HomeMy WebLinkAbout1997-08-28-PBC-min.pdf TOWN OF LEXINGTON, MASSACHUSETTS
PERMANENT BUILDING COMMITTEE
Minutes of Thursday August 28 1997 Meeting in Room 111 , Town Office
Building, as approved September 16, 1997
The meeting was called to order at 7 50 a m by Chairman Bruckman after
a futile search for a larger room to accommodate the large group, who
included other committee members Johnson, Kelley, and Poinelli , as well
as project manager D'Avignon and Director of School Buildings Operation
Moynihan Also attending were HMFH representatives John Miller, Dorthea
Hayes , Philip Lewis and Deborah Collins as well as Peter Bradley of
Daedalus estimators and TMP representatives Mike Spence, Roger Wardwell ,
Craig Hergenrother, Jud Traub, Brian McCormick and Kevin Alles
Chairman Bruckman explained that TMP personnel had been invited to tell
why engineering cost estimates had come in significantly higher than
expected from the Master Plan study Architect Lewis talked of refine-
ments
and changes in scope, some quite necessary He also noted that
the focus of the Master Plan study was on educational planning and
Archetype figures (updated, with additions included) were inserted in
the Master Plan estimates With the detailed analysis of each building
in the spreadsheets used in current estimates more realistic estimates
could be made However, there clearly is a conflict between political
and architectural realities , and the current cost estimates have
shocked Schematic estimates have provided the first good handle on
costs
Mechanical costs of approximately $3 8 million for all elementary
schools could be shaved by about 9 percent or $1 per square foot by
reduction in scope such as replacement of only half of the boilers
Univentilators are about 30 to 42 years old and would need gutting at
minimum The $10/square foot cost might go to $9 in design development
Commented that the numbers carried in the Archetype report , guided by a
"repair it" mentality and were way too low, especially in the high
school ($5 00 a square foot) Another possible saving might be attained
by cutting out conversion to gas service for heating Moynihan noted
later that bringing gas service to the high school (from Marrett Road)
would cost $50,000 and that the cost to convert all schools to gas would
run about $300 ,000 to $400 ,000 About $100 ,000 could be saved by
replacing steam traps and not replacing the univents
At Clarke a hydronic system is planned for the new addition and retro-
fitting for the existing electric heat pumps , which were donated by the
electric company only four years ago, and has raised many questions
about economy of operation Air conditioning has been recommended for
auditoriums at the middle schools Is this a "luxury item"? Delay in
replacing equipment could save money now, but might cost more later if
state reimbursement is not available
Moynihan questioned boiler and heating plant cost figures and what was
included in each estimate component He expressed preference for steam
systems rather than converting to hot water At Diamond the engineers
have planned for a hydronic stem in the library enlargement but that
steam be extended to the new wing Moynihan posed a comparison with
recent work on the Harrington heating plant Mechanical estimates are
coming in today for the high school without generators Battery packs i
are now being used for emergency exit lighting
PBC Minutes of 8/28/97 - Page 2
Plumbing engineers told that any piping and fittings from the ' 40s to
the ' 60s could contain lead and would require at minimum lead level
checking The most common problem in old plumbing was described as
leaking and wearing out of valves Highest plumbing costs were found in
the oldest schools , and all schools are in need of new water intake
service
Noted that phasing might affect costs, this has not been taken into
account presently Both general conditions and escalations will add to
costs Individual schools will have to be phased due to the small size
of each addition
Electrical overall costs were deemed in line, with a few up and down
adjustments of details Lighting systems for classrooms were discussed
in terms of costs and merits Indirect/direct lighting was deemed
optimal for classrooms Deep set parabolic lighting, commonly found in
office buildings , would cost about $180 ,000 less if installed in all six
elementary schools Engineer Alles was asked by the committee to
explore if an el-ectric company rebate program would be available for the
project Intrusion alarm systems would be needed mostly in the high
school , possibly also a motion detection system Money could be saved
by not replacing systems existing in gymnasiums
Concluding the discussion on generators , the committee determined that
small propane generators would be required for emergencies only
Engineers were instructed to go with battery packs for all schools
except for the three elementary schools that now have generators No
replacements will be done at the high and middle schools
At Hastings the electrical system was only partially replaced and two
original panels and much original equipment such as main switch still
are there Furthermore the generator is not connected to all emergency
fixtures In addition, more electric service needs to be brought into
the building than now is By code, fire alarm upgrade will be needed,
however, there will be no gym lighting or communications replacements
At Clarke new technology will affect the communication system At
Diamond TMP recommends replacement of all systems due to their age
Moynihan agreed, but also protested the piecemeal manner of presenta-
tion Chairman Bruckman called for grouping related items across
classifications and net savings reported for substitutions or reductions
in scope Architects promised refinement of schematic cost estimates
with full design development Chairman requested a list by the weekend,
with cost estimates incorporating committee decisions for next Tuesday
( September 3) meeting By September 5 there must be a book for each
school with existing condition spreadsheets (these without cost figures ,
which would be confusing) , one mounted set of drawings , a set of
drawings for each PBC member and Moynihan The color set for the public
should also be mounted
After departure of the visitors , the committee discussed recent ques-
tions that came up in meetings with Selectmen and Comptroller Ryan
Question arose about the imperativeness of the $83 million cost figure,
and need for sprinklers Agreed to begin the September 2 meeting at 5
p m Adjourned at 10 45 a m
GRespectfully submitted, Pi afr2---- Secretary