HomeMy WebLinkAbout1974-BOH-rpt.pdf 1
1
REPORT
RELATIVE TO
l FLUORIDATION
1 LEXINGTON, MASSACHUSETTS
1 JULY, 1970
I 1
[i ��ZH OFAtgs;�
/...;,e‘..\.‘
ELIAS bG
(g COONEY t
E) NO. 21769 0 it
F, s'f F' 4�
SL
\FSS/4NAL
WHITMAN & HOWARD, INC
IJ ENGINEERS AND ARCHITECTS
89 Broad Street
Boston, Mass
j
LJ
I
L.
I �
ofttellied by
YAt'.IUC G2r-19.77?;
1-1
1 EST 1869— INC. 1924
W&H
I
i
C. Roger Pearson, President ASSOCIATES
C R.Wickerson,Treasurer WHITMAN & H O WA R D INC
I-; Paul F Howard, Chairman f
George G. Berlow
I Jr. Gerald T Carey
Paul C. Bucknam,J
Engineers and Architects Anthony Chiaravelotti
Brewster W. Fuller Elias A.Cooney
Myles F Howard 89 BROAD STREET BOSTON, MASS. 02110 TEL. (617) 426-6400 Robert E. Crawford
Robert T. Jones Roger P Disken
Charles G. Ellis
Frederick D.A King,Jr. Ernest H. Fagerstrom
James T.McDonough George A.Howland,III
Howard R. Perkins,Manager Laurence T Kraynick
C. Glover Thompson,Arch Officer July 13/ 19 7 Kenneth A. Lucas
Edward R. Mayer
Mr William L Cosgrove, Chairman
Lexington Board of Health
Town Hall
Lexington, Massachusetts 02173
Re Fluoridation of Water Supply
Dear Dr Cosgrove
In accordance with our agreement with the Board dated
April 3, 1970, we are pleased to submit the following pre-
liminary report on the methods, costs and operating procedures
for the fluoridation of the Lexington water
Lexington is supplied with water from the Metropolitan
District Commission (M D C ) and is fed at four remote points
At each of these locations the quantity of water is metered
by the M.D C and the Town of Lexington is billed for the water
based on these readings At the present time, the average daily
water consumption is in excess of 5 , 000 ,000 gallons per day
In order to effectively fluoridate the water, the chemical must
be injected at each of the four locations where the water enters
the Town At each metering location the Town owns an adjacent
I
lJetz /0/4 Teat a UanLtnt[atta c etvtce
r1
concrete vault which presently houses chemical feed equipment
1 for injecting sodium hexametaphosphate into the water to control
corrosion and to sequester iron and manganese and, thereby,
prevent red water problems The size of these subsurface
vaults averages 290 cubic feet (6 ft x 6 ft x 8 ft ) The
vaults are located under the sidewalks on Summer Street at the
Arlington Town line, on Watertown Street near the Route 2
crossing, on Waltham Street near Route 2 and on Massachusetts
rl Avenue near the Arlington line Three of the vaults flood
periodically with water
Although there are different chemicals and feeding methods
available for fluoridating water two alternatives , sodium
fluoride and sodium silicofluoride, are feasible for Lexington
Llsince these chemicals are easily obtained, relatively safe and
the feeding equipment reliable
11
Sodium fluoride chemical is more expensive to feed than is
l sodium silicofluoride but the equipment to feed sodium fluoride
is considerably cheaper For larger installations sodium silico-
nfluoride is more economical (chemical costs lower) while in smaller
II installations sodium fluoride is usually more economical Since this
installation would be moderately sized, the choice of feeding
it methods becomes not only a matter of economics but convenience
and handling as well The two alternates will be described
Jseparately
-2-
Ui
f
SODIUM FLUORIDE ALTERNATE I
Sodium fluoride is a granular crystal that is easy to
handle and presents little or no health danger from dust A
` 4% saturated solution of the chemical is prepared and this
ri
solution is then pumped into the water system, the entire
1 process being automatic The operator only has to periodically
add sodium fluoride crystals to the 50 gallon saturator tank
1 Within the four existing vaults there is enough room to
j house sodium fluoride equipment along with the sodium hexa-
1 metaphosphate equipment The vaults themselves , must be water
` tight to insure the integrity of the chemical system To do this ,
a waterproofing compound would be applied to the walls,
1 new hatches installed, new concrete floors added and high
capacity sump pumps installed Once this has been done, the
fluoride equipment would be installed along with new phosphate
feed equipment The chemical pumps could be paced from the existing
-� M.D C water meters located adjacent to the vaults and the
chemicals fed into the main using the existing lines A typical
floor plan of one of the vaults may be seen in Figure 1
1 On Table 1 are listed the itemized costs for feeding sodium
fluoride from the existing vaults The total project cost would
L1 be $50 ,000 and the cost for feeding the fluoride would be about
`� $5000 per year Although this method would have the least
initial costs , other factors must be considered
L -3-
I TO DISTRIBUTION SYSTEM-›* ELECTRICAL DRAIN
WALL MOUNTED PHOSPHATE ELECT
PUMP—
WATER SUPPLY , 1
-
'I ' - lia. , al,g, 1
. ) .'t, , ____, --------,icEr----- ' \1/41
SUMP PUMP---CA,
1
ti SODIUM FLU RIDE 1
��� ATURA - r' V
n \b
- - tPHOSPHATEKS ;
it,
Ira. ,
WALLSIMOUNTEDLLRPUMP Ago
��
it
EXISTING HATCH
Li I
ELECTRIC
PACING SIGNAL FOR PUMP °
[ 1
TO
E FROM M.D.C.
H I ,
i
EXISTING CONCRETE VAULT 1
! 1
H TYPICAL SODIUM FLUORIDE RSTALLATION
ULEXINGTON, VASS.
SCAT E 14= %„
Li
WHITMAN & HOWARD, INC. PLATE I
ENGINEERS & ARCHITECTS BOSTON, MASS.
Lexington, Mass
Table 1
COST ESTIMATE FOR INSTALLING
SODIUM FLUORIDE EQUIPMENT IN FOUR
EXISTING VAULTS.
I ALTERNATE I
1. For waterproofing and reconditioning
the four existing vaults including,
waterproofing compounds, new concrete
floors, 70 gallon per minute sump
i pump, new watertight hatch covers
and all incidentals, labor, tools,
and equipment $12,000
11 2. For furnishing and installing
sodium fluoride equipment
including transmitters, chemical
pumps, two saturators per vault,
electrical controls, safety
equipment, test apparatus, unit
heaters etc. 24,000
3 For furnishing and installing
new sodium hexametaphosphate
feed equipment including new
pumps, two 55 gallon barrels per
vault etc 4,000
LITOTAL CONSTRUCTION COST $40,000
Contingencies & Engineering 10,000
TOTAL PROJECT COST $50,000
-5-
Li
U
r
Since the vaults are below ground, the bags of fluoride (100 lb )
would have to be carried down steep stairs The vaults are
l relatively small and maintenance and record keeping would be
II
difficult No room for storage would be available in the vaults
l
so the operator would have to transport the fluoride to each
location from a central storage And, of course, the possibility
always exists that the vaults could lose their watertight
integrity As a routine safety precaution, a second man should
be present whenever the first enters a vault
Based on financing this alternate over a 20 year period,
Il the annual cost would be about $3800 not including operation
and chemical costs
SODIUM SILICOFLUORIDE ALTERNATE II
An alternate to feeding sodium fluoride using saturators
would be to feed sodium silicofluoride using dry feeders and
LIdissolvers Sodium silicofluoride is a powder which is fed in
a dissolver from a bag loading hopper Water is automatically
LIadded to the dissolver so that the strength of the solution is
II always constant (0 2%) Using a proportional feed chemical
pump the solution is fed from the dissolver into the water
system
-6-
LI
I
r
The equipment necessary to feed silicofluoride is
11
relatively large and is more expensive than the equipment
Fl
to feed sodium fluoride but sodium silicofluoride is a less
expensive chemical and consequently costs less to feed The
I
vaults previously mentioned, are not large enough to accommodate
silicofluoride equipment
i
i
In order to use silicofluoride new above-ground structures
i } would have to be built in three locations, at Summer Street near
the Arlington Line, at Watertown Street near the Route 2 crossing
and at Waltham Street near Concord Avenue At the fourth location,
) 1 Massachusetts Avenue near the Arlington line, no room is available
for an above-ground structure and therefore, the present vault
will have to be reconditioned and the fluoride will have to be
fed using saturators and sodium fluoride as discussed under
I
Alternate I
jI A typical sodium silicofluoride station is shown in Figure
2 and 3 Within each building there would be proportional feed pumps,
helix feeder, dissolver, bag loading hopper, valves , piping,
electrical equipment, heater, file, desk, phosphate feed equip-
ment and storage for both fluoride and sodium hexametaphosphate
The total project cost for Alternate II including three
new silicofluoride installations and one sodium fluoride in-
IF ] stallation in the vault on Massachusetts Avenue would be $89 ,500 ,
LJ
while the cost for the chemicals alone will be $2800/year
!J
-7-
LI
9
Lexington, Mass
Table 2
COST ESTIMATE FOR INSTALLING
SODIUM 'SILI'COFL'UORIDE EQUIPMENT IN
NEW 'ABOVE_GROUND"STRUCTURES
ALTERNATE II
ri 1. For constructing three new above-
ground structures to house new
sodium silicofluoride equipment
including concrete, brick & block
masonry, excavation, fill, labor,
tools, materials etc. $30,000
i
2 For waterproofing and reconditioning
[ the existing vault on Massachusetts
Avenue near the Arlington Line to
house sodium fluoride equipment,
including waterproofing compounds,
II1 new concrete floor, 70 gallon per
minute sump pump, new watertight
hatch cover and all incidentals 3 ,000
3. For furnishing and installing new
11 sodium silicofluoride equipment
in the structures of Item #1
complete including piping and 27,000
electrical work
ll4. For furnishing and installing new
sodium fluoride feed equipment in
the renovated vault given in Item 2. 6,000
5. For furnishing and installing
new sodium hexametaphosphate
feed equipment including new
pumps, barrels etc. in each of
Ij the four locations 4,000
�� $70 ,000
Contingencies & Engineering 17,500
TOTAL PROJECT COST $89,500
-8-
H
{ Lexington, Mass.
i
1 Table 3.
CHEMICAL COSTS
FOR ALTERNATES I & II
11
1. Chemical cost for feeding Sodium
Fluoride into system at rate of
1 0 mg/L of Fluoride ion as
r� described as Alternate I based $ 13 60/day
on average 1970 water consumption or $ 50Q0%/year
tii 2. Chemical costs for feeding Sodium
silicofluoride in three installa-
i
11 tions and sodium fluoride in one
installation at rate of 1.0 mg/L
fluoride ion as described as
I_l Alternate II based on average $ 7 68/day
1 1970 water consumption or $ 2800/year
i
11 3. Chemical cost to feed 2 0 mg/L
of Sodium hexametaphosphate as
is now being practiced in
�
iLexington based on average 1970 $ 10 82/day
water consumption or $ 4000/year
I_Jll
l
LI
LI
-9-
d
Hi
A t
ri
Il' - 6 ..
r
9 .1 . 9 ' v
iI I PROPORTIONING PUMP -7
1�\ `\-\\\�`��\S\ \\ St \i - iii`\s�-• t �\ ko
n K) \' ,:xxXXxxxxxxxxxxyL xl///X/'X':✓Y�
\ F \ jl\ WALL
C - I / MOUNTED
\ :• ELECTRIC . PHOSPHATE
\ HEATER FAIl
, PUMP
\ \
~ 11,
PHOSPHATE
TANKS
by SCALE pmT�� FEEDER -m� WSODIUM+SILICOFLUORIDE DISSOLVERcriBAGS
_
LI 7 ELECTRICAL PANEL
+—STORAGE
( l \ • PLATFORM
J � i DESK
\ • PHOSPHATE
(l \ BAGS
\ '
\ •,
\ p FILE 4'
H4.\ CABINET 4`
\ xx)cxxk 0cri?,,r XxXXXX)XXX • A_AR s•
\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\` `D I
HSCALE 3/8" = I.- 0" 1
LI TYPICAL SODIUM SILICOFLUORIDE INSTALLATION
1 LEXINGTON MASS
1] WHITMAN C HOWARD INC .
I ENGINEERS and ARCHITECTS
BOSTON MASS .
Li
FIGURE 2
I
If the construction cost of $70 ,000 is bonded over a 20-year
period, the annual cost not including chemicals would be about
r $6700
A cost comparison between Alternates I and II can now
be made
ALTERNATE I ALTERNATE II
Annual Capital Cost
to 'orroT* coney
1 for initial con-
,truction $3800 $6700
Annual Cost for
1 Fluoride 0500n $2800
Total Annual Cost* ^0200 $9500
The difference in annual cost is t7n8 This difference
must be balanced against the convenience of above-ground
structures, the added safety, ease of maintenance, on-site
storage, record keeping etc that would be available with
new structures to house the equipment One additional factor
beyond the scope of this report is the land takings that would
be necessary for new structures
L
* Does not include labor or land costs
-11-
rl
I r
\ / Y
iii ""`�
; ‘, i 1
r
®� _
i ‘ - N. ,,. ,... _,_,_.,________.,..._...__..._.._..___..__....________________,...-., 1 '--. '1-ii:0-11H----
1 , '1 rek,43„--,
f , , . -a -________________,,i k,,,,\\,\, r------7 ,0,____-_,Tht
______ ,, \k
li
� � aar � a� �I III LH°LJ��.� 1 ��
jl
c 0‘ :i ril t. v i...-----------------------"--t—m-
C ��
TYPICAL SODIUM SILICOFLUORIDE STATION oJM
- NOT TO SCALE
co
it
I )
Once the 'initial capital expenditure has been repaid a
comparison between the Alternates should be made based on
11.1 chemical costs alone In fact, six years after the municipal
bonds to finance the project have been retired, the cheaper
cost of sodium silicofluoride has offset the higher equipment
costs and the two Alternates become economically equal
It is our recommendation that should Lexington proceed
it to fluoridate the water, Alternate II using sodium silico-
fluoride should be chosen based on long range costs , ease of
handling, safety and maintenance
OPERATION OF EQUIPMENT
1 Sodium fluoride, a granular chemical, is purchased
in 100 pound bags Each bag would last approximately three
L1
days per installation at average flow rates At maximum and
peak days fluoride would have to be added perhaps every day
The chemical is free-flowing and relatively safe to handle if
routine safety precautions are observed The saturator itself
jj is a 50 gallons plastic barrel in which the fluoride is added
LJ in excess resulting in a saturated solution of 4% strength
This constant strength solution is then pumped from the sat-
urator to the main Other than adding the chemical routine
L maintenance would be required to keep the equipment in top
operating condition Once every two or three months, the
saturators would have to be drained and thoroughly cleaned
-13-
a
1
2 Sodium silicofluoride is a free-flowing powder that
r
is slightly more dangerous to handle than sodium fluoride since,
as a powder it can form a fluoride dust The chemical is
shipped in 100 pound bags and each bag is hand loaded into the
hopper From the hopper a helix screw feeds the fluoride into
the dissolver The rate of chemical feed and the make-up water
it is continuously and automatically controlled to insure a t con-
stant strength solution in the dissolver From the dissolver,
a proportional pump discharges the solution into the water main
One bag of silicofluoride could last anywhere from 1 1/2 to
5 days depending on the rate of water consumption
Il 3 In both Alternates new sodium hexametaphosphate feed
equipment is proposed to replace the equipment now in use
J This is necessary because of space and to couple the pacing
Iequipment to all the pumps
Since the M.D C water for Lexington flows through
Arlington, the possibility exists that a joint venture be-
tween the two municipalities could prove beneficial to each
For this reason, we recommend that a conference be held
with Arlington, representatives of this office and with the
M D C to ascertain the feasibility of this
I
l1
-14-
U
J
I
ri
r
Petition will have to be made to the M.D C to obtain
permission to use the existing water meters to pace the
fluoride pumps
1
We shall be pleased to meet with the Board at any
time to discuss this report
rl Respectfully submitted,
WHITMAN & HOWARD, INC
11
X7. /ef/e/vrey
Steven Medlar
SM/ed
Approved By
��.�F-.
E A. Cooney, P E
-NOF MAssyC\
} I ELIAS t'
COON EY
0 NO. 21769
L \SeorgA cc'- ,
J
-15-
Li