Loading...
HomeMy WebLinkAbout2000-12-13-PM-PBC-min.pdf TOWN OF LEXINGTON,MASSACHUSETTS PERMANENT BUILDING COMMITTEE Minutes of Wednesday December 13. 2000 meeting in the Construction Trailer on the high school grounds, as approved January 3, 2001. The meeting was called to order at 7 18 p.m. by Chairman Kelley with other PBC members Cannalonga, Himmel, Johnson, Kennedy Poinelli and Touart present. Also attending were Project Manager/Owner's Representative Bill Kealy,Director of School Building Maintenance John Moynihan and Philip Lewis of HMFH. Distributed: Meeting agenda Report of Phase I extension meeting of December 1, 2000 Kealv's renort gave a newly revised schedule for the high school, as discussed at a meeting December 1 Library is in progress and cafeteria is done. Three of the four parking lot lights are up, but the fourth was vandalized and waits for bolts. A new company Walsh, has been hired for the site work, to replace Site, Inc., who was released by Peabody Construction. They will start tomorrow Grease traps are needed for the drains from the cafeteria kitchen. Eastern's CPM has just been received. According to them they are "on schedule" although at Clarke there are material problems; windows are delayed; and at Diamond, the steel is only 80 percent up. Eastern's requisition claims 40 percent completion,but the schedule suggests they are really only at 35 percent. Kennedy urged pressing Eastern to "get on with it' A change order is anticipated for the roof at Diamond as well as for the door added at the Clarke science room. Reauisitions from Eastern and Peabody were passed around for review and comment. Change Order Number 9 for$45,972 for the high school was also discussed. PBC members raised questions about the large number of man-hours (177) and high cost of materials. Kealy reported that Sullivan signed off on the number of hours for the six people working on the job. Both Lewis and Kealy expressed surprise at the appearance of this change order. More explanation was requested. The committee members complained about the lateness of the change order since the work for it was actually done between the end of September and Columbus Day weekend. Elementary schools draft contract copy was passed around. Meeting adjourned at 8:58 p.m. Respectfully submitted, Erna S. Greene, Secretary