HomeMy WebLinkAbout1997-05-01-PBC-min.pdf TOWN OF LEXINGTON, MASSACHUSETTS
PERMANENT BUILDING COMMITTEE
Minutes of Thursday May 1 1997 Meeting in the School Administration
Building in two sessions , as approved May 20 , 1997
The meeting was called to order by Chairman Bruckman at 8 32 a m with
other committee members Kelley, Johnson, Poinelli and Touart present
Also present were Director of School Buildings Operation Moynihan, Dawn
McKenna and Bruce Collier ( last-named in afternoon only)
Prenaration for interviews Suggested that in first part of design
development the scope of work must be well defined, and that the
committee ask what additional information would be needed such as indoor
and outdoor environmental testing
Interview I HMFH Representing this firm were Principal-in-Charge John
Miller, Project Principal for the high school Stephen Friedlaender,
Project Principal for middle schools George Metzger, Design Director
Mario Torroella, Project Manager for the high school Philip Lewis ,
Project Administrator Dorothea Hayes , M/E/P (engineers) Principal
Michael Spence and Construction Manager James Mitchell
HMFH stressed the importance of their assistance in building community
support for the project so that it can meet success at Town Meeting and
in an override vote They emphasized their already-established good
rapport with school staff , reporting some staff skepticism at the high
school , where renovating the Science Building and addressing deferred
maintenance as well as systems upgrading are planned Torroella
described the HMFH design philosophy providing a stimulating
environment that is user-friendly and a flexible asset to the community
Miller talked about logistics of renovating during school operation when
"swing space" is lacking A "safe learning experience" is needed for
all students , he stated He also explained his firm's cost estimating
process , which would involve first the PBC and then the contractor in
the planning Jim Mitchell added that cost estimating is done in two
ways One is a computer-based program ("parametric") that factors in
area costs and is capable of managing costs within three percent Cost
managing measures must be accomplished with the stakeholders
Miller summed up the advantages of HMFH head start , superior
experience, design quality, management capability with quality teams ,
with depth of personnel to meet a tight schedule Responding to
Bruckman' s questions on tasks for the first few weeks should HMFH win
the design contract They would meet with the PBC to decide formats ,
organize a team for each school , and using the Archetype report as a
basis , report on each school 's existing condition This process would
be translated into the scope of work
HMFH's fielding of questions included note of rejection of a plan for
the town of Winchester, where citizens were insufficiently involved
HMFH is presently seeking partial solutions to educational needs of this
community and Wakefield in similar circumstances "Our job is to
reinforce a community's educational philosophy, " HMFH representative
stated, adding that (middle school ) clustering is difficult to encourage
PBC Minutes of 5/1/97 - Page 2
and achieve through design At the high school the challenge will be
the lack of unity among faculty and students ; there building redesign
should encourage linkages and other positive changes
Interview II Desian Partnership of Cambridae was represented by David R
Phinney, landscape architect Gary Larson, Greg Schroeder for the high
school , Keith Hoffses for middle schools and Jim McMillen for elementary
schools They underscored their depth of experience in renovation,
rapid response and high level of technology they could bring to a
project They would use Meridian Engineering A time-line schedule had
been drafted showing steps preparing for a September town meeting, with
middle schools plans going to bid in winter A Design Partnership team
would be freed June 1 , and the firm is presently recruiting to add to
their staff of 45 If they should receive the Lexington job, it would
be their number one commitment , taking the majority of their staff
Responding to questions about successes and failures , they told what
they had learned that preparation, organization and positive press are
key, that specifics must be supplied early in time to be digested
Project managers are an integral part of corralling community support
DPC can produce brochures When asked about worst nightmare they cited
Lowell ' s need to understand the budget before bidding and construction
Their comments on the high school entry problems touched on the lack of
a team of teachers , the confusing approach, the need for a central
library location (and a recommendation that the library should include
seminar rooms) , the need for more unified student commons and a total
science laboratory enlargement/renovation Larson added that separate
and clear accesses are needed for pedestrian and vehicular traffic, with
allowance for drop-off and pick-up More exploration of entry location
may be needed
Fielding queries on feed-back, cost estimating and phasing/scheduling,
Phinney talked of need for close relationships with contractors and
tradespeople, handling subcontractors with "an iron hand and tight
fist" He pointed out that 80 percent of his firm' s work is in
renovations When Moynihan asked what if the project is strung out ,
Phinney said they would like it ! His firm has had as many as nine
projects going at once Design philosophy/approach would focus on each
building' s needs to get more bang/economy of design Interior design
commonality is a good idea to enhance what is already there Diamond,
"most interesting, " would profit by having science integrated into the
new addition DPC would be available to start work in two weeks
A reauest for information from PBC has been received from supporters of
the Town Meeting' s appropriation for design development Suggested the
group 's literature include facts and what the alternatives might be if a
negative referendum were to reverse Town Meeting's action
The morning session ended at 10 55 a m ; the afternoon session opened at
1 00 p m
Interview III D R A who were represented by Carl Franceschi , Jim
Barrett ( formerly with Hastings project) , Pao-Ching Chi , Scott Dunlap
and Nancy Angney These people all showed on the organization chart in
PBC Minutes of 5/1/97 - Page 3
a folder of materials given the committee Under them would be job
captains and consultants chosen for the project About 25 to 28 of the
45 person firm would be working on the Lexington project Barrett would
be point person, channeling information in two directions
They showed on a board a 17-week work plan to the first week in
September They would want to establish the project goals and hold
weekly meetings The work plan for the project showed work on
elementary schools proceeding first
In the question period, DRA representatives cited design challenges in
giving the high school entrance better definition (more connected and
unified, with opportunity for outdoor relations) ; challenges at the
middle schools would be to make clustering work, and the elementary
schools need updating and to be made "more welcoming" When asked how
they could help with publicity and displays , DRA people recommended
public forums PBC chairman Bruckman asked about the role of "job
captains" (would be people having intimate knowledge of the project
without administrative responsibilities The "worst nightmare" response
told of fumes from a new gym floor in Gloucester, where the floor had
not been properly prepared Parts of that job had to be redone
Interview IV Earl R Flansburah & Associates Inc featured a large team
that included Design Review Principal Earl R Flansburgh, Principal -in-
Charge David S Soleau, Community Relations Principal , Kate M
Brannelly, Senior Project Manager Duncan McClelland, On-Site Coordinator
Dominic Pedulla, project manager for elementary schools Jeanne Kuespert ,
project manager for middle schools James Highum and project manager for
the high school James Williams , Jr Of the 82 total on the Flansburgh
staff , who have been specialized in schools in the past 31 years , about
20 would be available early in June Consultants agreeable to Lexington
would be engaged
Project issues were explained, as seen by the firm's visit to
Lexington' s schools Two independent cost estimators would be used
Overall oversight would be provided by Earl Flansburgh himself
Considerable attention was given to the possibility of waiving Chapter
149, the filed subbid law) as an aid to renovation projects The firm
is working to incorporate construction management into the project until
September, since costs and scope must be confirmed prior to a fall
special town meeting In the proposed work plan, all pertinent studies
would be reevaluated right away As-built plans would be scanned in;
RFP ' s would go out for extra studies that might be needed Weekly news
releases , including updating a web site, would be done by Kate
Brannelly
In the question period, design opportunities at the middle schools were
considered most challenging - to bring 40 to 50 year-old buildings "back
to life" The Flansburgh team would spend a day at school , checking how
lockers , circulation, school culture and long corridors work Seismic
code will have to be dealt with in the buildings , which are principally
steel-framed Different engineers would be hired for the elementary and
secondary schools , and the town would be consulted on who these would
be Moynihan quizzed the group on how they would handle construction
during the school year without "swing space" Flansburgh people would
PBC Minutes of 5/1/97 - Page 4
analyze the situation school by school Thought that some flex space
might be found at Clarke The firm has had experience with renovations
for the Renaissance (charter) School in Boston Flansburgh invited the
committee to their offices (being renovated) and to tour the firm's
projects Included in the Flansburgh handout were evaluation sheets for
site RFP and project management bids (described as 2 to 2 5 percent of
project cost) for a job in Malden
Interview ended at 3 00 p m and meeting resumed at 3 15 to consider
interviewing firms
The evaluation Process began with Moynihan's statement that he had
checked the references of the four bidders but not visited their
projects cited Bruckman asked each committee member to rank the
designers and explain reasons Below are some of the comments during
this round
About HMFH "Knowledgeable and with well established relations , but may
be too married to what they have already recommended They have a leg
up Followed our directions on presentation New design power would be
aboard for the next stage tremendous experience, good design does not
have to cost there were scheduling problems in the study preparing the
Master Plan, partly due to Lexington's actions HMFH is a nice firm,
but their first pass is overdesign What you see is what you get But
they are not strong on cost control HMFH must tell us when the
information is bogus We need to question their cost estimates more
often "
About Design Partnership "They have good energy level , freshness and
capability, technically up-to-speed However, they do not have a
history of accomplishment They are too small and somewhat
insensitive they do not have design capability, lacking
imagination they are light on people power "
About DRA They are adequate and will catch on Their schedule sank
them Franceschi is impressive, but none of the others have enough
experience They are not in touch with the town "
About Flansburgh "They have public relations capability; there may be
some economies of their size I like them best; they have lots of
person power We heard more from the chiefs than from the actual
working people; when they err they do it big Site management is a
great idea, but I wonder about their design ability "
The chairman then announced that HMFH and Flansburgh tied for first
place Further discussion, ranked HMFH first Agreed to re-interview
Miller clarify more about job organization Suggested he meet with
Moynihan, Bruckman and Johnson tomorrow at 12 30 in Moynihan's office
Meeting adjourned at 4 18 p m until Tuesday, May 6 at 7 30 p m
Respectfully submitted,
I
Erna S Greene, Secretary