HomeMy WebLinkAbout1995-03-03-BFC-min.pdf TOWN OF LEXINGTON
AD HOC BUILDING FINANCE COMMITTEE
Minutes of Meeting March 3 1995 in Room 111 , Town Office Building, as
approved March 10 , 1995
The meeting was called to order by Chairman Peter Kelley at 8 10 a m
with the following others present Committee members David Eagle,
Gilbert Garber, Donald Jenkins and Mark Moore, as well as Capital
Expenditures Committee Liaison Ron Grammont Also attending were staff
members Town Engineer Frank Fields , Superintendent of Building
iii Maintenance Fred Sweet and Director of School Building Operation John
Moynihan
Continuation of Town Building Review was presented by Fred Sweet In
summary, he noted that a "paper plan" for full ADA compliance had been
produced for all town buildings but that it does not have to be
implemented immediately , dependent upon use of the building
Report from Chairman on expectation for the committee Chairman Kelley
told of his meeting , beginning an hour ago, with Selectmen' s Chairman
Dailey and the Capital Expenditures Committee They discussed the
committee charge and progress toward "practical solutions" Among
related issues under consideration were the possibility the town might
share in a proposed regional salt storage shed and how possible $120 , 000
might best be spent Basically this committee is expected to look at
the facilities study, advise on action, and report to the March 27
session of Town Meeting Therefore the committee should meet for the
next three Fridays , the 10th, 17th and 24th By conclusion of March
24th meeting the report should be approved and ready for presentation to
Town Meeting
Field Trip Tentatively Scheduled for Saturday March 18 !
Further discussion of general town needs centered on how to proceed
For example, when a one to two year plan of immediate priorities was
mentioned, a committee member was concerned that the range was not long
enough However, at this time a statement is necessary to fulfill
political expectations
Agreed first priority is to identify "critical needs" , to be followed by
more long-range problems For example, Cary Hall ' s many problems due to
obsolescence of the roof , especially Water damage is due to water
running down inside the outside walls Current cost of slates was cited
(about $1 , 700 to $1 , 800uare er square)q ) as quite prohibitive of total fix of
ice-dam problems In addition committee agreed that most immediate
needs should be pointed out with ballpark estimates of cost , not
worrying about exactly how much or where the funding is to come from
Grammont suggested focusing on the oldest and neediest buildings ,
possibly splitting the committee giving various members look-see
responsibility for different groups of buildings Sweet asked if
resetting the front steps of Cary to prevent the most damaging water
would be in the first priority
Summarizing on Cary Memorial Building, Sweet reported that about $22 ,000
annually is allotted to replacing broken slates and repairs to chimney
and flashing Expenditure for full repair of the ice dam problem has
{
Ad Hoc Building Finance Committee 3/3/95 2
not been requested or estimated Eagle pointed out that ventilation is
also needed "Let ' s get the whole story, the full estimate of the real
fixing " he recommended Presently the only data is from the Archetype
report
In further discussion of immediate versus long-range fixing, Grammont
asked if making an unequivocal statement or judgment call is not akin to
preparing for a 100-year storm Replacement of Cary Memorial roof was
quoted as costing $94 000 in the report , but that today would cost at
least $120 ,000 while Town Office Building roof replacement would cost
27 , 000 and the police station about $13 , 000 but that need is not as
serious and repairs will do at this time
The bandstand is in need of more ventilation above and below The DPW
barn now seems to be "on its own" with plans for rebuild/renovation
Most needed now is a more accurate estimate of Cary Hall ' s needs Sweet
was thanked for his input on town buildings
Schools Report by Moynihan The Archetype report put a figure of $64
million for the schools in the next 10 years Moynihan has broken down
this list into needs , wants and "wish list" About $32 million of work
are driven by program changes Another $31 to $32 million would be
needed to bring the buildings up to today' s ( 1993 ) standards , but it was
asked whether that is really wanted or needed Moynihan told that about
$15 million really needs to be done, especially parking/paving
mechanical and electrical work Furthermore , the Archetype report
really covers only seven of the nine schools The high school and
Clarke were singled out for further program versus plant study Quite
possibly $90 , 000 more could be spent on studying the high school and
$40 , 000 more studying Clarke
The Administration Building is included in the list of town rather than
school buildings The schools are now completing the 5-year plan of
1990 that included leftovers not done in the 1986 renovation project
The schools have also prepared an ADA compliance plan No prioritizing
was done in the Archetype study The $31 million list has been given to
the School Committee
Among the most pressing needs to be addressed in the schools capital
budget request are $371, 500 for safety measures including Harrington
windows , doors and boiler work $1 1 million for system-wide electrical
work in all buildings and $653 , 000 for the networking technology plan
Computers will have a dedicated circuit as required Since 1987 all
roofs have been replaced except for Harrington, and that should be put
in next year (When questioned later about real need for replacement,
Moynihan gave history noting that the roof is approaching its life and
will need replacement in two years )
Of the $15 million most urgently required needs , $2 5 million have
already been done, including $2 million for Hastings renovations and for
boilers at the high school , $75 ,000 to rebuild the Crumb Field bleachers
and $25 , 000 for accoustical work at the high school $12 5 million is
yet to be done Moynihan was asked to provide a report on this in
writing
Ad Hoc Building Finance Committee 3/3/95 3
Classroom space will be lacking in the middle schools soon With
existing programs the school system will lack 14 to 16 classrooms in two
years Grammont emphasized that people want to hear from this committee
about impending problems "The town fathers are looking for direction, "
he advised "Be definitive "
After agreeing to meet each Friday from 8 to 9 30 a m for the rest of
the month, the meeting adjourned at 9 14 a m until March 10
Respectfully submitted,/
Erna S Greene, Secretary
{