HomeMy WebLinkAbout2014-10-22-LHA-min LEXINGTON HOUSING AUTHORITY
SPECIAL MEETING—OCTOBER 22, 2014
MINUTES
1 ROLL CALL
The meeting was called to order by Chairman Leo P McSweeney at 6 00 P.M.
MEMBERS PRESENT MEMBERS ABSENT OTHERS PRESENT
Leo P McSweeney Weidong Wang Steve Keane
Nicholas Santosuosso
Melinda Walker
Robert D Peters
2 EXECUTIVE DIRECTORS REPORT
A Snow Contract
Steve solicited 6 local landscaping companies for snow removal at Vynebrooke
Village The one response received was from R.L Barnard Landscaping, Inc
They provided 2 quotes The price for the season, which includes plowing,
shoveling of walks, ice melt and salt is $13,223 00 The other option is to pay by
the storm and inches 1-3 inch $425 00, 9-12 inch $875 00, and there is an
additional charge for a call back of the same storm Last season we had 22 snow
events The Board discussed both options and decided that the season price is the
best option.
Upon a motion by Robert D Peters and seconded by Melinda Walker, the Board
voted to accept the proposal from R.L Barnard Landscaping Inc in the amount of
$13,223 00 for snow removal at Vynebrooke Village for the upcoming season of
October 2014 through May 2015 The roll call vote was as follows
YEAS NAYS ABSTAIN ABSENT
Leo P McSweeney NONE NONE Weidong Wang
Nicholas Santosuosso
Melinda Walker
Robert D Peters
B Laundry Contract
Our current 3 year Mac Gray laundry contract is due to expire 12/27/14 The
housing authority retains 70% of monies collected at all 3 villages The machines
are only 3 years old. Mac Gray provides excellent service and we receive our
money regularly each month. The housing authority has the option to extend the
contracts for an additional 2 years
Upon a motion by Nicholas Santosuosso and seconded by Robert D Peters, the
Board voted to extend the laundry contracts for an additional 2 years The new
expiration date will be 12/27/16 The roll call vote was as follows
YEAS NAYS ABSTAIN ABSENT
Leo P McSweeney NONE NONE Weidong Wang
Nicholas Santosuosso
Melinda Walker
Robert D Peters
C Approve final completion, release retamae Vvnebrooke Village Water
Remediation Protect
Fred Russell, the civil engineer, has signed off that the Vynebrooke Village Water
Remediation project has been completed by Barrows Contracting, Inc The
retainage due is $7,180 83 as Application for Payment#4
Upon a motion by Nicholas Santosuosso and seconded by Melinda Walker, the
Board voted to approve the Certificate of Final Completion and release the
retainage due to Barrows Contracting in the amount of$7,180 83 as Application
for Payment#4 The roll call vote was as follows
YEAS NAYS ABSTAIN ABSENT
Leo P McSweeney NONE NONE Weidong Wang
Nicholas Santosuosso
Melinda Walker
Robert D Peters
The civil engineer has to file the proper documents with the Town of Lexington.
The contract included removal of basement debns within reach. Some of the
insulation and chicken wire needs to be retacked to the ceilings Our maintenance
staff is going to complete this so we will bill CPA for this along with the allowed
administrative fees The project came in at a substantial savings of$70,000 00
The Lodestar Energy contract and ASNE Generac maintenance agreement need
to be signed by Leo so they can be submitted. It was suggested to sign a 2 year
contract with ASNE Generac so as to lock in the pnce of$850 00 annually
Upon a motion by Robert Peters and seconded by Nicholas Santosuosso, the
Board voted to enter into a 2 year maintenance contract with ANSE Generac The
roll call vote was as follows
YEAS NAYS ABSTAIN ABSENT
Leo P McSweeney NONE NONE Weidong Wang
Nicholas Santosuosso
Melinda Walker
Robert D Peters
D 2014 CPA Prosect discussion
As discussed at the last meeting, Steve and Leo attended a CPC meeting. It was
suggested that the ongoing CPA projects should be completed and closed out
before applying for more funding.
3 ADJOURNMENT 6 30 P.M.
A true copy attest
STEPHEN KEANE, EXECUTIVE DIRECTOR
3