HomeMy WebLinkAbout2014-10-30-SMPC-min 4'7"°
aM°"1''G
TOWN OF LEXINGTON
Ad hoc School Master Planning Committee (AhSMPC)
APPo'L I4'
Minutes
Date October 30, 2014
Place and Time- School Administration Building,Upper Level Conference Room, 8 00 A.M.
Members Present Paul Ash, Superintendent of Schools, Judy Crocker, School Committee
Peter Kelley, Board of Selectmen(BoS) Patrick Goddard, Director, Department of Public Facilities
(DPF) Jon Himmel, Permanent Building Committee (PBC) Carl Oldenburg, PBC Jessie Steigerwald,
School Committee
Members Absent None
Liaisons Present David Kanter for Rod Cole, Capital Expenditures Committee
Liaisons Absent Mollie Garberg, Appropriation Committee Alan Levine, Appropriation Committee
Semmes, Maini, and McKee Associates (SMMA) Phil Poinelli, Educational Planner Joel Seeley-
Project Manager
Others Present Tom Diaz, Candidate for School Committee Bill Hurley, Candidate for School
Committee Kate Colburn, Lexington Parents Advocacy Group(LPAG), Gretchen Reisig, LPGA, Claire
Sheth, LPAG Ashley Waring, LPAG Katie Wipke, LPAG Sandy Beebee, LPAG Becky Barrentine,
resident; Christina Lin, resident; Patricia Valda, resident; Harvy Simkovitz, resident; Bettina
McGimsey, Sidewalk Committee and Parent Teacher Association-Parent Teacher Organization
Presidents' Council, Bob Pressman, Community Preservation Committee Mark Barrett, DPF
Recording Secretary Sara Arnold
Dr Ash started the meeting at 8.02 A.M.
1 Administrative Details SMMA agreed to accept comments on the Lexington Public Schools Master
Plan- Phase 1 report until Monday,November 3rd The School Department is creating a website for all
materials associated with school population growth, the impact this has on the school system, and the
efforts by this Committee to address these issues This will include all comments received by the
School Department regarding this subject. Documents should be forwarded to Dr Ash.
2. SMMA Update on Phase II Master Plan Mr Poinelli reported that SMMA has started its work on
the Lexington Public Schools Master Plan - Phase 2 by looking at short term options at the elementary
schools, as requested by this Committee, to address anticipated near-term enrollment increases This
will be followed by looking at short-term options to address enrollment at the middle schools
Using PowerPoint slides,Mr Seeley reviewed three tasks that were explored for the elementary schools
and responded to questions, as follows
• Task 1 Relocate one pre-kindergarten program into the current School Administration
building In this scenario, two rooms in the School Administration building are repurposed for
the Occupational Therapy/Physical Therapy (OT/PT)pre-kindergarten program. The room
identified as an OT/PT waiting room is larger than necessary because that is the size of the
current room and there is no need to decrease it. The estimated cost of this project is
approximately $420,000 Some of the cost drivers, such as new floors, cabinetry, air
conditioning and accessible toilet rooms are included in an effort to make the space equivalent
to that which is currently used for the pre-kindergarten OT/PT program. Some of those items
could be removed from the scope to reduce the costs if the renovations were considered to be a
temporary solution.
• Task 2 - a two-step process
Step One Renovate the School Administration building to accommodate the entire pre-
kindergarten program,which is currently in the Harrington Elementary School
(Hamngton) Step one has two alternatives
o The entire pre-kindergarten program is accommodated within the current
envelope of the School Administration building and prefabncated facilities are
added to accommodate displaced school administration needs. The estimated
cost is approximately $13 7 million.
o Prefabricated facilities are installed next to the School Administration building
to supplement the pre-kindergarten needs. This results in less disruption for the
school administration staff. The estimated cost is approximately $12 1 million.
In both alternatives, the gymnasium in the School Administration building is converted
into areas for professional development programs and storage space The high cost for
the School Administration building renovations is influenced by code requirements,
including installation of a sprinkler system and meeting Americans with Disability Act
requirements
Step Two Repurpose the vacated pre-kindergarten space in Harnngton into
Kindergarten-Grade 5 program space and support areas for such use The estimated
cost is approximately $330,000 Mr Seeley noted that this conversion works well with
the rest of the space in Harrington. He added that this part of the project couldn't be
started until the completion of step one he projected a March 2017 completion date but
felt this could be adjusted to a less disruptive time
Mr Poinelli agreed that if Option 2 is pursued, it would change the Harnngton capacity
figures in the Phase 1 report, although the change may not be significant. He also agreed
that the scope of work for Option 2 could be tweaked,but the current data provides an order
of magnitude for this project
• Task 3 Installing two classroom-sized temporary modular units at Bowman Elementary School
(Bowman), Bridge Elementary School(Bridge), and Fiske Elementary School(Fiske) The
estimated costs are approximately $690,000, $730,000 and $980,000 respectively Fiske carnes
a higher cost because of site utility work involved in moving two geo-thermal wells Other
locations that were evaluated involve tree removal or the loss of some play area space,neither
of which seemed advisable Adding a partial second floor instead of using modulars was not
explored,but if the current foundation wasn't built to support a second floor this would be cost
prohibitive
There was considerable discussion about the unknowns associated with long term solutions,which have
not yet been studied, and concerns that these could be negatively impacted by the short term decisions.
For example, it was noted that it isn't known whether adding wings to some school buildings is a
reasonable long term solution,but if wings are added, the location of temporary modulars should not
negatively impact the preferred location of those wings It was also noted that modulars are a temporary
solution, generally used for no more than three years, if the space they provide is going to be needed for
more than three years,prefabncated buildings would likely be more cost effective
Numerous comments supported the idea of understanding the big picture and long term solutions before
making decisions about short term solutions Comments also supported the need for some School
Committee policy decisions, Mr Kelley expressed particular concern about the lack of clarity associated
with school districting He wants to understand the degree of flexibility the School Department has,
based on its policies, in assigning neighborhoods to elementary schools and how this impacts enrollment
at both the elementary and middle schools There was discussion about the importance of sequencing
decisions to facilitate a logical process for moving forward and the need for an interface between the
temporary solutions and the long term solutions Mr Poinelli commented that, in January 2015, SMMA
will have a draft Phase 3 report with long term solutions identified, these could help this Committee
develop short term recommendations and could inform a 2015 Annual Town Meeting funding request
related to short term solutions
Dr Ash said that moving students from Fiske to Estabrook Elementary School,which currently has
three extra classrooms, can provide a stop-gap measure to address 2015-2016 enrollment demands,but
he stressed that the projected enrollment demonstrates a need for additional system-wide elementary
school classroom space no later than September 2016 He added that in December he expects to have
information from the Massachusetts School Building Authority regarding a state subsidy for rebuilding
Hastings Elementary School (Hastings),which will help the Town understand the long term picture,but
whether or not the Hastings project is approved for a subsidy, the school needs to be replaced or entirely
renovated and expanded. Mr Kelley commented that the Town needs a three year window to get
taxpayer support for any major school project.
There was discussion about developing a decision tree that demonstrates a process layout. Ms
Steigerwald, Mr Himmel, and Ms Reisig agreed to work on this in preparation for the Monday night
School Committee meeting Ms Crocker suggested that this effort try to incorporate concerns that have
been identified during this meeting or previous meetings
• The space limitations for the pre-kindergarten program,which indicate that one more student
may result in the Town having to fund out-of-district services.
• Requests for a master plan before making recommendations about installing modulars
• Requests for an understanding of the impact school districts have on specific schools.
Mr Kanter asked this Committee to make note of the memo that he had distributed from Mr Cole,who
was unable to attend this meeting He also suggested that it will be important for this Committee's to go
to the general populace with its long range recommendations
3 Minutes A motion was made and seconded to accept the October 23,2014 Minutes The motion
passed. VOTE 7-0
4 Adjournment The meeting was adjourned at 9 45 A.M.
These minutes were approved on December 4, 2014
Materials distributed/used at the meeting.
Public Meeting Agenda, October 30, 2014, AhSMPC
Draft Lexington Public School Master Plan, Phase 2 Elementary Schools Short and Long Term
Options Study, prepared by SMMA, October 30, 2014
SMMA PowerPoint slides Lexington Public Schools, Ad hoc Schools Master Plan Committee, School
Committee Progress Report, Phase 2 Elementary Schools, October 30, 2014
Memo from Mr Cole to the AhSMPC, October 30, 2014
3