HomeMy WebLinkAbout2002-11-06-CEC-min
Town of Lexington
Capital Expenditures Committee
Meeting Notes
November 6, 2002
Town Hall, Room 111
Committee members present: Bhatia, Burnell, Hornig,
Rosenberg, Stolz
Appropriation Committee liaisons present: Karen Dooks,
Sheldon Spector
Department of Public Works presenters: Peter Chalpin (Town
Engineer), Derek Fullerton (Senior Engineer), Brian Gilbert
(Operations), Bill Hadley (Director), Ralph Pecora (Water
and Sewer), Kelly Zeoli (Policy Analyst)
Minutes of the October 30 meeting were approved, as
corrected, and will be forwarded to Appropriation Committee
liaisons.
DPW staff presented “Town of Lexington Capital Improvement
Program FY 2004 to FY 2008” in summary form and with
background information. Reference is made to that document
throughout, and it should be considered a part of these
minutes. The DPW listed its 10 priorities in the following
order, highest to lowest: landfill closure, DPW operations
facility, traffic improvements, equipment replacement,
street improvements, building envelope, water distribution
system improvements, storm sewer improvements, sanitary
sewer improvements, and sidewalk improvements.
At the committee’s request, presentation and discussion
of these priorities began with number 5, street
improvements, and then cycled through the list; discussion
of planning and construction funds for a DPW operations
facility will be reserved for later review at a separate
meeting, pending progress from the Selectmen’s DPW/201
Bedford St./Senior Center advisory group.
Street improvements (FY 2004 request $1.045 mil., with a
like amount, inflating, each subsequent year. $460,ooo from
Ch. 90, $500,000 from original debt exclusion, $85,o0o from
cash capital. Note that this total EXCLUDES the effects of
the four-year, $7-million program approved in the spring
2002 debt exclusion; initiation of this program depends on
the timing of arranging suitable contracted project
management/oversight personnel, to complement the Town
personnel who manage the existing, continuing street
program.)
List of streets—principally thoroughfares— not yet
available; DPW was requested to provide, and should be able
to do so by end of January.
$7-million program will proceed in quadrants, as
outlined (NW, SW, SE, NE), but may not start until 2004;
that decision should be made before Town Meeting. (Question:
is 2004 soon enough, given planning of next debt exclusion
in 2005?)
Spector questioned the availability of the budgeted Ch.
90 funding.
DPW was asked to provide a list of streets worked on
during the summer 2002 season.
Building envelope (FY 2004 request: $750,000, with a like
amount, inflating slightly toward the end of the five-year
planning period.)
First priority: $100,000 to update 1993 facilities
study, to identify building envelope needs for next several
years; are now past end of 1993 10-year priority list, and
this request has been deferred twice. Absent it, DPW
maintains, it cannot plan for projects or set priorities
rationally henceforth. The report, reviewed by an ad hoc
building finance committee, would be the proper way to set
priorities.
In response to committee questions, DPW said the report
would not encompass schools (the projects are larger in
scope); if approved would be undertaken by 9/03, to be
available for Town Meeting in 2004; and should feed into the
computerized building maintenance management system,
operation of which should begin during the next few weeks
and which should be populated with complete (prototype) data
on Diamond School and Town Hall by town Meeting 2003, with
the library coming on-line thereafter. (But note that the
updated facilities study will not cover schools, so will not
feed school-building data into the maintenance management
information system.)
Other priorities: $100,000 for Visitor Center wiring
(not upgraded since 1947); prior work has covered roof,
heating, and repainting, with ADA access at the front door
and bathroom modification authorized an d in design now. The
electrical system work would complete the Visitor Center
program
$350,000 for a proposed review of need and replacement
of lighting for Town Hall, driven by usability and changes
in use of the building, and (only secondarily at best)
potential energy savings. No inventory, no sense of lighting
levels vs. standards—determining which would be by retaining
a consultant and lighting designer, the first part of the
project (chicken and egg, with no separate design money
available first). Further detail unlikely to be available
before Town Meeting. DPW could conceive of phasing the
request: planing money first, then implementation in a
subsequent year, but that takes longer.
$150,000 for Cary Hall refinishing/post-library move-
out. To revert to hall use, including painting, aesthetics,
cleaning, reverting to old layout. Spending was anticipated
in the plan for library use/swing space during library
renovation.
$50,000 for ADA upgrades, meant to be a running item,
for up to 10 years, to meet needs identified by the
Enablement Committee. No details.
20o5 plan: Westview Cemetery Building, Police Station
elevator, etc.: no details available.
General inflation (about 10 percent) from prior years’
plans? Driven by general inflation, information from
appraisals of projects, ADA requirements, etc.
Water distribution system improvements (FY 2004 request:
$900,000, declining to $850,000-800,000 in the subsequent
three years, and $500,000 in 2008. Water enterprise funds.)
Encompasses cleaning/lining and replacement, continuing
a long-running (nearly 20 years) program. New: “supplemental
roadwork allowance”—amount NOT specified (but one of several
such attempts to carve capital needs/protected funds out of
DPW operating budget), to coordinate with street repaving
program, so don’t have to take funds from operating account
when needs are discovered during course of that work. As
complete 20-year program of relining pre-1929 cast-iron
pipes less than 10 inches in diameter, hope to do a three-
year program of lining 10- and 12-inch pipes at roughly
$700,000 per year, in FY 2008-2010. Where find structural
problems, budget for “relay” work to replace the pipe. No
relining contemplated for larger-diameter lines.
Risk of failure in larger lines? DPW always alert to
the possibility, but they are thick-walled, and the strategy
is to leave them alone. Sufficient allowance to cover
anticipated roadway-related work? Believe so; amount of
relaying spending shown here is for the current $1-million
annual street program; funding for the four-year, $7-million
program incorporated funds for anticipated pipe relaying.
Storm sewer improvements (FY 2004 request: $150,000, rising
thereafter to $335,000-365,000 per year, including both
engineering/design, and construction. Sewer enterprise
funds.)
Separate from long-planned Lake and Winter street
projects, for which $100,000 appropriated last year. A
program coupled to annual and $7-million road paving
program. In most recent season, sewer reconstruction ate
into funds available for paving work on Spring Street, as
storm drains were opened and found to need extensive
subsurface reconstruction. Meant to correct drainage defects
to protect new pavement (as with the supplemental funding
proposed, above, in water distribution system improvements).
In future, would be wise to include in funding dedicated to
the street resurfacing/improvement work, per se.
Sanitary sewer improvements (FY 2004 request: $75,000 for
design/engineering, followed by $525,000 for construction in
2005; like amounts budgeted each subsequent year, but no
detail on use. Sewer enterprise funds.)
With study in hand on Grant Street/Saddle Club overflow
problems, design repair work ($75,000). But new connection
to MWRA relief sewer delayed until MWRA relines to correct
acidification problem (to be bid 9/03); Lexington
construction then ready to proceed a year later (9/04 at
earliest).
Later years just a plug number.
Sidewalk improvements (FY 2004 request: $105,000 to begin a
sidewalk maintenance and construction program, followed by
like amounts budgeted each subsequent year, but no detail on
use.)
Begin with requested walks near Bowman and Hastings
schools., plus $25,000 for maintenance (currently fund
patches out of $10,000 of highways funds).
Virtually no requests from residents for new sidewalks;
1981 master plan was for new sidewalks, not updated, and in
light of limited demand, no reason to do so (but note that
the project description lists updating the master plan).
Out-year proposed funding reflects likely School Committee
requests for new walks, plus maintenance. Could see asking
for maintenance dollars only in out years; town-wide, might
be a few-million-dollar item (get data from Wayne Brooks).
Landfill closure (FY 2004 request: $450,000. Cash capital.)
DEP presumed to allow closure under Hazardous Waste
Management regs, now Solid Waste Management regs. DEP
reviewing report from DPW, and approval not certain but
seems favorable. Current estimate reflects Camp Dresser &
McKee assessment, based on field work (two hot spots). Reuse
would be commercial-industrial, and, importantly, this
treatment would satisfy requirements of legal closure.
(Question: what if the community wanted to reuse as playing
fields, as some members of the DPW/201/Senior Center study
group may desire?) Work is pending state approval.
Traffic improvements (New request. FY 2004 request: $25,000,
followed by a like amount in 2005-2006, rising to $500,000
in 2007 and $200,000 in 2008. Cash capital.)
To carve out a fund for minor traffic safety
modifications on all Lexington Streets, ranging from
pedestrian-crossing cones n the center to no-parking signs
(cost $175 apiece with poles, when set), now taken out of
highway operating budget. Includes new crosswalk painting,
etc.
Committee members pointed out that this is, borderline,
not capital spending per se.
Harrington Road traffic improvements? Early read it
that they are working. Accidents remain, but fewer injuries.
2007 spending includes making temporary modifications
permanent.
Chance of state funding for major intersection traffic
lights, as on Maple St. and Mass. Ave, Hartwell Ave?
Unlikely.
DPW master plan of major traffic improvements? None
such exists. This funding proposed only for signs, striping,
cones, NOT signals, intersection redesign and reconstruction
(but note, Harrington Road reconstruction is just this kind
of reconstruction, isn’t it?) DPW doesn’t see compelling
need for such major traffic/intersection improvements? No,
it does not.
State highway issues? State would love town to take
over all the mileage; don’t go there!
Equipment replacement (Note MODIFIED. FY 2004 request:
$295,000, followed by amounts of $300,000-370,000 in
subsequent years. Cash capital.)
As listed. Mileage, condition, and usage data, repair
vs. replacement costs, to be presented by DPW.
DPW ranks as higher priority than all building envelope
proposals.
Discussion, other DPW items
DPW to provide 5 years of data on project spending,
accomplishments by end of January (in support of committee’s
emerging priority of communicating capital spending plans
and programs to the wider community).
Brook cleaning? DPW has met with Conservation on
Worthen Road wetlands area; characterizes as “falling” if
not actually “moving” in the right direction on the Lincoln
Park committee’s $20,000 grant to plan repairs to wetlands,
opening up of Vine Brook, etc.
Street light relamping for energy efficiency? Done in
part. Lighting Options committee requested funding from
Selectmen last year for comprehensive relighting, but
funding to be made available unclear. If program advances,
would come before the committee via DPW, in all likelihood.
Intent to come to committee, Town Meeting for
operations facility plans and design this year? Yes. Amount
there is a placeholder until refined.
DPW query: how much capital funding expect to have,
since it takes a significant effort to plan projects, many
of which may not advance/ Committee guesses $1 million for
roads (Ch. 90 plus prior overrides), plus $1 million cash
for all other capital items, of which landfill closure would
take half, leaving $500,o00 for all other cash capital
requests—implies very limited equipment and building
envelope funding.
(DPW personnel and Appropriation liaisons depart. Committee
continued in session for general business.)
Schedule update
November 12: Gang of Eight, 8:00-9:00 a.m., Stolz to
cover, Burnell and Hornig as backups
November 14: Town Manager, 7:30-8:15; Electrical study
committee thereafter
November 19: Summit II, Hastings School, 7:00-8:00
November 20: Recreation 7:00-7:30, then committee to
join Selectman’s meeting on all town capital except schools.
School briefing deferred, Burnell will try to reschedule
December 12 or December 10 (assuming Special Town Meeting on
PAYT will be December 9 or 11).
Rosenberg to arrange briefing on DPW operations
facilities December 18 or 19 (Hadley, Kennedy, Lapointe):
scope, renovate vs. build new, timing.
Cash Capital Policy discussion
Assuming $1 million available, half to landfill
closing.
Current 5 percent policy yields something like $4.5
million, but mostly goes to debt service. Should new policy
be a cash amount, preclude borrowing or debt service? Hornig
things yes, Burnell thinks no. Burnell says the point is to
secure adequate funding for capital needs; as existing debt
goes down, so long as don’t drive up total amount of debt,
why not borrow to sustain needed stream of funds for capital
spending. Bhatia concurs. Burnell says point is to stay at
something like the 5 percent level, borrow if need to do it;
don’t risk relapsing to a 15-year period of no capital
spending. Consensus at this point; hold on to 5 percent
policy, and fund it, until an acceptable new policy is put
in place.
Meeting adjourned 10:25 p.m.
John S. Rosenberg