HomeMy WebLinkAbout1988-11-10-PBC-min.pdf TOWN OF LEXINGTON, MASSACHUSErib Gr a t
o
PERMANENT BUILDING COMIC nthJ
MINUTES OF MEETING
NOVEMBER 11, 1988 CotihacteaAo n/so At
( : `
ATTENDEES.
William Kennedy Marylou Tuart Brian Rowlands
Ted Edson Jun cranlon Ian Aitchison
John Kennedy Peter Johnson Dave Smith
Manny Coscia Jim Maclnnes
Review and acceptance of previous minutes postponed.
Progress Report - I Aitchison reported that the renovations at the
High School and Harrington and Estabrook will be practically complete
by the end of the year The Christmas vacation will be fully utilized
by the contractors to complete outstanding items. The only
outstanding work will be to the new library additions at Fiske and
Diamond schools.
B. Rowlands presented construction report, budget update and
contingency fund statement
Field House roof. I Aitchison reported that a meeting was held on
November 8, 1988 between, Chartwell, Bill Kennedy, Palmer & Dodge,
Briggs Associates, Morello Construction and respective attorneys. In
summary, Briggs volunteered to make the roof watertight and
leakproof Palmer & Dodge requested a formal offer and description of
their proposal so that the Town could review it. Briggs and Morello
will want to complete work as soon as possible.
The PBC were then addressed by TAMS Consultants in support of their
claim for extra fees.
Presentation frau TAMS. .Lee page 2
TOWN OF LEXINGTON, MASSACHUSEITIS Cr
PERMANENT BUILDING C06T4Iaahh J � t
MINUTES OF MEETING
NOVEMBER 11, 1988 Cli/io/&$1
PAGE 2 J
TANS personnel present:
Ron Axelrod, Barbara Manford, Jackie MONicolas, Chris Iwerks
R. Axelrod outlined.
- Major changes in scope
- Additional services
li � l - Increase in number of Contracts
C. Iwerks presented information on:
Program additions - incremental in nature - item by item went well
beyond the scope of the original services.
Example: Original entrance and auditorium program scope very vague in
program dont prepared by KLQ. C. Iwerks outlined what new scope
was in lobby and auditorium.
Lobby - has escalated from one sentence cdescriptien to what the lobby
design is currently
Field House - storage areas, basketball floor was added. New
lighting Weight roan expanded into larger scope. Generally, a lot
of the project developed extra scope with many small examples such as
these.
New libraries developed greater scope after discussion with school
librarians.
C. Iwerks admitted that the problem may have been that notification of
these extras to the PBC was late.
John Kennedy addressed question that TANS had assumed too much in
their design. C. Iwerks Leplied that it was a question of degree.
Barbara Manford diccsissed the following topics:
-Contract adminisU.dtien: degree of c :mplexity through design period
translated into extra contract AdminisLLati_on. Work has been so
implicated that Ruse input was necessary
-Program/Budget/Cost Estimating- assembling program within budget was
difficult. Cost estimating was an extra service. Value Managaient
was inLLuluced which was an extra service. Change orders demanded
more time. e.g F House (High School) heat, air quality problems,
etc. demanded more time. Accounting was made for each extra services.
- Packages: original included 3, there were actually 5.
- More time was requi*ed to do this work and to bid the documents.
TOWN OF LEXINGTON, MASSACHUSETTS —
PERMANENT BUILDING clviiirim two
MINUTES OF MEETING / Ch
NOVEMBER 11, 1988 lv�o/g$�
PAGE 3
- Timing* Decision to form packages was mutual. To obtain better
bidding situation and attract more bidders. If TAMS had thought that
extra packages would not be considered as an extra service they may
not have proceeded on this basis.
T Edson asked who decided on packages. HN s plied that it was a
collective decision.
R. Axelrod summarized that the PBC have recieved good value for money
all efforts were made to this end.
J Kennedy put forward the position of PBC was that extra packages
were made to enable TAMS to meet dpadlines. TAMS commented that
decisions were made by PBC. General dicrussion ensued on this item.
111 T Edson cemented that it was difficult to qualify that TANS had
addressed what KLQ had originally planned. HN suggested that KLQ
report was very vague.
J Kennedy questioned that if the original KLQ report needed
scjJJ La sa,.ILifg and they were jnid for such could they not have
projected that extra costs in dcclgn would follow.
D. Smith oammnted that scope and value of work did not increase.
R. Axelrod replied that many original items were in exterior paving
that were dropped for more canplicated design issues.
R. Axelrod cemented that the initial fee was low but surely not by
100%
T Edson cemented that them overrun in October 1987 of $162,000 has
increased to $600,000 today
R. Axelrod answered that it snowballed because of the extra contracts
and extra contract administration.
R. Axel road thanked the Committee for their consideration and offered
' any documentation for verification.
i
B. Kennedy reaffirmed that the bottom line of the project still is the
original amount allocated of $11,870,000
Meeting closed at 10:20 p.m.
B. Kennedy requested that the meeting went into executive session and
reminded the committee of the Guiclalines and stated his reasons for
doing so.
TOWN OF LEXINGTON, MASSACiUSEris Ca o `
tW
PERMANENT BUILDING COM Ilabh
MINUTES OF MEETING
NOVEMBER 11, 1988 Cs/ib/$gj
EXECUTIVE SESSION
PBC Committee Meeting.
B. Kennedy P Johnson J Scanlon
T Edson M. Touart I Aitchison
D. Smith J Kennedy B. Rowlands
The discussion of TAMS' request for extra fees commenced.
M. Touart commented that TANS went to far before claiming their
extras.
B. Kennedy explained that Chartwell had notified him of $160,000 of
extras from TAMS in late 1987 BK suggested that they be held off
until contracts were let successfully I Aitchison explained that
TANS were just realising that they were in a losing piupisition at
that time.
J Kennedy commented that we should be careful that we review our
exposure before proceeding
I. Aitchison commented that the Town were possibly exposed to the cost
of the extra packages.
B. Kennedy cemented that that there maybe some exposure because the
PBC did not release details of the design bids originally He was
Irl reminded that the PBC were operating under a axnpetitive bidding
situation and could not disnlose the information immediately
Discussion ensued on which direction to take to settle the problem.
Arbitration could result in an uncertain den sion dependent on
circumstances. Negotiation is the preferred way to go.
B. Kennedy suggested that the PBC offer $100,000 for settlement and
forte a settlement amount for TANS. Then proceed to bring the amounts
together
Discussion ensued on the anoint the PBC can afford to settle. Agreed
by unanimous vote to offer amount remaining of the contingency as per
Chartwell's calculation of approximately $116,000.
Meeting closed 11:00 p.m.
TOWN OF LEXINGTON MASSACHUSETT
PERMANENT BUILDING COMMITTEE
Addendum to Minutes of November 10 1988 meeting
The meeting began shortly after 7 30 p m with Edson presiding
Library progress was reported by Director Hilton Approval of
contractor ' s application No 3 for payment of $5 865 was VOTED
following approval of supervising architect John Davies and presentation
by Hilton
List of those present who constituted quorum is given below
�yyr'f'cUD