HomeMy WebLinkAbout1988-10-20-PBC-min.pdf TOWN OF LEXINGTON, MASSACHUSETTS
PERMANENT BUILDING COMMITTEE
Minutes of October 20 1988 committee meeting in Room G-15 , Town Office
Building, as approved January 12 , 1989
The meeting (that had been postponed from October 13 , the previous
Thursday) began about 7 45 p m Quorum for Cary Library business ,
scheduled first, was attained at 7 58
The following were present for the library only Ann Wallace, committee
member for the library and director Bob Hilton
RE Cary Library VOTED to approve payment requisition for $15,025 ,
mostly for cabinet work done but not yet installed
Present for school renovation matters for all or part of the meeting
were the following committee members William Kennedy (presiding) ,
Edson, Johnson, John Kennedy and Scanlon
School staff Anthony Capezza, Acting Assistant Principal , LHS
Michael Waring, Principal LHS
Paul Lombard, Acting Principal Bowman School
Ellen DeFantis , Principal Fiske School
David Horton, Principal Estabrook School
Paul Foley, Principal Harrington School
William Terris , Principal Bridge School
Eugene Sullivan, Principal Diamond Jr High
John Hibbard, Principal Clarke Jr High School
James Maclnnes , Assistant Superintendent
Town staff Manny Coscia, Clerk-of-the-works
TAMS Architects Ron Axelrod, Barbara Manford, Jackie MacNicholas ,
Chris Iwerks , and engineers from Amtech Lou
Picciuolo and Marek Orzechowski
List of items not yet done or still needed reviewed with each principal
and the architects and engineers
Estabrook library and computer room completion has been delayed due to a
finding a beam larger than expected This caused revisions in plans for
ductwork, etc Engineers , answering complaints about lack of heat in
the new tutorial rooms , noted that extra heat should be added because f
the rooms are at the end of the heating line
Harrington library millwork has been delayed until early December The
gym is now being used to store library furniture and this is upsetting
In addition, materials are piled up in the cafeteria and outside the
building, and the Fire Department is unhappy about that Elevator
delivery is also delayed
Clarke new clocks have been ordered, but delivery will take four to five
weeks Existing old clocks do not work with the new clocks The air
quality problem may go on the extra priority list
PBC Minutes 10/20/88 - p 2
Diamond principal complained that the new doors are very stiff and that
the "Portal" brand anodyzed aluminum is discolored Response New
closers are needed as the specs call for adjustable closers that were
not supplied Closers are to be replaced at contractor's expense
Lombard further commented that doors need to be handicap-accessible
Auditorium dimmers (on the previous contract) are still awaited
High School shortcomings were listed in a handout P A system and
insulation of field house roof were emphasized
An executive session was VOTED unanimously by roll call vote at 9 50 to
discuss sensitive negotiations regarding the field house roof and
payment of architects
Open session meeting resumed at 10 28 p m
APPROVAL VOTED to spend $11 ,000 for the P A system at Diamond
A $12 ,000 callback at the high school should be decided before the
contractors leave, it was noted an estimate of $10 ,000 has been
received by school personnel to install new air conditioner with roof
venting for the high school offices Committee will add it to pool of
additional work to be considered if funds remain
VOTED $5 ,000 additional allowance to J P Construction Co for HVAC and
miscellaneous metals at Fiske and Diamond
Meeting adjourned at 10 35 p m
Respectfully submitted,
A
Erna S Greene, Secretary
to the committee