Option Costs
Cost of Lexington Solid Waste Cost of Solid Waste
Fiscal 1980 Landfill Closed
Fiscal 1981
Landfill Operation
Personnel $42,739 $29,170.
Expenses $65,290 $23,550
$108,029 $52,720.
Administrative Cost
Director $ 5,824 $ 2,000_
Engineer $ 2,300 $ 2,300
Clerical $ 5,500 $ 500.
$ 13,624 $ 4,800.
Garbage Collection $ 72,000 $ 7,200.
Eauiprent Maintenance - 7/1/79 - 2/8/80
Fuel Estimate $ 3,008 $ 1,000.
Reppirs $38,683 $10,100.
Necnanics
Wages $11,905. $ 1,000.
$ 53,596 $12,100.
Total $247,249 Total $76,820
TABLE V
RECYCLING - 1978
INCLUDING NOV & DEC.,1977
(beginning of curbside recycling)
Newspaper Collected Total Income
North Shore Recycled Fibers Corp. 114 280/tons @ $26 00
Salem, MA 91 40/tons @ 21.00
79 302/tons @ 16.00
88.17/tons @ 14.00
194 645/tons @ 6 .00
414 38/tons @ 5 00
982 177/tons $10,633.66
Glass
Miller Disposal, Inc. 301.70/tons @ $10 00 $ 3,017 00
Bedford, MA
Cans
Miller Disposal, Inc.
Bedford, MA 42.98/tons @ $10.00 429 80
Su.tap Metal
Tewksbury Auto Parts, Inc.
Tewksbury, MA 438.02 /tons @ $10.00 $ 4,380 20
GRAND it/1AL $18,460 66
TABLE VI
4' RECYCLING - X979
(Curbside Collection Ended - 5/31/79)
Total Income
Newspaper
North Shore Recycl Fibers 853 449/tons @ $5 00
Salem, MA 01970 91 295/tons @ $8.00
944 744/tons $ 4,997 60
Glass
Miller Disposal, Inc.
Bedford, MA 379 30/tons @ $10 00 $ 3,793.00
Cans
Miller Disposal, Inc.
Bedford, MA 37 77/tons @ $10.00 $ 377_70
(6 months)
Scrap Metal
Tewksbury Auto Parts, Inc.
860 East St. , Tewskbury, MA
(Martel Recyclables, Saugus) 303 15/tons @ $10 00 $ 3,031.50
Grand Total $12,199.80
(Revised - 2/1/80)
4
TABLE VII
SOLID WASTE TRANSFER STATION
R.F.P (7 Feb , 1980)
- With/without townwide curbside pickup
- Hartwell Ave location
- Out-of-town processing and/or disposal
- 5, 10, 20 year contracting periods allowed
- Able to accept waste by 31 Dec. 1980 at location or at acceptable
interim facility
- Bonded construction 3
Labor and materials
Bonded operation
- If accepts out-of-town waste, Lexington is paid a fee
J
EPA/CORDIAN ANALYSIS OP ALTERNATIVE RESOURCE
RECOVERY PROJECTS IN NORTHEASTERN MASSACHUSETTS
100
90 • LANDPIL4.
80 •
70 SESWC
60 BAYSIDE
50
40
- NESWC
30 •
20
10
•
0
79 80 82 84 86 88 90 92 94 96 98 2000 02
YEARS,
Mardian Assoc , Inc. for U S EPA 2 April 1979
01
A
-4-
NESWC
At the 1979 Town Meeting, the Selectmen's Solid Waste Advisory Committee obtained
the approval of Town Meeting to allow the Selectmen to sign a long-term contract
for disposal of Lexington's solid waste with resource recovery from the waste
stream. The program is going forward, but slowly
We have included in this report a comparison of per-ton costs done by Gordian
Associates, Inc of Washington, D.0 for certain North Shore communities to
compare NESWC with other proposed local solutions As one can see, the cost
levels and cost-growth for the NESWC facility is most favorable. This is due
to the sale by the facility of electric power to the New England Power Company
(NEPCO) at a certain stated rate NEPCO has recently, however, proposed a decrease
in the agreed upon purchase price of electric power from NESWC and all other
generators, the result of which is a less favorable cost-versus-time picture
The Mass Department of Public Utilities will hold a hearing on the matter before
Town Meeting
The Committee still favors the NESWC project as the long-term solution to Lexington's
solid waste disposal problems We are continuing to work with their Contract and
Transportation Committees and to be vocal in expressing our views on the project
CONCLUSION
1. The Couuuittee.recommends three year collection and out-of-town disposal as
an interim cost effective measure
2 The Committee recommends support of Article 29 (NESWC) subject to the
Selectmen and appropriate advisory committees feeling that this is the
most cost effective measure for the Town Any change will result in a
full report to Town Meeting
3 The Committee does not recommend a transfer station at this time because it
is not cost effective and requires a long-term commitment that requires
commitment to escalators such as the CPI that are not controllable.
4. To sustain a commitment to recycling, appropriate locations will be
designated to continue a recycling commitment to cans, glass, paper and
metals
Respectfully submitted,
James Reilly, Chairman, Solid Waste
Advisory Committee
Fred C. Bailey
Susan Solomon
Robert Hauser
Michael Hanlon
Warren Empey
Robert M. Hutchinson, Jr.