Loading...
HomeMy WebLinkAbout2023-12-06-PBC-minTOWN OF LEXINGTON Permanent Building Committee Permanent Members Jon Himmel, Co-Chairman, Charles Favazzo, Co-Chairman, Peter Johnson, Philip Coleman, Celis Brisbin, Elizabeth Giersbach, Frederick Merrill Police Station Members: Semoon Oh, Wendy Krum Associate Members: Curt Barrentine, Henrietta Mei PBC Minutes for the Zoom meeting held on: 12-6-23. Members Present: Phil Coleman, Charles Favazzo, Elizabeth Giersbach, Jon Himmel, Wendy Krum, Fred Merrill Others Present: Julie Hackett [School Superintendent], Cindy Arens, David Kanter, Bob Pressman, Todd Rhodes, Dan Voss,, Matilda Walker The PBC Meeting was called to order at 7:05 pm. The 6 December 2023 meeting was a self-examination of the PBC and its role on projects in general. The meeting was free flowing in nature and covered the following topics. · The Integrated Design Policy and its 2007 precursor were joint efforts by both the PBC and Sustainable Lexington. With every consecutive project starting with the Estabrook School, Lexington’s sustainable and resilient efforts have gotten more rigorous; all in anticipation of the high school project. The high school is the real test. · The PBC and Sustainable Lexington believe that the weeks following the initial data gathering are extremely important Feasibility Study weeks. SMMA has given an abstract calendar of meetings, but both the PBC and SL want a better idea of the inner workings from the consultant team of this crucial period. · “SMMA is being bombarded with stuff. How can we help to the design team be more effective?” · We all have experience managing very large, complex projects. “We need to find the sweet spot where we can be the most effective.” Areas where the PBC can add value include but are not limited to: o Site Logistics, o Procurement, o Cost Control and cost estimating [conceptual through Change Orders] o Schedule Control o Complexity of working in an occupied building o Capital projects politics in Town, o Constructability, o Bidding strategies, o Design and Design review, o Sustainability and resilience, o IDP implementation, o Lessons learned, o Master Planning, o Commissioning · The MSBA requires that Owner Project Managers (OPM) be retained on projects like our high school project. The MSBA also requires that the community have a School Building Committee (SBC); the PBC has functioned as the SBC on prior projects. Because the high school affects that entire town, it made sense to cast a wider net. Lexington’s SBC role on the high school is unclear – someone needs to draft up the SBC role and the roles of other committees, boards, and commissions. Who is responsible for what? · We need to have a discussion with staff about roles and responsibilities and revisit this conversation in February 2024. Motion to adjourn 9:05 pm, all approved.