HomeMy WebLinkAbout1988-12-08-PBC-min.pdf TOW OF LEXINGTON MASSACHUSETTS
PERMANENT BUILDING COMMITTEE
Minutes of December 8 1988 committee meeting in Room G-1 Town Office
Building, as approved January 12 1989
The meeting began at 7 40 p m with a quorum for the library Attending
especially for the library were Stella Liu Assistant Director and Ann
Wallace of the committee Others present for this and/or the following
section of the meeting included Chairman Kennedy, Edson, John Kennedy
Scanlon Smith and Touart Also present were staff Maclnnes and Coscia
and consultants Aitchison and Rowlands
Cary Library committee appointee Wallace reported that the new cabinets
look lovely and are almost done Painting is now in progress The
electrical work is not yet done and apparently neither is the HVAC
work Recently installed ducts seem to have caused cold air to flow
into the office formerly occupied by Ms Liu. The HVAC work is supposed
to cost $17 600 none of which has been paid The architect has been
visiting the job weekly or more often VOTED to pay Langton Douglas
$22 800 and architect Davies $1 006 94 for supervision of the contract
Quorum for the school renovation project arrived at 8 p m
Approval of all minutes not already accepted has been scheduled for the
next meeting The secretary was asked to provide a list of all minutes
not yet voted approved so that committee membe s can be prepared
November meeting minutes approval VOTED later in the meeting
This vote included acceptance of executive session minutes but not
their release , which would be automatic at the conclusion of the
project Among the corrections to stat .ments reported in the minutes
were the following
Though Iwerks had termed the basketball floor an addition the
replacement of this floor was in the KLQ report Furthermore telephone
calls to sell the old wood floor had been made by Rowlands not Iwerks
Rowlands said that he would correct the date on the minutes to read
November 10 and that the vehement dissent of Edson from the committee s
"collective decision" (to split the 1988 school renovation work into
three bid packages) should be noted
Hiah School Field House Roof Briggs is getting in touch with Morrello
who presently appears to be out of touch The roof is leaking at the
other end of the court , and towels have been put down when necessary A
question was raised about the welfare of the new fi.-tures beneath the
leaking roof Reports that they are water-filled have not been
substantiated Heating problems have been surfacing as winter has been
setting in The old gym and locker rooms are overheating at the same
time :peculated that the field house heabsng problem may be more than
missing insulation Coscia expressed concern that air movement is
insufficient and that the fans are not producing enough Rowlands said
he has some information on air flow measurements that were taken at the
end of the air ducts
1
PCB Minutes 12/8/8S
Air Quality at Clarke is still a
problem Rowlands is tryingto reach
Thermal Control Inc Plywood blocking has been discovered in air 1
handler equipment In the meantime Amtech has been saying, "Get another i
report " Chairman lamented that there is nobody to come in and
troubleshoot Committee requested that a letter be sent to Amtech
expressing the committee ' s dissatisfaction with the job they did on this
aspect of the project for $13 , 000
Progress Report Estabrook doors are warped High School is almost
complete Auditorium seats are being installed Lobby floor is not
universally liked Noted that all of the tiles will be down fully in
two or three weeks Final touches will be applied at the high school
during Christmas vacation Reported that J P Construction is suing the
town because of delays due to rebidding on metals and HVAC There were
failures in receiving the order for steel Diamond steel has arrived
Fiske steel is yet to come Noted that TAMS may be involved in the
delay Rowlands reported that there was a mixup between the contractor
and subcontractor Also at Fiske the roof was found to be saturated
When cut for the addition water oozed out Insulation was like soft
sand-clay However there is no more money to remedy this
situation Estabrook computer room roof air conditioner will be
delivered in about ten days This and the counters did cause
delay Asbestos work remains at Fiske and Diamond
Finances VOTED $4 000 extra for double doors for storage near the
stage to the rear of existing doors $6 000 extra expense was incurred
in cutting the Fiske roof Committee asked if this would affect
remaining contingency funds
Conclusion of Contract and TAMS A November 7th completion date is
given in the contract with TAMS However , architect MacNicholas is on
the job daily "It will sift out in the next month or so " a committee
member stated A letter from Jim Whalen of Palmer and Dodge was read
out loud An unclosed communication loop between the committee and
Palmer & Dodge was noted
Payment of Invoices as recommended by Chartwell consultants VOTED
Meeting adjourned at 9 30 p m until January 12 1989 at 7 30 p m
Respectfully submitted,
Erna S Greene
Secretary to the committee