HomeMy WebLinkAbout2015-09-28-GCC-min
Greenways Corridor Committee
September 28, 2015
Room 125, Hadley DPW Building
Lexington, Massachusetts
Members Present: Alex Dohan, Peggy Enders, Eileen Entin, Don Grant, Bob
Hausslein, Keith Ohmart, Mike Tabaczynski,
Other Attendees: Susan Kenyon
Votes
: Minutes approved: 8/31/2015
Reports/Updates
:
• Susan Kenyon is considering the invitation to join the GCC.
• The GCC will sponsor the application to the Conservation Commission for a bench
in Rick Abrams’memory to be placed in Dunback Meadow. The GCC sponsorship
saves the application fee to the Town since the GCC is a Town committee.
• The MAPC visit is scheduled for 8:45am in the Selectmen’s Meeting Room on Oc-
tober 8. There will be a half hour or so of presentation, including a short presenta-
tion of the development of the ACROSS concept and routes by Keith, followed by
a walk on a segment of Route A, through lLowervVine bBrook, Chiesa Farm and
Parker Meadow.
• Conflict of Interest meeting - Peggy was unable to attend. (You probably got an
email with the paperwork, and must, as a committee member, complete an online
course every two years.)
• Brochure distribution - we have about 1000 left, which means we’ve distributed
11,000 brochures in the past year. It cost us about $1,700.00 to print the 12,000. It
would only be a small dollar amount more to order 15,000 next time. It probably
does not make sense to order more now. We should wait until the new routes are
marked. We discussed creating a QR code to be made into stickers to place on
the brochure holders so people could access the online maps with a smartphone.
Bob will look into QR code stickers. We will leave the lucite brochure boxes up for
the winter even though they are empty. We need to think about how often to up-
date the printed brochure. The website can be updated easily as necessary. Park-
ing areas should be marked on the maps.
• The website revision is happening, but there are lots of steps.
• There is a residential development going in on Lincoln Street near the Cambridge
Reservoir. This could be a good opportunity for developing trails and a parking
area.
• Shire Trail - there will be more information available by the October meeting.
Ongoing Business
:
• Route E/F work is ongoing, communicating with Conservation and Recreation as
necessary, Peggy has been talking with Karen Mullins and Karen Simmons, re-
spectively. The Martingale Rd/Freemont St intersection needs a post where the
trail goes in at 2 Martingale. Dig Save should be called for post installation. About
a dozen posts will be needed between Meagherville and Poor Farm. Also, leaves
will need to be cleared off the steep part of the trail where the trail exits from the
Freemont St Playground. This Bikeway-to-Battle Road connection does not require
going before the Selectmen. We can update them later on. We should let Karen
Mullins know, as a courtesy, that we will be going through the Poplar St play area.
We also need to be in touch with the National Park about putting in an “End of
Route”post. We discussed getting stickers to say END that will go on the existing
markers when necessary. Eileen is still working on the route plan for the path go-
ing from the Lincoln Park section of ACROSS Route B to the Poor Farm exten-
sionand Meagherville, she will confer with Dave Williams about the portion of the
route that goes through Lincoln Park’help. John Livsey, Dave Cannon and Dave
Pinsonneault should all be kept in the loop as well.
• We may need to re-post Willards’Woods when the stream daylighting project is
finished.
New Business:
none at this time
Next Meeting
: October 26, 2015, 4:30-6:00pm, DPW Training Room
Future meeting dates: November 23, December 14
October Agenda Items:
-
Certification of ACROSS Lexington Completion program update - Gil Benghiat
-
ACROSS Lexington Friends Group - Keith
-
Easement/Town Access Project
-
Expenditure of FY16 monies - Keith
Respectfully Submitted by
Alexandra Dohan, Secretary