HomeMy WebLinkAbout1987-03-12-PBC-min.pdf TOWN OF LEXINGTON, MASSACHUSETTS
PERMANENT BUILDING COMMITTEE
Minutes of March 12. 1987 meeting in Room G-15, Town Office
Building, as approved March 26, 1987
The meeting was called to order by Chairman Kennedy at 8.00 p m.
with other committee members Edson, Scanlon and Touart present;
John Kennedy arrived shortly. Also present were staff members
Maclnnes and Coscia, School Committee member Wik, Capital
F. penditures Committee representative Spector, Selectmen/liaison
McSweeney, Chartwell consultants Aitchison, Ralands and Heninger,
as well as local newspaper reporter Lisa Redmond
Minutes of February 12 1987 were accepted as amended and cor-
rected Agreed that copies of corrected minutes would not be
sent out unless changes were substantial (Copies of corrected
minutes will be sent out to Chairman, Town Manager and Maclnnes
Please correct typo not noted at meeting date is 1987, not 86)
Minutes of October 1 and 16, 1986 were accepted as submitted
Progress Report No. 5 review. Bowman and Bridge design work is
complete The new lockers and carpet at Bridge look very good
Bids for renovations are being reviewed
For the other schools TAMS has about 12 people at work About a
week 's slippage has occurred so far Aitchison does not consider
it serious. The engineers are keeping on schedule
Replacement screens at Diamond and the high school have been
inspected and are OK but not impressive for all the money
Committee members expressed a plea for installation of telephone
available to users of the Field House when school offices are
closed (one had been removed from the passageway due to vandal-
ism) Maclnnes said consideration would be given to installa-
tion of one in the Field House itself since that building is
locked when not in use and can be monitored
Bid Packages Schedule is now divided into three after further
negotiations with TAMS according to the Issue #5 timeline (2/12
revised 2/16)
Bid Package 1: Estabrook & Fiske
Bid Package 2: Harrington, Clarke (all ) Diamond and H.S
Bid Package 3. Balance of Estabrook (library) , Fiske
(library and storage) Harrington (library & elevator)
Diamond (library expansion and office alterations) , high
school (A-F houses, lockers, elevator, auditorium & add-ons)
Noted that the majority of code items except for elevators are in
the second package Maclnnes requested plan handouts in 8 1/2 x
1 9
PBC Minutes 3/12/87 p 2
11 inch size to explain building modifications to PTA groups etc
Budget Report No. 3 was reviewed with committee asking who
received copies of it They also questioned TAMS use of design
contingency funds for electrical work Aitchison responded that
theoretically these funds should be used There is also a change
order contingency for the construction phase Another query•
Why do numbers keep changing from month to month'' There appears
about $30 000 difference between appropriation and cost estimate
Also, committee members wondered why an item entitled 'KLQ under-
statement of overhead, " was still showing Rolands assured that
it will eventually disappear He also explained that a zero in
the "Original Budget Amount" column meant that it was not
originally estimated A zero in the "Current Budget Amount" F
column means that it was cut out All Lexan removal and replace-
ment is still included Some of the removed items will be done
under the school maintenance budget TAMS helped monitor these
decisions a month ago Rolands' financial report was commended
Schedules for roofing work are on time and work should begin
before vacation All bids are now in Asbestos survey will be
done by Briggs at the rate of one school per week, with Bowman
and Bridge first The work is scheduled to be done in the first
two-thirds of summer so that replacement can also be completed F
that vacation There is also a 30-day waiting period after bid
award Asbestos removal will probably done in summer, 1988.
Package 1 A week's design slip was noted
Package 2: Bids will close May 6; award to be May 13
Committee members questioned what is do-able, and also noted that
Cutler still has to finish the roof at Bowman
Meetino with TAMS Trio (Axelrod Iwerks. Manford) concerned
mostly plans for the Field House A storage area carved from the
main floor is to be added and the weight room is to be moved,
revising the locker area. The wood basketball floor is to be
replaced with a poured rubber one The weight room will have a
new rubber tiled floor The present weight room is to be conver-
ted to a team room
Committee members expressed concern about reduction in lockers
Response additional lockers will be added in other spaces such
as the team room. The weight room is to be accessible to women
Present plans do not call for roofing the storage area. If a
roof were to be added it would have to be designed. A long
discussion on the floor ensued The base will be concrete and
it will be an updated version of what is at Clarke, including
lines. Basketball people have commented favorably on this plan
Asbestos A February 23, 1987 proposal report revealed that
Briggs price is just about half of TAMS' A further proposal
2
PBC Minutes 3/12/87 p 3
from Briggs on March 6, 1987 gave a $21,850 price for combined
options 1 and 3 This is what Chartwell recommended, and the
committee VOTED to accept this proposal for options 1 and 3. (Bid
summary attached for those not at the meeting)
Bids for Bridoe/Bowman Constructioin were reported The base bid
was $789 447 and the budget estimate $795,445. Of the subbid
components, only the glazing was rejected but will be carried by
the general contractor Most subbids were close to estimates.
VOTED to accept the base bid with no alternates. An only-one
base bid situation was deplored by Messrs Kennedy. Aitchison
commented "that's the marketplace
High School Reroofing Bids were received seven strong, but
Hartford, the lowest, withdrew due to miscalculation The second
lowest was Morello who in the past has had problems getting
bonding Committee agreed to accept his bid, pending further
checks into his financial position performance and payment for
materials Chairman will be apprized of any problems.
Removal of Covina at Clarke filed subbid of NAACO (bond included)
was recommended Budget $26, 250; bid $24,500. VOTED to accept
A Management Workshop on Value Enoineerino is to be conducted by
Chartwell on May 27 to 28. Recommended to include about three
representatives each from TAMS Chartwell and the PBC/schools.
This will take place after preliminary drawings are completed
There was some discussion about furnishings and whether or not
added classrooms will contain blackboards. Committee members
commented that these should be assumed. Plans for spaces like
libraries already contain perimeter built-ins.
Approval of Bills as listed by Chartwell was VOTED (List
attached for those not present )
The meeting on plans for the high school has been rescheduled for
May 28 A May 5 meeting with the staff will precede it
Signoff on Bid Package 2 is scheduled for April 2, 1987
Clerk of the Works provision possibilities were discussed
For $14,000 Heydecker could provide the services of his person
Briggs could provide similarly. The town s buying this service
appeared to be the favored course
After scheduling meetings for March 26 and April 2 1987 at 7.30
p.m. , the meeting adjourned at 11 :00 p m. ��
E! i ! inmttee
Sad/ 4�
3