HomeMy WebLinkAbout2023-05-11-PBC-min 5,r��R"'"� TOWN OF LEXINGTON
Permanent Building Committee
Permanent Members
Jon Himmel, Co-Chairman, Charles Favazzo, Co-Chairman,
IN(!T
Peter Johnson,Philip Coleman, Cells Brisbin, Elizabeth Giersbach, Frederick Merrill
Police Station Members: Semoon Oh, Wendy Krum
Associate Members: Curt Barrentine, Henrietta Mei
PBC Minutes for the meeting held on: 5-11-23
Meeting was held remotely via Zoom
Members Present:
Jon Himmel, Charles Favazzo, Celis Brisbin, Elizabeth Giersbach, Henrietta Mei
Others Present:
Mike Cronin, Dave Kanter, Mike McLean, Joel Pressman, Joe Pato, Todd Rhodes, Mark Sandeen, Dave
Pinnsenault, Melissa Battite, Kathleen Lenihan, Mark Barrett, Steve Brown
The PBC Meeting was called to order at 5:00 pm
Meeting Minutes
The minutes for the 3-9-23, 3-21-23, and 4-13-23 meetings were distributed earlier in the week. There were edits and
no further comments received. The minutes were updated and sent out again by Mark Barrett.
Charles Favazzo made a motion to approve the amended 3-9-23 meeting minutes, Jon Himmel seconded, and the
motion was passed unanimously.
Charles Favazzo made a motion to approve the 3-21-23 meeting minutes, Jon Himmel seconded, and the motion was
passed unanimously.
Charles Favazzo made a motion to approve the amended 4-13-23 meeting minutes, Elizabeth Giersbach seconded,
and the motion was passed unanimously.
DPF status update on Westview Cemetery Building
Mark Barrett provided an update on the Westview Cemetery project. He stated that the installation of wallboard began,
in the administrative wing with the expectation that it all would be completed next week. The primer and first coat of pai it
would follow. The overhead doors were arriving on May 11th and the installation was planned to begin on Monday, May
15th. The exterior panels and trim installation was continuing. It was reported that the site work will resume next week.
The remaining two exterior doors and windows were being delivered on May 11th, and the installation would begin the
week of May 15th. It was reported they were waiting on Eversource for the final connection to the transformer for prima
power. Mark Barrett presented pictures and stated it was anticipated that the project would be complete end of June or
early July. It was clarified that the landscape planting was removed. DPW staff would likely manage that work when the
time was right. The present contractor was responsible for loam and seed. It was reported that there were no electrical
charging stations planned for at this time. It was stated the building itself was solar-ready, and once the building was
complete and there was funding available a rooftop solar system would be placed.
DPF status update on Police Station Construction
Steve Brown provided an update on the Police Station construction. He reported that in April, final welded connections
On the structural steel frame were completed April also saw rebar placement, mesh, and concrete placement at the
2nd-floor slab on the deck; the north-side stormwater infiltration system was completed; the prefabricated steel roof
trusses were installed at the South section. In May, the plans included finishing installing decking on the roof trusses,
finishing interior underground utilities and backfill & pouring a concrete slab on grade, installation of additional
stormwater infiltration systems, and continuing with exterior framing. On June 8th, it was anticipated to start interior
construction.
The roofing was anticipated to be done at the end of July. Steve Brown shared updated pictures of the construction
activity.
Solar Canopy update
On Tuesday May 9' there was a meeting with the police station neighbors to discuss the solar canopy designs and
received continued feedback. The overall goal to maintain as close to net zero as possible was also discussed. There
is a scheduled HDC hearing on 6-1 at which the original design at a new lower height and the new options develop
from abutter input sessions would be presented. It was hoped to have another meeting on May 30' with the abutters
prior to the June 11 HDC meeting.
Update on LHS Project Status
Mark Barrett reported that March 29'was the release of the OPM request for services. Responses were due on
April 20th, and there were seven proposals received. The committee for OPM selection shortlisted the proposals to four
firms, that were interviewed on May 2nd. The committee then met on May 3rd to finalize the rankings after having held
the interviews, and a full school building committee meeting was held on May 4' to discuss the final rankings and
support a decision. The selection packet was submitted to MSBA on May 10th. There will be a MSBA OPM meeting on
June 5th, where the MSBA will vote to support (or not) the Towns selection of an OPM.
It was asked if the designer selection process was similar. It was stated that with the Designer selection the Town does
not rank the firms and they have only three representatives on a 12 member selection panel made up of MSBA
representatives.
Elizabeth Giersbach stated she spoke with Nancy, Charlie, and Barbara, and they raised questions about the feasibility,
study and site analysis. Mike Cronin stated that the feasibility study would not be moved forward without input from
residents. It was stated that it was expected Dore &Wittier would be on board on June 5th
Jon Himmel stated it would be useful to have a discussion at the next meeting on how Wittier thought the outreach
would go.
Urgent Business
Integrated Design Policy
Todd Rhodes stated that the Integrated Design Policy was tentatively put on the Select Board agenda for June 5th.
It was discussed that there would likely be sequential meetings with the Select Board and the School Board, Joe Pato
Will however reach out and see if the School Board would be able to join the Select Board on June 5th. Todd Rhodes
and Jon Himmel would coordinate the final presentation to the boards.
Munroe Center for the Arts (MCAS
An Inquiry was made about the MCA project.
It was reported that there had been conversations with the MCA individuals and Facilities staff. DPF reported that
some of the project soft costs were coming from MCA own budget, however DPF was still working to define all budget
parameters and will be developing a combined budget sheet to examine what would be coming out of the separate
budgets. The Annual Town Meeting appropriation was $6.6 million, and the last construction cost estimate, as
previously discussed was at $8.8 million. The architectural process as DPF understands it is on hold will full project
budget accounting was developed and a full Value Engineering phase was completed.
Motion to adjourn, approved.
Next meeting 6/8/23