HomeMy WebLinkAbout2002-11-20-CEC-min
Town of Lexington
Capital Expenditures Committee
Meeting Notes
November 20, 2002
Town Hall, Room 111
Committee members present: Bhatia, Burnell, Hornig,
Rosenberg, Stolz
Appropriation Committee liaison present: Karen Dooks
Recreation Department staff presenters: Karen Simmons,
director; Sheila Butts, assistant director. Recreation
Committee members: Sandra Shaw, chair; Pam Varrin, vice
chair; Don Chisholm; Richard Neumeier. DPW staff presenter:
Dave Pinsonneault, public grounds superintendent
Minutes of the November 14 meeting were approved, as
corrected, and will be forwarded to Appropriation Committee
liaisons.
Meetings Schedule (new items highlighted, note earlier
meeting time December 12)
7:15 p.m.
Thursday, Dec. 12,, Schools, Town Hall Room
(Meeting location may change to accommodate joint
111
meeting with Appropriation; start time is to accommodate
photography)
(Monday, Dec. 16, 8:00 p.m., Special Town Meeting PAYT
Refunds, Clarke Middle School)
Tuesday, Dec. 17, 7:30 p.m., Summit III, location to be
determined
Wednesday, Dec. 18, 7:30 p.m., Town Hall Room 111, DPW
operations facilities and senior center planning
updates/progress reports
Recreation Presentation
Karen Simmons presented “Recreation 5-Year Capital Plan, FY
2004- FY 2008,” October 28, 2002 (the document should be
considered part of these minutes).
•Park and playground improvements: Tax levy, $35,000
Kineen Park. Prior years, $30,000 to do park upgrades. New
estimate reflects higher demolition, removal, and
resurfacing costs; the committed urged Recreation to use an
inflation factor for out-year requests. This work is given
higher priority than Valley; Recreation now favors upgrading
existing structures for ADA, etc., than upgrading lesser-
equipped playgrounds. The 2008 request for lighting raises
questions of fees and Enterprise vs. tax levy funding.
FY ’07 envisions $200,000 to replace Center Playground
with modular play equipment, assuming current equipment cost
estimates, DPW-assisted demolition and uncomplicated
removal/disposal of existing structure.
•Pine Meadows equipment replacement: Enterprise,
$50,000 for a package of mower ($36.5 k after trade-in), $9k
for aerator, $4.5k for spreader (and a like amount/package
in FY ’07). Individual items lower than $25,000 threshold,
but sometimes useful to bid package of equipment from
vendors, securing better pricing. The committee asked
Recreation to provide its documentation of Pine Meadows
equipment, totaling about 30 pieces, including estimated
life, replacement schedule, and annual funding requirements.
Approximately 4 of the pieces of equipment individually cost
more than $25,000. Operating vs. capital items, vs. efficacy
of package bidding.
•Skate park: Tax levy, $35,000, new request. 1997
private fundraising group formed; funds and in-kind have
gotten concrete slab installed, but inadequate to install
skating features (“events”), cost of which is up to $50,000.
This request is for safety fencing (590 linear feet, 6-foot
height) to protect spectators, users of track and softball
field; plus benches, bike rack, trash receptacles.
Recommended by insurance carrier for safety.
•Pine Meadows improvements: Enterprise, $400,000 in FY
’05. To replace failing Upper Pond dam, which is now subject
to daily inspection and to a lower than designed water
level. Has been patched by DPW, but partial failures when
there is heavy rain. Recent engineering study suggests that
can be deferred to FY ’05 with daily inspection and
necessary patching, but Recreation would do sooner if it
were sure of financial resources given new funding
obligation for $1oo,000 annual debt service on Lincoln Field
renovation. FY ’08 rebuild third hole, $200,000 (not
discussed).
•Old Reservoir: Enterprise, $50,000. FY ’06 resurfacing
of currently heavily pitted parking area. Estimate assumed
bituminous, but Lincoln Park designs suggest a perhaps more
expensive paved gravel surface. DPW currently patches and
regrades, but the lot has, fundamentally, failed, and is
deeply holed.
•Adams, Valley Tennis improvements: Enterprise,
$125,000 FY ’06 reconstruction of failing, cracked tennis
and basketball (Adams) playing surfaces (currently patched
and crack-filled by DPW, but no longer working), and
refencing. Usage not trackable since no consistent permit
requests (vs. Center, Clarke courts).
•Center Pool complex: Enterprise, $30,000, FY ’07 study
of infrastructure, especially filtration system.
Discussion
•Is enterprise funding adequate given Lincoln Field
debt service? Simmons said Recreation is working on that,
and will make a December-January presentation to Recreation
Committee on overall funding requirements, needed fee
increases (pool complex, leagues, field permits, golf
course) as debt service begins in FY ’04; some fee increases
will just cover cost increases (e.g., golf-course management
contract). Jointly brief Capital Expenditures and
Appropriation on financial status in January.
•Lincoln Field status? Will publicize progress/status
to community. Presentations by five alternative filled turf
manufacturers in Town Hall G-15 Nov. 27, 9:00 a.m. Bids due
December 3, contract in early January. Construction as soon
as spring weather permits, with use scheduled for fall
sports season (end of August 2003).
•Major issues for next decade? (1) Upgrading athletic
facilities (fields, backstops, irrigation) as renew
elementary schools. (2) Perhaps pool infrastructure,
lighting track. (3) Indoor space. Old Harrington School?
Cannot not adequately schedule activities at schools (PTA
and concert use), and have demand (growing basketball
leagues, minimal preschool program (Cary Hall?), would like
teen weekend-night program for those not in team sports;
Hayden not interested.
The Recreation discussion concluded, and those
participants departed.
Discussion of Capital Issues
The committee discussed current-year capital priorities
under the assumption that there were no operating budget
override, and essential no cash capital. It also considered
whether current conditions would continue for the indefinite
future, compelling the town to manage for cash conservation,
and therefore to defer indefinitely a new DPW operations
center, new Senior Center, and new school elementary
buildings (in which case, Burnell suggested, it would be
appropriate to renovate one school every five years).
In the immediate future, the equation has changed.
During the past two years, essentially all cash capital
items requested, except Fire Engine 2 replacement, were
funded from cash and borrowing. Now, IF there is an
override, the current fiscal year tight as it is, would be
the best capital funding year; thereafter, things would
again get tighter until the next override. Given current
borrowing costs covered within the cash capital policy (5
percent of tax level), about $1.5 million is available for
capital items each year: $1 million actual cash capital
after debt service, and $500,000 from the prior override for
road repair and maintenance. Current cash capital request
total at least $2.0-2.5 million.
The interest cost on short-term borrowing will
certainly be below what the town is estimating (Hornig will
get current rates and build into the committee’s model now),
but debt outstanding, rather than declining, will begin to
rise rapidly as school supplemental items and library
funding ramp up.
Current FY schools request: School presentation not
until December, but based on preliminary outline shared by
Town Manager, items appear to total $425,000 (roof,
foundation, and gym floor repairs) plus the as-yet uncosted
LHS acoustical retrofit ($2-3 million?) and unspecified
requests for the LHS auditorium.
Excluding streets and LHS acoustic and auditorium,
total requests for cash capital therefore appear to be in
the $2 million range, while the current funding policy would
provide approximately $1 million. Again as noted, the
squeeze would worsen in FY ’05 and ’06, even assuming an
override, under the current cash capital funding policy. In
the past cycle, that gap was covered by borrowing and modest
project deferrals (fire engine, some school requests). This
year, two pending requests (landfill closure, fire engine)
would consume 80-90 percent of cash capital, absent
borrowing.
(Side discussion, for Appropriation consideration: Fire
staffing, dispatch of truck with staff on ambulance runs?)
•Policy. Committee wants to weigh in on new cash
capital funding policy Rick White expects to draft, raise
with Selectmen. White apparently favors a smaller percent of
tax levy, but NOT including debt service in the costs the
funds would cover. Bhatia asks whether having debt service
included, for perhaps a small percent of the total spending,
might not be desirable, in light of appropriate use of
short-term borrowing to fund cash capital priorities. The
problem is excluding the funding cost for the supplemental
and big-ticket requests (school acoustic retrofits,
library). The committee’s interest and expertise is in
identifying the real needs, and then advocating for adequate
funding in discussions with the Selectmen (Dec. 9? Summits?
etc.)—allowing for appropriate flexibility, but keeping cash
capital safe from indiscipline problems (supplementals, big
ticket borrowing). Hornig will remodel the committee’s
annual five-year assumptions, based on
•Tentative priorities for FY ’04 requests (using the
preliminary School list, prior to discussion with School
Committee, and excluding LHS acoustics and auditorium; based
on Town Manager November 14 list and prior presentations to
the committee); assumption is cash, not borrowing, and with
full 5 percent of levy (current funding policy). Further
assumes street work funded at Ch. 90 level plus prior
override ($950,000 total), but the remaining $85,000 cash
capital funding at risk; and committee wariness about
sneaking operating items (street striping, small equipment
requests) into capital:
1. Landfill closure, $450,000
2. Fire engine replacement, $327, 000
3. Hastings foundation wall repair, $65,000
4. DPW equipment replacement (amount from cash capital
vs. enterprise unclear, based on later presentation
to Selectmen; assume about $125,000)
5. School roof leak repairs, as many as could be
accommodated (up to about $190,000)
6. Cary Hall retrofit out of building envelope,
$150,000
7. Fire air compressor equipment, $35,000
(Side discussion on whether School Committee will seek
capital funding for LHS acoustical retrofit, or will
consider offering in-room listening-assistance devices vs.
tuitioning students out of the system.)
Committee preliminary evaluation of remaining small-
ticket items:
“B” list: Playground improvements
“C” list: Visitor center wiring; Town Hall lighting
study; and access upgrades (all from building envelope);
sidewalks; skate park; gym floors
Items in disagreement: Building facilities inventory
study (building envelope); Electric Utility Ad Hoc Committee
funding ($150,000)
Corrections: Social Services ADA upgrades is double-
counted from DPW building envelope request; Selectmen
presentation makes clear the $50,000 MIS automated
permitting system request will not proceed. Stolz remains
concerned over Buckman Tavern roof replacement (needed but
not requested)
Based on these priorities, Hornig’s modeling will
inform both committee recommendations on cash capital
funding policy and, in the Summit meetings, will show the
effects on the town of various cuts and override scenarios,
parallel to the operating/program/no growth in services
being modeled at Appropriation request.
Meeting adjourned 9:51 p.m. Committee members moved to the
Selectmen’s meeting room to listen to budget presentations
concerning capital items, and to ask questions. Among the
points of importance raised in that hearing and discussion
were:
•As noted above, double counting of $50,000 request for
accessibility upgrades, and deferral of MIS request at least
until FY ’05.
•McKenna urged that the $500,000 for Green road
circulation improvements be brought forward from FY ’07
•McKenna urged wider discussion of appropriate
sidewalks policy, center vs. neighborhoods
•Sweeney said the Senior Center planning money request
($100,000) was a placeholder, and could grow; note, the
committee did not prioritize this item, above
•McKenna suggested that the committee consider
inserting an item in the override for cash capital funding,
much as the $500,000 for annual street repair/maintenance
was included in the prior operating override. (This relates
to cash capital funding strategy, of course, but raises two
questions: Is it prudent to put this money at risk? Would
voters entertain open funding for a grab bag of projects,
vs. a visible item like annual road work?)
John S. Rosenberg