HomeMy WebLinkAbout2009-07-14-PBC-min
TOWN OF LEXINGTON
Department of Public Facilities
Patrick W. Goddard, CFM Tel: (781) 861-2580 x201
Director of Public Facilities Fax: (781) 863-5829
14 July 2009
Meeting Minutes
Lexington Permanent Building Committee (PBC)
nd
Location: 201 Bedford Street, 2 Flr. Conference Room
Date & Time: 14 July 2009, 5:00PM
Attendees
: Jon Himmel, Chairman, PBC
Eric Brown, PBC
Peter Johnson, PBC
Dick Perry, PBC
Bill Hadley, DPW
Pat Goddard, DPF
Mark W. Barrett, DPF
Laurie Lucibello, DPF
Mike Lawrence, HKT Architects
Members not present:
Carl Oldenburg, PBC
Bill Kennedy, PBC
Abbreviations that may be used in this document:
PBC – Lexington Permanent Building Committee
DPF – Lexington Department of Public Facilities
DPW – Lexington Department of Public Works
HKT – HKT Architects – Architects of Record, Lexington DPW Facility
CTA – CTA Construction Co., Inc.
SB – Sebesta Bloomberg
WS – Weston & Sampson
1.0 GENERAL BUSINESS
1.1 Minutes
7/14/09
19 May 2009and 24 June 2009
To Approve the Meeting Minutes, as amended from
Motion: Peter Johnson 2nd: Dick Perry Voted: Unanimous
146 MAPLE STREET • LEXINGTON, MASSACHUSETTS 02420
PBC Meeting Minutes
14 July 2009 Meeting
1.2 Monthly Bills
6/24/09
DPF presented the May 2009 Bills for payment by the Town for PBC approval. The invoices included HKT
architects monthly invoice, UTS testing, and legal fees, a copy of approved invoices is on file. The PBC
Approved the Monthly Bills for Payment. Invoices approved by signature.
7/14/09
DPF presented the June 2009 Bills for payment by the Town for PBC approval. The invoices included HKT
architects monthly invoice, UTS testing, and legal fees, a copy of approved invoices is on file. The PBC
Approved the Monthly Bills for Payment. Invoices approved by signature.
2.0 PUBLIC WORKS & FACILITIES BUILDING PROJECT
2.01 Contractor Monthly Requisition
06/24/09
Application for Payment # 20 to the General Contractor was reviewed. The Clerk of the Works, The Architect
and the Town’s Project Manager has previously reviewed the Requisition. Many items were discussed and
evaluated prior to acceptance.
Motion: To approve Application for Payment #20 in the amount of $402,458.00
Motion: Eric Brown 2nd: Dick Perry Vote: Unanimous
7/14/09
Application for Payment # 21 to the General Contractor was reviewed. The Clerk of the Works, The Architect
and the Town’s Project Manager has previously reviewed the Requisition. Many items were discussed and
evaluated prior to acceptance.
Motion: To approve Application for Payment #21 in the amount of $397,979.00
Motion: Peter Johnson 2nd: Eric Brown Vote: Unanimous
2.02 Diverted Construction Waste
3/10/09
The diverted Construction waste is reported at 86%.
2.03 Construction Change Orders
05/19/09
Construction Change Order # 16 in the amount of $83,103.34 includes PCO’s103 – 111, PCO 113 – 117,
PCO 119, 120, 122, were identified and briefly discussed.
Motion: To approve Change Order No. 16 in the amount of $83,103.34
Motion: Dick Perry 2nd: Eric Brown Vote: Unanimous
Page 2 of 15
PBC Meeting Minutes
14 July 2009 Meeting
6/24/09
Change Order 17/ Time Extension Language $86,539.00
Motion to approve $86,539.00 for CO 17
Motion: Eric Brown Second: Peter Johnson Vote Unanimous
7/14/09
Change Order 18 $85,567.68
Motion to approve $85,567.68 for CO 18
Motion: Eric Brown Second: Peter Johnson Vote Unanimous
2.3 Commissioning Status
For the purposes of reducing ongoing printed text previous entries under this heading may have been
removed from current meeting minutes. Please refer to previous editions of the minutes for older insertions.
10/14/08
Commissioning work shown on schedule, no new activity or meetings until equipment start up.
11/04/08
Sebesta to start Energy Modeling, progress meetings should begin.
01/13/09
Commissioning to commence with start up.
3/10/09
There have been two Commissioning meetings held on site since January. Minutes from those meetings are
copied to the PBC this evening. Next meeting tentative 3/19/09. Start up of equipment will be commencing.
04/14/09
Start-up and training are ongoing
7/14/09
PBC was informed that commissioning is ongoing. Balancing and testing are continuing and RTU-1 is being
assessed for conditions and capabilities. Commissioning will continue once all balancing is complete.
Sebesta Blomberg to come to future meeting for full update.
2.4. DPW Construction Schedule
For the purposes of reducing ongoing printed text, previous entries under this heading may have been removed
from current meeting minutes. Please refer to previous editions of the minutes for older insertions.
4/14/09
Punch list draft completed, carpet being installed, RWS Sullivan punch list being completed this week.
Meeting held with all inspectors and Building commissioner for review, Fire alarm testing scheduled.
Tentatively 05 May 2009 looked at for C.O. Updated schedule will be issued for next week.
5/19/09
Leak into Fire Alarm panel. Potential for delay in receiving C.O.
06/24/09
Elevator inspection scheduled for 6.29.09. Tentative move in week of 7.6.09.
7/14/09
Administrative functions moved in the first week of July.
Construction is anticipated for completion by end of july.
Landscaping continues, Green roof continues.
Shelving and line painting still to be completed
HKT and RWS have update the punch list twice thus far, to recognize completed items.
Page 3 of 15
PBC Meeting Minutes
14 July 2009 Meeting
2.9 Furniture
For the purposes of reducing ongoing printed text, previous entries under this heading may have been
removed from current meeting minutes. Please refer to previous editions of the minutes for older insertions.
12/09/08
Report back in January with proposed cost. Six weeks production two weeks install.
01/13/09
PBC has agreed for Pat Goddard and Bill Hadley to make final decisions on furniture and colors based upon
the palette accepted by the PBC.
3/10/09
Price Quote was received by DPF and DPW for furniture systems for the new building. Quote was finalized
with final color and fabric choices with a total cost of $209, 941.01. To be posted against the FFE budget
line item of $300,000 for hard and soft costs. A purchase order was issued by the town. Delivery schedules
are being reviewed with early may as a current projection. PBC recommended finding out about vendor
storage time in PO agreement as delays in occupancy should not result in extra charges.
4/14/09
Delivery of Furniture 5/7/09 assembly and installation should take approximately 1 week.
5/19/09
Furniture installed. Some minor changes may occur. Few issues with wood furniture in one office. HKT to
work with WB Mason and Allsteel to resolve.
7/14/09
Installation Complete, no repair punch list items known at this time
2.20 Exterior Finishes
For the purposes of reducing ongoing printed text, previous entries under this heading may have been
removed from current meeting minutes. Please refer to previous editions of the minutes for older insertions.
9/9/08
The colors that were decided at an August 25th site visit were as follows:
a. Sand and Salt Shed – siding 3040 Cottonwood
b. Sand and Salt Roof - FABRAL color selected: Light Gray #589
c. Solid Surface - Avonite Surfaces, Studio Collection, White Sands K1-6636
d.Color for the canopy channel to be sent to Eric and Carl for further consideration – intent to be blue (HKT
to send) Final painted channel to be painted front and top and bottom at a minimum
e. Fuel Island Canopy to be Mac’s White
f. Blue color sample for canopy was sent out for sample requested for site.
10/14/08
HKT has received blue color samples for canopies. PBC would like to view on site with natural light.
11/04/08
PBC would like to view canopies on site with natural light in the spring.
3/10/09
HKT / DPF will email members of the PBC to determine a possible day to review the canopy color samples
at the project site
4/14/09
The selected blue color was painted onto the steel channel band for review.
7/14/09
PBC discussed lack of trim ring at light fixtures under entrance canopy. HKT to find trim ring for light fixture,
as PBC does not feel that caulking the space between the fixture and the cut-out is an acceptable solution.
Page 4 of 15
PBC Meeting Minutes
14 July 2009 Meeting
2.21 Town Network Head End
9/9/08
Town looking to bring in Network head end to DPW building, meeting scheduled on site for Thursday 9/18/08
@ 1:00 PM to review.
10/14/08
Town Head End Room being revaluated and may be relocated to accommodate needs of HVAC system
Head End for building, and computer access for facilities maintenance staff.
11/04/08
Contract amendment for additional cost to HKT $12,580.00 for additional HVAC equipment design for Facility
Room, plan changes, does not include construction.
Motion: To approve the Contract Amendment to HKT Architects Contract for additional HVAC
equipment design for Facility Room, plan changes, does not include construction.
Motion: Bill Kennedy 2nd: Carl Oldenburg Voted: Unanimous
01/13/09
PBC approved PCO’s 56 and 62 on a time and materials basis not to exceed $116,205.79.
3/10/09
Construction Work in this area is ongoing
2.22 Telephones for DPW
11/04/08
HKT to hire a consultant to help determine what is needed for a phone system. Additional cost of $6,160.00.
Motion: Bill Kennedy 2nd: Dick Perry Voted: Unanimous
12/09/08
Additional cost for telephone consultant was originally quoted wrong, additional cost is actually $8,624.00.
PBC authorized.
3/10/09
Telephone System Vendor Price Quotes were requested under State Vendor Contract ITT29. Three Price
quotes were received and reviewed by the Town. Two Finalists were determined and a Site Visit has been
scheduled for 3/12/09 to visit the demonstration show room for the two finalist vendors.
Motion: To authorize the Director of Public Facilities to proceed with the purchase of the finally
selected Telephone system contract in an amount not to exceed $60,000.00, with an additional
amount not to exceed $15,000.00 for the selection of various options deemed appropriate to the
system, for a total of not to exceed amount of $75,000.00
Motion: Jon Himmel 2nd: Peter Johnson Voted: Unanimous
2.24 Meeting Minute Format
3/10/09
DPF discussed the idea of simplifying the meeting minute format currently being used. Citing a time
consuming process for monthly updating and minute reviews as well as the length of publish minutes.
PBC discussed the favorable characteristics of this format and a prior moment to purchase and utilize the
software Prolog for development of meeting minutes and potentially tying in budgets and schedules into the
minutes.
DPF representatives expressed a concern that that would develop into an even more cumbersome process
requiring a greater time commitment form DPF to manage. DPF requested that the issue be tabled until the
DPF director was available to participate in the discussion. No changes to be made to format currently. DPF
stated that if time permitted they would issue the minutes for this meeting in the current format and in a
simplified format for review.
Page 5 of 15
PBC Meeting Minutes
14 July 2009 Meeting
2.26 Budget
3/10/09
During review of various budget line items, the definition of some of the budget column headers was
discussed. The PBC requested an accounting of the previous appropriations to verify that there are not
unmet obligations, as we come to the end of the project and discuss or define any ending or remaining
balances in the current appropriation.
The PBC asked for an executive summary of the Project Accounting that clearly shows the Estimated Cost at
Completion for each of the major line items in the budget. While the current form of the budget is focused on
Town Accounting requirements, it is difficult for the PBC to get a convincing understanding of the remaining
contingency across the project and the various appropriations.
7/14/09
It was agreed that a budget review would be planned for the next meeting.
2.27 Technology
4/14/09
IT Department head Dorinda Goodman was present to review technology items that are needed to run many
of the systems in the building but were not prior intentional budget cuts in the project. These items include
but are not necessarily limited to, servers, switches, cables, data racks and miscellanies devises.
Discussions also focused on whether or not the PBC would want wireless capability in the new training /
conference room, that this could be made available through a Verizon install with router similar to what you
might get at a residence. The PBC discussed and elected not to pursue.
Motion: To authorize the DPF to expend up to $109,000.00 for the technology equipment (network /
data) specific to the operation of the new building systems.
Motion: Dick Perry 2nd: Carl Oldenberg Voted: Unanimous
Motion: To approve $24,000 for the GIS Server procurement and up to two additional licenses,
subject to the approval of the Town Manager, to determine that the appropriation supports the
purchase, after the finances of the project are sufficiently closed that the availability of the funds is
certain.
Motion: Dick Perry 2nd: Carl Oldenberg Voted: Unanimous
5/19/09
DPF requested on behalf of the IT department and additional amount of up to $16,500 to purchase
additional switches for the network equipment. Currently some outlets in the building would not be
operable without additional purchase.
PBC was reluctant to approve additional switches without a more specific accounting of what might
be un-operable. Further PBC was okay with not building out full connectivity of all devices if they
were otherwise not currently scheduled for use.
2.28 CTA Time Extension
4/14/09
HKT presented a discussion on a CTA Time extension. The proposal was originally received for an 81 day
extension with a general conditions cost of $135,000. This submittal was vetted and CTA agreed to a
reduced proposal of 71 days and $86,000, reflective of the time delays incurred through many of the delay
issues documented in the letter, the majority of which were related to differing ground and site conditions.
The PBC would like to see the final language of the Change order prior to approval.
5/19/09
Change Order/ Time Extension Language.
The language text was discussed with copies distributed to all members. Mark Barrett directed to incorporate
suggestions to text and send to PBC representatives for confirmation.
Page 6 of 15
PBC Meeting Minutes
14 July 2009 Meeting
6/24/09
Language for time extension change order was finalized with PBC consent. PBC Approved Time
Extension request through approval of Change Order 17 in the amount of 71 days and $86,539.00,
see item 2.03 above.
2.29 Equipment
5/19/09
The proposed Equipment list was discussed with a corresponding estimate of $445,000.00 against
a budget of $550,000.00. The equipment was predominately items included in the original plans
i.e. shelving and industrial equipment that was removed for budgetary reasons and is now being
reinstated. PBC was advised that bids were being received for the equipment and in turn advised
DPF to remain within the established budget.
Concrete Truck Stops proposed for Vehicle Staging and Prep Area $6,000.00
Motion to approve $6,000 for Concrete Truck Stops
Motion Eric Brown Second: Carl Oldenburg Vote Unanimous
Padlocks for Lockers Requested for Locker room $ 600.00
Motion to approve $600 for Padlocks
Motion Eric Brown Second: Carl Oldenburg Vote Unanimous
6-24-09
Bids for Equipment
Requisitions #1-#5 and CTA Change Order proposal 127 $202,931.35
Motion to approve $202,931.00 for Equipment Bids
Motion: Dick Perry Second: Eric Brown Vote: Unanimous
Salt Brine Not to exceed
$80,000.00
Motion to approve not to exceed $80,000.00.
Motion: Peter Johnson Second: Jon Himmel Vote: Unanimous
Start Up supplies Car Wash $1,649.45
Motion to approve $1,649.75 for start up car wash supplies
Motion: Eric Brown Second: Peter Johnson Vote Unanimous
7/14/09
DPF reported that two pieces of equipment remain for purchase and have budget allocations.
2.30 High Density File Storage Unit
6-24-09
High Density File Storage $44,887.75
Motion to approve $44,887.75 for High Density Storage
Motion: Peter Johnson Second: Eric Brown Vote Unanimous
2.31 Bi-Directional Radio
5/19/09
The operation and need for a Bi-directional radio system in the building was discussed with the Fire
Department. The system boosts the signal of the fire department radios allowing them to communicate in
the building and improves fire fighter safety. Expected costs range from $30,000 to $50,000.
PBC expressed need for an Additional services fee from HKT Architects to develop an RFP for the antenna
system to obtain design/build quotes for same.
Page 7 of 15
PBC Meeting Minutes
14 July 2009 Meeting
6/24/09
HKT Additional Services not to exceed $8500.00
(Bi-directional Radio)
Motion to approve not to exceed $8500.00
Motion: Eric Brown Second: Jon Himmel Vote: Unanimous
7/14/09
RFP drafted by HKT and going to be sent to fire department for review.
2.32 Fire Suppression System at Sand & Salt Shed
5/19/09
The need for a fire Suppression / Sprinkler system was discussed in the Sand and Salt Shed located behind
the building. The size of the building dictates that a sprinkler system is required based upon statute.
Upon review of the current progress of the project and the extent of sprinkler coverage present, and through
consultation with the Fire Department it was decided that the DPF would apply to the State Board for a
Variance on the requirement.
7/14/09
Application for variance has been submitted to the State Board. The application is supported by
the Fire Chief. Hearing is forthcoming.
2.33 Appliances and Office Equipment
5/19/09
The purchase of Refrigerators and Office Copiers, were discussed for the new building. The PBC
expressed a reluctance to approve the purchase of equipment where the language of the
appropriation may not clearly support it, without direction from the Town Manager.
7/14/09
DPF reports that the Town Manager supported the use of funds for this purpose and Purchase
Orders were issued by the town
2.34 Movers
5/19/09
The PBC approved the award of a Purchase Order to Sterling movers for the relocation services of the DPW
and DPF Offices.
Motion to approve quote of $8,684.00 to Sterling Movers.
Motion Eric Brown Second: Dick Perry Vote Unanimous
Page 8 of 15
PBC Meeting Minutes
14 July 2009 Meeting
2.35 PCO’s
5/19/09
PCO’s 123, 124, 125, 126 were reviewed and discussed with description by HKT Architects.
Motion to approve PCOÒs 123, 124, 125, 126 in the amount of $28,555.14, as presented.
Motion Dick Perry Second: Bill Kennedy Vote Unanimous
06/24/09
PCO 128 $8,146.00
Motion to approve $8,146.00.
Motion: Eric Brown Second: Peter Johnson Vote Unanimous
PCO129 extend concrete apron $19,286.25
Motion to approve up to $25,000.00 for concrete apron.
Motion: Eric Brown Second: Peter Johnson Vote: Unanimous
2.36 HKT Contract Amendment
5/19/09
Discussion on the contract end date of Basic Services for HKT Contract
Motion to authorize up to $23,500 for Contract extension for additional Construction Administration
Services on an hourly basis, expected to cover a three month period.
Motion John Himmel Second: Eric Brown Vote Unanimous
2.37 HKT Additional Services
5/19/09
Additional services required to revise electrical requirements for equipment being purchased for
the new building.
Motion to authorize $7,700 Additional Services to HKT Architects for RWS Sullivan electrical
engineering revisions.
Motion Dick Perry Second: Bill Kennedy Vote Unanimous
2.38 Budget Transfer
6/24/09
Budget Transfer $518.76
For install owner telephone lines from Allowance for Operations
Motion to approve $518.76 for budget transfer
Motion: Peter Johnson Second: Eric Brown Vote Unanimous
2.39 Kronios Time Clock
6/24/09
Kronos Time Clock System Estimated $33,000.00
Motion to approve $33,000.00 for Kronos.
Motion: Peter Johnson Second: Eric Brown Vote Unanimous
Page 9 of 15
PBC Meeting Minutes
14 July 2009 Meeting
2.40 Pavement testing
6/24/09
Pavement Testing $3,850.00
Motion to approve $3850.00 for Pavement testing.
Motion: Dick Perry Second: Jon Himmel Vote Unanimous
2.41 HP Parking Signs $145.28
7/14/09
Motion to approve $145.28.
Motion: Jon Himmel Second: Eric Brown Vote Unanimous
2.42 Software for Fuel Management $2,818.00
7/14/09
Motion to approve $2,818.00 for software.
Motion: Eric Brown Second: Peter Johnson VoteUnanimous
2.43 PCO 143-Head End Electrical
7/14/09
Additional Electrical requirements are needed at the new Head end room.
PBC discussed need for planning to prevent needs such as this not being identified earlier in the process.
Motion: To approve additional electrical work identified in PCO 143 in the amount of
29,351.13
Motion: Eric Brown Second: Peter Johnson Vote: Unanimous
2.44 PCO144 - Exhaust Fan Reconfiguration
7/14/09
PCO to relocate existing ex. Fan in large Conference room.
PBC recommends that that EF be modified to have manual control to avoid unintentional operation and noise
and to save on relocation costs.
PBC did not approve PCO 144
2.45 PCO 142 – Fluid Distribution Equipment
7/14/09
Price quote received for Fluid Distribution equipment originally in project but removed prior to bid for cost
savings. Budget line item in budget for this item at $140,000.00. PCO 142 Cost $147,772.76
Motion: To approvePCO 142 in the amount of $147,772.76.
Motion: Peter Johnson Second: Eric Brown Vote: Unanimous
Page 10 of 15
PBC Meeting Minutes
14 July 2009 Meeting
2.46 PCO 141 Installation of Town owned Lift
7/14/09
The PCO was submitted at $13,026.00. The scope was discussed and the PBC asked the DPW to
look into alternative ways to install lift at more conservative costs. If alternative ways are not found
then the PCO is authorized for approval not to exceed $13,026.
Motion: DPW to meet with HKT to investigate options for a more conservative way to install
the existing lift, finding none, the proposed PCO 141 in the amount not to exceed
$13,026.00, shall be approved.
Motion: Peter Johnson Second: Eric Brown Vote: Unanimous
2.47 PCO 140 Stone Swale
7/14/09
Motion: To approve PCO 140 in the amount of $3,248.25 (T&M) for the installation of
the proposed stone swale.
Motion: Eric Brown Second: Peter Johnson Vote: Unanimous
2.48 PCO 139 – Relocate Stanchion
7/14/09
PCO was submitted to move the entry stanchion back 15 ft away from the gate for better vehicle access into
the facility. PBC requested that
DPW meet with HKT to investigate options for alternative methods to complete the
work and look at perhaps performing some of the work.
2.49 PCO 138 – Wetland Planting
7/14/09
Motion: To approve PCO 138 in the amount of $3,646.35 for the installation of the
additional wetland planting.
Motion: Eric Brown Second: Dick Perry Vote: Unanimous
2.50 PCO 137 – Sidewalk railing
7/14/09
Motion: To approve PCO 137 in the amount of $9,412.90 for the installation of the
sidewalk railings required for accessibility.
Motion: Peter Johnson Second: Dick Perry Vote: Unanimous
2.51 PCO 136 - Additional seeding at slope
7/14/09
Rear slope of site, which increased in size to reduce amount of material being removed from site at high cost
requires seeding.
Motion: To approve PCO 136 in the amount of $13,476.91 for the installation of the
added seeding at rear slope
Motion: Dick Perry Second: Peter Johnson Vote: Unanimous
Page 11 of 15
PBC Meeting Minutes
14 July 2009 Meeting
2.52 PCO 134 – Added Security Camera
7/14/09
PBC discussed value of adding additional camera and requested DPF to investigate adding
camera if found to be needed under maintenance.
2.53 PCO 133 – Rain Harvesting System Automation
7/14/09
Motion: To approve PCO 133 in the amount of $4,226.70 for the automation of a
portion of the rain harvesting system to integrate more effectively with the vehicle wash.
Motion: Peter Johnson Second: Dick Perry Vote: Unanimous
2.54 PCO 131 – Sealing Washbay
7/14/09
PCO was not approved, HKT to investigate responsibilities of subcontractor..
2.55 PCO 130 – Exterior Corrugated Metal Panel
7/14/09
HKT still investigating
Issue involves proper sealing of the building skin, specifically at seams and penetrations prior to the
installation of the metal panels. PBC recommends review of clerk of the works photos and videos during
construction to gain confidence in thoroughness of work and the removal of selected panel locations as a
sampling to expose area and inspect for proper sealing.
2.56 PCO 123 & 129 – Concrete Apron
7/14/09
PBC in favor of reducing square footage to maintain methodology, but to keep costs as approved of
$46,041.25
2.57 PCO 118 - Vehicle Exhaust Wiring
7/14/09
Motion: To approve PCO 118 in the amount of $596.78.
Motion: Peter Johnson Second: Eric Brown Vote: Unanimous
2.58 Substantial Completion
7/14/09
Proposed Form of Substantial completion reviewed and language discussed. Punch list expressed
as being attached. PBC recommends not to cancel the builders risk insurance until substantial
completion. Contractor should maintain insurance while still working on project.
The PBC made no objection to the dates, times of the proposed Certificate of Substantial
Completion, but proposed that the Town Managers Office review the language as well since much
of it dealt with insurance issues.
Page 12 of 15
PBC Meeting Minutes
14 July 2009 Meeting
2.59 Ribbon Cutting Ceremony
7/14/09
th
Ribbon Cutting Ceremony set for Friday August 7 at 8:30 AM
2.60 Signage
7/14/09
Dedication Plaque approved as circulated, Signage option 3 for building approved.
Signage still requires approval for site sign out by Bedford Street.
3.0 K-12 Master Plan
3.1 Preliminary Review of Master Plan
01/13/09
Representatives of the Design Partnership of Cambridge presented an overview of the K-12 Master Plan
findings to date.
PBC advised DPC verify setbacks with zoning for any construction.
PBC requested full disclosure of footnotes on any and all cost documents and estimates showing
escalation provisions and terms.
PBC requested town expenses be added to project cost sheet.
Scheduling discussions involved estimates on MSBA review schedules and funding cycles.
3/10/09
DPF reported that the K-12 Master Plan was being finalized and is scheduled for a presentation to the
School Committee in March of 2009.
3.2 Adhoc Committee
6-24-09
The Superintendent of Schools has asked for an adhoc Committee to review the K-12 Master Plan.
Committee members are being requested from several different areas including two
representatives form the PBC.
John Himmel and Eric Brown volunteered to serve the Adhoc K-12 Committee in representation of
the PBC
Page 13 of 15
PBC Meeting Minutes
14 July 2009 Meeting
4.0 Stone Building
4.1 Continued development / next steps for Stone Building Project
1-20-09
The Purpose of the meeting was to provide an opportunity for interested parties to discuss with the PBC the
concern they may have with regard to the continued or further development of the Stone Building Project.
Representatives were in attendance from the Historical Society, Historic Commission, CPC, and CEC in
informal or un-official capacities to engage in a dialogue on the best course of action for this project.
Discussion points included:
1. Historic Restoration vs. Preservation
2. The intended use of the building – not as a dedicated library but as a Heritage Center
3. Scope of the prior study and satisfactory completion of the work
4. Renovation of the building without more detailed knowledge of the intended use
5. Costs proposed for continued work versus those of other projects of historic character
a. The budgets proposed to CPC were clarified as budget figures only and did not indicate
plans to contract exactly at those dollars.
b. Completion of a Historic Structures report for the Stone Building, costs were discussed
between $25,000 and 50,0000.
6. The engagement of a qualified historic specialist for future work relative to the historic details
7. A reduced budget ($180,000) was outlined for re-issuance to CPC for a modified scope for moving forward, to
include a Historic Structures report and design such that a 2010 request could be made for monies for
construction documents.
2-10-09
General Discussion on the Stone Building project continued and is summarized below:
This Project is requesting $180,000 in Community Preservation Act funds to preserve the historic Stone
Building by stabilizing the structure. The first step of the stabilization process will entail a Historic Structures
Report (HSR) augmented by further existing conditions assessment; all of this will be the basis of the
Stabilization bid documents. Strategic building stabilization repairs will be bid and completed within these
funds.
Concurrent with this Stabilization process, the Town needs to identify the users and then fully describe the
building program. Should there be any residual money left from the stabilization effort, that money will be put
towards preliminary programming of the space for an identified user.
A year or more out, with the building stabilized and the building program fully described and vetted, the
Stone Building will again be before Town Meeting for funds to hire an Architect/Engineer team to complete
design and bid documentation for the full renovation of the building. That Architect/Engineer team will utilize
the Historic Structure Report (HSR) and the completed code analysis, structural, mechanical, electrical, and
plumbing systems preliminary analysis that are a part of the recently completed Feasibility Study. Thereafter,
once the bid documents are complete, the Project will again be before Town Meeting for a vote on
appropriating Construction dollars.
3-10-09
No further development. Jon Himmel reports that a meeting is pending for discussion on the time lines for
the project and next steps.
4.2 Stone Building Designer Selection
5/19/09
Architects are submitting proposal for the Stone Building HSR phase.
A committee is being formed for the Designer selection Committee of which two members of the
PBC are being requested.
Dick Perry and Carl Oldenburg volunteered to represent the PBC on this committee
Page 14 of 15
PBC Meeting Minutes
14 July 2009 Meeting
7/14/09
Presentation by Architect for Stone Building Study work at next meeting 8/11/09 at 7PM.
Next Meeting:
8/11/09
Public Services Building, 201 Bedford St. 5:00 PM
Meeting Adjourned 10:15 PM
Motion to Adjourn
Motion: Dick Perry 2nd: Eric Brown Voted: Unanimous
Page 15 of 15