HomeMy WebLinkAbout2017-01-12-PBC-min
Lexington Permanent Building Committee Meeting
Maria Hastings Elementary School Building Project
SBC MEETING MINUTES
DATE OF MEETING: January 12, 2017 at 7:00P.M. at 201 Bedford St, Lexington MA
PROJECT: Maria Hastings Elementary School Building Project
Dore & Whittier Project #MP16-0112
SUBJECT: School Building Committee Meeting (D&W#6)
ATTENDING: Jon Himmel Lexington PBC Chair
Andrew Clarke Lexington PBC
Curt Barrentine Lexington PBC
Richard Perry Lexington PBC
Charles Favazzo Lexington PBC
Philip Coleman Lexington PBC
Carl Oldenburg Lexington PBC
Pat Goddard Lexington DPF
Mark Barrett Lexington DPF
Judy Crocker School Committee Liaison
Trip Elmore DWMP
Rachel Milaschewski DWMP
Donna DiNisco DiNisco Design
----------------------------------------------------------------------------------------------------------------------
1.Approval of December 22, 2016 PBC/SBC Meeting Minutes PBC
Motion to approve and certify the December 22, 2016 meeting minutes as the official
certified record for the MSBA, by C. Oldenburg, 2 by D. Perry.
nd
Discussion:
Minor typo correction was cited: 1
st
A question was raised on the value of the Add/Reno option in the minutes; does it include the cost of
swing space? The OPM clarified that at the time of the meeting it was an unknown cost and was
NOT in the Add/Reno value. However, after the meeting, the OPM contacted Triumph Modulars and
estimated the cost of an 80,000 SF complex to cost over $5 million for a 20 month duration. It was
when added to the Add/Reno option it would push the cost higher than the new building option.
VOTE: Unanimous to approve the December 22, 2016 minutes
2.PSR Submission update
OPM and Designer reported that the Preliminary Schematic Report (PSR) had been submitted to the
MSBA on January 4 as planned. The MSBA responded that in their cursory review, all of the
th
required material was included in the submission. The project team reported that they had a Pre-
Facility Assessment Subcommittee (FAS) Conference Call with the MSBA and Lexington
representatives describing the FAS meeting which is scheduled for January 18 at 9:10 AM at the
th
MSBA offices.
T. Elmore explained that at the FAS meeting, the District describes their Educational Program and the
Designer reviews the preferred solution to the MSBA team and their selected Board Members. In the
call,
unusual issues.
3.Presentation of Construction Delivery Method options & Inspector General CM at Risk
Application process (See attached Construction Delivery Slides)
The OPM reviewed the slide presentation that had been included with the meeting information packet
to the SBC members. The committee held a lengthy discussion on the benefits and concerns with
both construction delivery methods, of which most of the topics discussed were captured in the
attached presentation slides.
After the committee asked specifically about other project experiences using both methods to the
OPM and Designer, both the OPM and the Designer recommended the CM at Risk Construction
delivery method for many of the control and safety reasons that exist in this process.
The Dept. of Public Facilities and Estabrook School Principal both agreed that the CM at Risk benefits
were evident from the Estabrook Building experience, especially in terms of a quality building and the
safety aspects of the construction process.
at Risk delivery method,
which could range from 3 to 10%. It was noted that s
highly speculative and tend to be more opinion than fact. However, the MSBA is eliminating the
additional 2 reimbursement points, and is commenting that there is a premium cost. The team
believes that we are still entitled to the additional 2 Reimbursement points if the decision is to use the
CM at
J. Himmel commented that there are a number of summary benefits related to chapter 149A, CM at
Risk construction delivery which should be included into this evenings notes:
Improved site safety and management of construction vehicles coming to and from the site.
Better control of the schedule ie better on time completion of the project
Occupancy of building 4 to 6 months earlier than 149 process (Design, Bid, Build)
Earlier use of the site after building construction is done
Preconstruction services
Subcontractor quality providing better project quality
Better fit with redistricting since there is a sense that re-districting is best done at the start of
the school year \[there is a greater chance that a September completion is more at risk with
the 149 process.
D. DiNisco indicated that her read was that the schools that are currently in the pipeline, such as
Hastings, are eligible for a CM reimbursement of 2% of eligible costs \[$312 per sf\].
The current construction is thought to be $450 per sf; Lexington would be on the hook for the $138
per square foot delta for the first 2%, or $303,600 if there are 110,000 sf in the project. Furthermore,
Lexington would be on the hook for the 149A process premium at a rate of
2
$450*1%*110000=$495,000 per each additional 1% over the 2% reimbursed by the
MSBA. Therefore, if the 149A premium is, say, 5%, Lexington would be on the hook for the $303,600
, plus $450/sf*3%*110000= $1,788,600.
The OPM discussed the CM at Risk Selection process, which starts with the selection of a
Construction delivery method. If CM at Risk is selected, the OPM would then need to begin the IG
Application for submission.
The remainder of the steps will take place in a sequence that gets the CM on board in approximately
3 months, or in case, by the beginning of April 2017. Following the selection of the
Construction Delivery Method, the PBC would then have to select the CM Selection Committee at the
next meeting if they voted to select CM at Risk.
Motion to use the CM at Risk Construction Delivery method on the Hastings elementary
School Project and have the OPM submit the IG Application, by C. Favazzo, 2 by P Coleman.
nd
VOTE:
Unanimous to approve the motion to use the CM at Risk Construction Delivery
Method and submit the IG application.
4.The Design Meeting update
D. DiNisco commented that the 1 design meeting that took place on the 11was primarily focused
stth
on the site aspects around the building. She reported that the tentative agendas for the next four
meetings were handed out in case any of the P/SBC members have interest in participating.
These meeting take place every other Wednesday at 7:30 AM at 201Bedford Street and PBC
Members are invited to contribute at these meetings.
5.Sustainable Building Process Update
C. Barrentine attended the Sustainability Stakeholders follow up meeting on January 9, 2017, and
summarized the additional detail generated in a spreadsheet, which was distributed and discussed.
(See the attached handout.)
Currently, the Stakeholders meetings are being scheduled to have a recommendation to the
Lexington Selectmen by March 1. This committee will be asked to vote their recommendations on
st
items in the next meeting. It was requested that the committee members be given a scoring sheet in
advance of the next PBC meeting which DPF agreed would be done.
6.Upcoming Meetings & Public Forums:
a.Scheduled meetings
i.TBD 2017 PBC Meeting
7.Motion to adjourn by D. Perry, 2 P Coleman. VOTE: Unanimous to approve.
nd
Hastings Project meeting ended at 9:35 PM
DORE AND WHITTIER MANAGEMENT PARTNERS, LLC
Trip Elmore
Dore & Whittier Management Partners
3
DecemberDecember
NovemberNovember
OctoberOctober
SeptemberSeptember
AugustAugust
2021 2021
JulyJuly
JuneJune
MayMay
CLOSEOUT
AprilApril
Abate/Demo/Site/LS/10 mon Com
MarchMarch
FebruaryFebruary
JanuaryJanuary
DecemberDecember
NovemberNovember
Abate/Demo/Site/LS/10 mon Com
OctoberOctober
CLOSEOUT
SeptemberSeptember
AugustAugust
2020 2020
JulyJuly
JuneJune
MayMay
AprilApril
MarchMarch
Building Construction + 1 month move-in
FebruaryFebruary
JanuaryJanuary
DecemberDecember
NovemberNovember
OctoberOctober
Building Construction + 1 month move-in
SeptemberSeptember
Road,utilities
AugustAugust
2019 2019
JulyJuly
JuneJune
MayMay
AprilApril
CONSTRUCTION
STRUCT STEEL
MarchMarch
Site/Found
FebruaryFebruary
JanuaryJanuary
ERP - road,site,util, SS, Found
DecemberDecember
EST+SUBMITEST+SUBMIT
NovemberNovember
PREQUAL & BIDPREQUAL & BID
OctoberOctober
CONSTRUCTION
SeptemberSeptember
AugustAugust
2018 2018
JulyJuly
CONSTRUCTION DOCSCONSTRUCTION DOCS
JuneJune
MayMay
AprilApril
EST+SUBMITEST+SUBMIT
MarchMarch
FebruaryFebruary
JanuaryJanuary
DecemberDecember
COMMISSIONINGCOMMISSIONING
NovemberNovember
DESIGN DOCSDESIGN DOCS
OctoberOctober
SeptemberSeptember
AugustAugust
2017 2017
JulyJuly
JuneJune
MayMay
SCHEMATICSCHEMATIC
CM SELECTIONCM SELECTION
AprilApril
MarchMarch
FebruaryFebruary
Hastings Elementary School Building Project - Timelines CM@Risk vs. DBB
JanuaryJanuary
FEASIBILITYFEASIBILITY
DecemberDecember
NovemberNovember
2016 2016
OctoberOctober
SeptemberSeptember
AugustAugust
JulyJuly
JuneJune
TBDTBDTBDTBDTBDTBDTBDTBD
Duration in MonthsDuration in Months
1.51.5
1414
23411545221455692341154522145569
Design, Bid, Build Hastings Schedule
Abate/Demo/Site Improve/Landscaping/10 mon CommissionAbate/Demo/Site Improve/Landscaping/10 mon Commission
Structural Steel - 1 month buy/2 mon fab&del/2 mon erect
Early release - road, site, utilities, Struct Steel, Foundations
CM@Risk Hastings Schedule
MSBA Issues Project Funding Agreement ($$ committed)MSBA Issues Project Funding Agreement ($$ committed)
MSBA Board Approval of Schematic Design - 8/23/17MSBA Board Approval of Schematic Design - 8/23/17
MSBA Approve to proceed into Schematic - 2/15/17MSBA Approve to proceed into Schematic - 2/15/17
MSBA Preliminary Design Program SubmissionMSBA Preliminary Design Program Submission
MSBA Schematic Design Submission - 6/29/17MSBA Schematic Design Submission - 6/29/17
MSBA Preferred Schematic Report - 1/4/17MSBA Preferred Schematic Report - 1/4/17
Building Construction + 1 month move-inBuilding Construction + 1 month move-in
Early release - road, site, utilities
Prequalify and Bid DocumentsPrequalify and Bid Documents
CM at Risk Selection ProcessCM at Risk Selection Process
Site Clear and Foundations
Final Closeout with MSBAFinal Closeout with MSBA
Construction DocumentsConstruction Documents
Project CommissioningProject Commissioning
Construction OverviewConstruction Overview
Design DevelopmentDesign Development
Schematic DesignSchematic Design
Project CompleteProject Complete
Select ArchitectSelect Architect
Town ApprovalTown Approval
FeasibilityFeasibility
Hire OPMHire OPM