HomeMy WebLinkAbout1988-06-09-PBC-min.pdf TOWN OF LEXINGTON MASSACHUSETTS
PERMANENT BUILDING COMMITTEE
Minutes of June 9 1988 Meeting in Room G-15, Town Office Building, as
approved January 12 , 1989
The meeting was called to order by Chairman Kennedy at 7 40 p m with
other committee members Edson Johnson John Kennedy Scanlon Smith and
Touart present (all) Also attending were staff Coscia and Maclnnes and
consultant Aitchison and Rowlands of Chartwell Acting high school
principal Wilson Acting Superintendent Zimmerman and School Committee
Chairman Newman arrived at 8 30 p m
Amendment and correction of April 14 1888 Minutes page 3 regarding
firm selected to study air quality at Clarke Middle School noted
(Approval and correction dates were also corrected\amended on page 1 )
Minutes of May 12 1988 were approved as extensively amended
Action Items as listed on agenda already taken care of by the
consultant
TAMS claim for additional funds Committee decided to request the
architects to state their case in a letter that the committee could
digest before taking action
Clarke Air Quality According to contractor Be'tLaneourt the system was
balanced and working when they finished their work However Certified
found elevated carbon dioxide levels due to insufficient circulation and
air exchange Maclnnes said that complaints of poor air quality have
existed since the school opened No money was allotted to this problem
because it was believed restoration of the original design would be
sufficient However the original design was deemed inadequate
Although new exhaust fans have been installed in guidance and laboratory
areas , air circulation is still insufficient Amtech, Certified
Chartwell and TAMS need to address this problem TAMS has the original
drawings
An Asbestos Management Plan has been proposed by Briggs for $27 500
The committee does not wish to include this in the project Maclnnes is
concerned with starting afresh, since Briggs price is lower than any
other would be and even lower their rough estimate given when they met
with the committee on this subject Maclnnes would like PBC funding,
since that would include 60 pe cent SBAB reimbursement Committee
members are not willing to commit funds until they know if any will be
left after covering all number one priorities
A prioritized list of items left out , along with their costs was
requested by committee members Kennedy
Review of contested Estabrook/Harrington Bid Package At last muting
it was decided to award the contract to Seaman Bratko rejecting
Morello Ten days later Morello filed a protest , alleging that the
rejection was capricious and arbitrary A hearing was held by the
Department of Labor and Industry (DOLT) on June 8 and both sides
presented their case The high school field house roof was brought into
the issue The PBC stated that its decision was based upon Morello s
PBC Minutes 6/9/88
lack of responsibility in dealing with complaints on leaks and upon
performance reference checks as reported to the committee Morello
tried to refute the committee ' s statements with newly obtained evidence
Iie also contended that the roof was improperly designed A speedy
decision was requested by the PBC Average decision time is two weeks
The committee mulled how best to handle the inevitable construction
delays Libraries are vital , visible and essential to school operation,
Maclnnes pointed out Estimated that 60 percent of the work would have
to be done during 'ummer vacation and that about 40 percent could be
done during the school year Libraries could be moved into gymnasiums
during September and October
Committee decided that if the decision is in our favor Seaman Bratko
should get the contract If the decision is in Morello ' s favor,
committee considered but decided not to reject all bids (This summer s
window would be missed entirely and next year would probably cost more
Furthermore , Morello could bid and get the job next year In any case
the scope of work would probably have to be reduced )
Clerk-of-the-Works Coscia assured that the job would be done correctly
whoever the contractor is VOTED to go with whatever contractor wins
the DOLI decision and go ahead (Noted that a sheet called "Protest
Update" is not a public document ) Acting Superintendent Zimmerman
emphasized that the school administration will need lead time for
publicizing if school opening is to be delayed
Memorandum from Maclnnes on School Issues was discussed particularly in
relation to need for a freight elevator in the high school and
substitution of wheelchair lift on stairs instead of handicapped
elevator VOTED to request TAMS to investigate double piston elevator
sustitution in C-house , where beam and ground water problems appeared to
be making elevator installation nearly impossible Committee also asked
if a vertical wheel chair liff could be considered Maclnnes noted that
among the subjects of a staff grievance were the gym lockers that had
been painted instead of replaced Principal Wilson was advised to see
Maclnnes or Coscia on problems with work being done at the high school
i
Progress Report on Bridge and Bowman schools is unchanged
Package 4 Fiske/Diamond filed subbids problems were repern.ed The only
HVAC bid was $70 000 above budget ($110 000 versus $175 000 bid) and no
bid was received on miscellaneous metals Chartwell to review this
General contractor for this package is 3 P Construction
High School Field House Roof is not being fixed by Morello due to
panding court case Morello has notified Briggs Morello has hired
their own engineer in an attempt to prove that original design was
deficient PBC-hired engineer Simpson Gumpertz and Heger will get up on
the roof next week
Payment of Accounts discussed in light of concern that subcontractors
are not being paid promptly and are complaining Edson asked if interim
4
PBC Minutes 6/9/88
certification is possible This is done only at the end
Subcontractors have been advised that they can request direct payment
VOTED to pay accounts as recommended by consultants Coscia questioned
payment of J P construction for concrete not yet poured However , the
contractor threatened to hold up the work if not paid as requested
Hioh School Field House HVAC Study and Design by Amtech at $1 000 VOTED
by the committee
Meeting adjourned at 9 59 p m Next meeting will be Thursday July 14
1988 at 7 30 p m
Respectfully submitted
Erna S Greene
Secretary to the Committee
{