HomeMy WebLinkAbout2022-03-24-REC-min 13S 75 TOWN OF LEXINGTON 2022 01Juin, 12A3 pin't
Permanent Building Committee TOWN CLERK
5 Permanent Members
LEXINGTON MA
< "PRIL1V Jon Himmel Co-Chairman Charles Favazzo Co-Chairman
EX1N61 > > > >
Peter Johnson,Philip Coleman, Cells Brisbin, Elizabeth Giersbach, Frederick Merrill
Police Station Members: Semoon Oh, Wendy Krum
Associate Members: Curt Barrentine,Henrietta Mei
PBC Minutes for the meeting held on: 03-24-2022
Meeting was held remotely via Zoom
Members Present:
Jon Himmel, Charles Favazzo, Celis Brisbin, Elizabeth Giersbach, Wendy Krum, Henrietta Mei
The Meeting was called to order at 5:00pm.
There was brief discussion about the meeting minutes that had been sent out for review for 03 February and
24 February 2022. All parties had not had the opportunity to complete their review so these minutes will be
taken up at the next meeting.
The primary agenda item was to review the Value Engineering list for the Police Station project. It was decided
to discuss each item as the review went thru the last and forego an initial overview, since the items were
briefly discussed at the last meeting.
There are 21 items on the V.E. List and each item was discussed in some detail. The final recommendation of
the PBC was identified on the VE list, attached, with a:
Red Square— "PBC does not recommend adoption of this item"
Yellow square —"PBC Not offering an opinion"
Green Square —"PBC Recommends pursuing this potential savings"
The VE List also shows that the Department of Public Facilities and the Police Department had previously
reviewed the list and took similar action on each item, for their recommendations.
For each item on the VE list, the PBC added a comment, where they felt appropriate, regarding their
recommendation.
At the bottom of the VE list is a summation of the possible project cost value that could be realized by
following the recommendations made on the list.
All PBC recommendations and comments are noted on the attached VE List, however there were 5 VE items
that the PBC made an additional recommendation for, as noted below.
#4 Rear Dormer— PBC Recommended that the Rear Dormer could be looked at as an additive Bid Alternate.
#7 High Density Storage — PBC recommends moving the High-Density storage to the FF&E phase but to keep
the appropriate slab depressions in the building to allow for flush install.
#9 Reduce Generator to Critical loads only - PBC did not support reducing the load coverage but did suggest
that an evaluation be done to determine if having two, smaller generators provided an advantage.
#16 Move Window blinds to FF&E— PBC supported elimination of any electrically powered blinds and have
manual blinds only under the FF&E phase.
#18 Change Terrazzo floor to porcelain tile— PBC added a Recommendation to consider Terrazzo tile as the
project will retain the durability of the material but should realize a cost savings over the poured Terrazzo floor.
An update on the status of the proposed High School project was requested.
DPF Director, gave the following update.
Ajoint mtg between School Committee (SC) and Select Board (SB) was held on or about March 9, 2022 to
discuss the potential High School Project.
There is a Special Town Meeting scheduled to be held on 4/11/22 to request approximately $1.825 million
dollars for a Lexington High School Feasibility study.
The Town had been notified that Lexington was invited into the Eligibility Period by the MSBA for the High
School, however, the invitation will not be official, and no work can begin, until June 1, 2022. From that date
on the Town will have 270 calendar days to complete the required tasks in the Eligibility period.
At the joint SC /SB mtg the composition of the future School Building Committee (SBC) was discussed. The
MSBA suggested qualifications of the future SBC members and it was suggested that they would not
necessarily use the entire PBC committee as the base membership of the SBC, as had been done in the Past.
This discussion was reported as a work in progress.
It was noted that the Town's Integrated Design Policy had requirements that should be considered when the
discussion resumes on how the future SBC is formed.
Meeting Adjourned 8 PM.
Lexington Police Facility V.E. Review
Value Engineering Item/Scope Possible Cost Recmnd Comments
Reccomended
Defer
Not Reccomended
v
0 0° a N
Potential Savings
1 Deduct Social Services office fit-out $105,000
Exposed framing on inside of offices,no floor or wall Architect This Space was added to the design to reflect input received from the community
finishes,no ceilings. Heat,Ventilation,and electricity converstation. Defering this work will see increased costs at the time it is
brought to area but not fitted to offices. performed.
DPF Defering the balance of Construction will only increase costs.
Police The Community expressed a desire for this space.
PBC
SB
2 Deduct De-EscalationTraining Fit-out $50,000
Exposed framing on inside of space,no floor or wall Architect This Space was added to the design to reflect input received from the community
finishes,no ceilings. Heat,Ventilation,and electricity Iconverstation. Defering this work will see increased costs at the time it is
brought to area but not fitted to room. performed.
DPF
Police The Community expressed a desire for this space.
PBC
SB
3 Deduct Glass&Millwork partitions $75,000
Replace with solid drywall partitions and HM doors Architect Was in response to Community input for visibility and provides transparency to
Administrative staff.
DPF
Police The Community expressed a desire for this transparency
PBC
SB
4 Remove dormer at rear of building $43,000
Architect
Provides natural Light in to Locker room areas and reduces need for artificial light.
DPF
Police The increased natural light will provide a healthier workspace for staff.
PBC
SB
5 Change Brown Stone to Cast Stone $116,150
Change Brownstone Base at Fa4ade ad at door Architect The Brownstone was chosen to provide a natural base to the Police building.The
surrounds to Cast Stone Town office building is brick to grade,while the Cary Building has a granite base
at the front,so it was thought that the brownstone was a good tone to align with
the Town Office building materials.
DPF May impact HDC approvals
Police
PBC
SB
6 Fire Supression at IT and Evidence Rooms $160,000
Change the Clean Agent Supression in these areas to Architect The use of Clean Agent is the Best application for use in the Evidence and
traditional water Network rooms. A completely wet system is not reccomended,and a pre-action
system adds a human component that interupts the fail safe system.
DPF Clean agent Fire Supression application in these rooms seems appropriate.
Police PD is concerned about the preservation of both equipment and Evidence against
leaks,accidental activation,etc.
PBC
SB
7 High Density Storage $225,000 Eliminates High Density systems entirely with no replacements
$175,000 Changes High Density systems to standard files and metal shelving
$75,000 Moves Hig Density Systems to FF&E(potential Savings)
Architect The High Density system was included in the Bid Process in an attempt to
streamline installation.This equipment is routinely provided under the
Furniture/equipment process at which time the scope can be adjusted to the
current budget.Some savings likely.
DPF DPF supports moving to FF&E.We have successfully taken this approach on other
projects
Police PD supports providing designing the structure to carry the required loads, but
moving the Item to the equipment budget.The use of High Density systems in
both areas will drastically improve theDepts ability to properly maintain both
evidence and Records.
PBC
SB
8 Parking Garage/Vehicle Maintenance notdetermined
remove exterior walls and leave as open air parking Architect This deletion would eliminate the maintenance bays and leave program needs
with upper floor of building extending over"outdoor" unaddressed. If these walls are eliminated it would alter the make up of
parking remaining walls to accommodate changes in thermal needs.
DPF Removal of the garage walls would change the overall image/design of the
building and impact HDC approval Process,considerable re-design would likely be
required.
Police Removal of the garage area is not reccomened by the user.
PBC
SB
9 Emerg.Generator to Critical loads only $200,000
Architect 80%of the building would not be supported during power loss.The Police
station is a critical operations facility and needs power in all areas to respond to
Community needs in an emergency.The new Fire station is also an Essential
Facility and has 100%emergency power.
DPF DPF defers to the Police Departments Operational Needs
Police The Dept,needs to be fully operational,especially if there are crisis situations,
such as power loss.
PBC
SB
10 Reduce Landscaping by 15% $36,000
Architect This represents a flat reduction of undefined scope to support a value engineering
process.
DPF
Police
PBC
SB
11 Interior lighting changes&reductions $100,000
Architect Based upon Fixture cost estimates,Light level analysis and energy modeling,
adjustments can be made to fixture type and qty without impact to the user
DPF
Police
PBC
SB
12 Reduce AV Scope $100,000
Architect ]Reductions can be made,based upon evaluation of Cost Estimate assumptions
and a final AV coordination mtg.,without effec ting Building user performance.
DPF
Police
PBC
SB
13 Streetscape coordination $150,000
Architect Funds were carried in the estimate for an unknown level of coordination with the
Streetscape project.A coordination meeting has defined project needs.
DPF
Police
PBC
SB
14 Simplify ceiling design in meeting rooms $50,000
Architect 7FProvide alternate ceiling layouts and details to provide a more business interior
and simply the design and cost.
DPF DPF supports the simplified design for ease in access and maintenance
Police
PBC
SB
15 Reduce Locker quantity&type $30,000 IIIIIIIIIIIIIIIIIIIII
Architect Reduce Uniformed Officer Locker quantity and replace with support staff lockers.
DPF
Police The PD feels that they can still meet growth expectations,no changes in Female
or Gender Nuetral locker room
PBC
SB
16 Omit window blinds in all windows $40,000 Eliminate all window blinds
$8,000 Move Window Blinds to FFE for Potential Savings
Architect Could be provided under Equipment/Furniture process with possible savings
DPF DPF supports moving to FFE-We have done this before.
Police PD feels that window blinds are a necessary treatment for windows.
PBC
SB
17 Reduce Ballistic Wall protection $50,000
Architect The overall scope was reviewed along with usage expactations of the spaces and
the savings opportunity was dicovered.
DPF
Police The Police Dept supports the re-evaluated assessment levels and is comfortable in
reducing the scope of the ballistic wall panels
PBC
SB
18 Change lobby Terrazo Floor 10,000/ 20,000
Porcelain Tile/Vinyl Tile Architect The Terrazo floor product provides the most durable long term flooring solution.
The Public Lobby will see tremendous traffic and the Terrazo floor will provide the
DPF most maintenance free and best longevity of any option.
Police PD defers to DPF reccomendation
PBC
SB
19 Change Curtainwall to storefront system $25,000 IIIIIIIIIIIIIIIIIIIII
The Curtainwall system provides more enhanced thermal protection and supports
Change to a lower performing Curtainwall system Architect the Towns Energy Directives.
DPF DPF does not recommend
Police
PBC
SB
20 Reduction of pavement $5,000
If pushing back front parking to improve green space
there is a net reduction in paving Architect Simply a by product of reducing four parking spaces
DPF
Police
PBC
SB
21 Storm water Management $200,000 IIIIIIIIIIIIIIIIIIIII
Omit underground infiltration chambers and provide Switching to storm water retention ponds will greatly reduce the useable green
retention pomds Architect space
Changing the design of the systems would require a redesign of the stormwater
DPF systems and push the overall project schedule.
Police
PBC
SB