HomeMy WebLinkAbout2023-06-08-PBC-minTOWN OF LEXINGTON
Permanent Building Committee
Permanent Members
Jon Himmel, Co-Chairman, Charles Favazzo, Co-Chairman,
Peter Johnson, Philip Coleman, Celis Brisbin, Elizabeth Giersbach, Frederick Merrill
Police Station Members: Semoon Oh, Wendy Krum
Associate Members: Curt Barrentine, Henrietta Mei
PBC Minutes for the meeting held on: 6-8-23
Meeting was held remotely via Zoom
Members Present:
Jon Himmel, Elizabeth Giersbach, Semoon Oh, Wendy Krum, Henrietta Mei, Charles Favazzo
Others Present:
Mark Barrett, David Kanter, Steve Brown, Mark Sandeen, Mike Cronin, Mike McLean, , Henrietta Mei, Dan Voss,
Liza Bouton
The PBC Meeting was called to order at 5:00 pm.
Meeting Minutes
DPF status update on Westview Cemetery Building
Mark Barrett reported that the project was moving along. Interior wall board complete with prime & First coat are
complete. OH Doors are Complete. Plywood sheathing in the garage is 90%.
Final site work is ongoing.
Permanent Power scheduled for Tuesday 6/13/23 and equipment start up to follow
Ceiling grid and some ceiling tile cuts are in place.
Roofing edge metal remains.
Flooring and plumbing & Electrical finish over next two weeks.
DPF status update on Police Station Construction
Steve Brown provided an update on the Police Station construction. He reported that the slab on deck was poured, half
of the slab on grade was poured, and the remainder should be completed by next week. There was a lot of work done on
the sub surface infiltration chambers in three locations on site. In June, the road excavation and water lines will be
installed on Mass Avenue. The roof insulation and panels on the flat and pitched areas will be finished to prep for the final
roofing material. The installation of studs and exterior wall sheathing will be finished. There will be work on interior
concrete and stud walls. The interior underground electrical, plumbing, and SOG concrete will be completed. The
exterior waterproofing is also projected to be finished in June. Steve Brown shared photographs of the work. There will
likely be temporary window protection as interior work continues. The official milestone date for weather -tight was
sometime in October. It was reported that the construction was currently on schedule. Although, it was noted that the
switchgear delivery and the transformer confirmation by the utility are the long lead items with potential schedule impact,
so these will be monitored closely.
In answer to a question it was stated that the electric transformers will go back by the communications pole.
Mike Cronin reported that there was main water line damage last week. When the clamp was placed on the wet
tap, it fractured a pipe. A T-tap was put instead. DPW also had a challenge with the gate valves. Once those were
fixed, the water line was once again operational. It was reported that it will not be the last time that excavation will
occur in the street.
Solar Canopy update
Since last meeting there has been an abutter meeting on 5-30-23, an HDC hearing 6-1-23 and an SBC meeting
scheduled for 6-12-23.
At each meeting the group was asked to express a preference for which design they most supported.
The Power point presented outlined 4 options. Option 1; Option 1 Alternate; Option2; Option2 Alternate
Option 1 is the original “table top” design over the rear parking lot with a leg to Mass ave.
Option 1 Alternate is the same as option1 except a row of solar panels is remove down the center of the rear
canopy to allow natural light to the parking area.
Option 2 has the more “Organic” structure that was preferred by abutters which had the rear canopy in two pieces
(one over each strip of parking) and no canopy over the drive aisle. There is a Mass ave leg and a raised section
where it meets the rear parking lot canopy. Because Option 2 did not have canopy over the drive aisle its overall
height could be reduced to a clearance of 12’-9”.
Option 2 Alternate was a duplicate of Option 2 except a raised section of the canopy was added at the south side
of the Fletcher Ave entrance to balance the raised section at the opposite end of this same section.
Michael Cronin reported that the original design (Option 1) and the new organic-feel design (option 2) were the
designs that had the most appeal to the groups. Everyone had agreed to include the Mass Ave leg as the framing
for Fletcher Field from the Police Station, which was incorporated into Jeff's proposal.
Michael Cronin reported that both options were presented to the HDC last week, and they were leaning toward
option one, which included the Mass Ave leg, but they were resistant to vote and wanted more feedback. The two
options will be discussed at the upcoming Monday Select Board meeting. In response to a question It was clarified
that the Mass Ave leg was now being incorporated into both designs.
Michael Cronin discussed that there were conversations about how Fletcher Field did not want to feel part of the
police station and about framing the park. Jon Himmel discussed that the liaison for the HDC feels that the façade
of the building was worked on a lot and should be visible.
It was asked if the options could be shown from the same angle to get the same perspective. Michael Cronin
stated that he would contact Jeff to see if he could modify option 1 to view the same angle.
It is expected that asphalt work would occur in October. It was stated that this project had two types of asphalt:
porous and non-porous.
Concerns were raised about the Select Board making a decision without a dollar amount for the work. It was also
discussed that there was a discussion with the Select Board that the net zero calculation was for the building, and
not building + vehicle charging. There is however support to incorporate the Mass Ave leg even if it exceeds the
net zero building requirements.
Michael Cronin stated he would try to have the math conversion for kilowatts for the solar canopy options for the
Monday meeting. Adding a plan at the bottom of each option was suggested to clarify and add a top-down view.
Michael Cronin invited everyone to join the discussion with the Select Board on June 19th.
Update on LHS Project Status
Michael Cronin provided an update on the LHS status. He reported that the OPM selection of Dore & Whittier was
validated and affirmed by the MSBA on Monday, and the designer selection process began. A draft RFS was
submitted to the MSBA because they operate on a first-come, first-serve basis. An A/E walkthrough of the existing
high school will be on July 12th; A/E submissions are due August 16th. A designer should be affirmed in early
October and the Feasibility study phase will commence and proceed for up to 24 months.
Urgent Business
Motion to adjourn 6:41 pm, all approved.