• Start Framing Exterior Walls. <br />• Complete ERU punch list for Locker Rooms. <br />Diamond November Schedule Priorities <br />• Final Steel Delivered. <br />• Completed Steel Erection. <br />• Completed Metal Deck Installation at Classroom Addition. <br />• Completed Pavement Inside Fence. <br />• Completed Underground Plumbing at the Cafeteria. <br />• Completed Tarp Installation and Temporary Heat at Classroom Addition. <br />Diamond December Priorities <br />• Pour Slab on Deck at Classroom Addition. <br />• Complete Underground Plumbing at Classroom Addition. <br />• Pour Slab on Grade at Classroom Addition. <br />• Complete Punch List in Locker Rooms. <br />• Add 15 Additional Parking Spaces on Sedge Road. <br />• Install Tarp for Temporary Heating at Cafeteria. <br />• Photos of work at Diamond were shown. <br />December Budget Update <br />• The approved Construction Budget is $51,586,281. <br />• GMP Encumbered to Date is $49,717,033. <br />• About $88,000 has been spent from cm overtime since the beginning of the project. <br />• Approx. $600,000 in pending pcos, claims, charges, etc <br />• Hill stated work is ongoing, and there are some concerns on how the project is progressing and <br />being managed, citing; <br />o Construction schedule concerns and as of now construction is 5 days behind schedule. <br />Hill has been trying to get updates since November 5th <br />o Analysis for the financials, in Hills view, is lacking. Paid allowance numbers are <br />inadequately organized. Payment items do not tie together adequately. <br />o DiNisco commented on the lack of leadership on site. No real central leader pushing <br />schedules, and contractors in getting their jobs done. <br />o DPF stated when the first phase was not getting done on time, a meeting was held with <br />Bond executives back in October. <br />o DiNisco feels this is not a crisis, but critical and needs to be fixed. <br />o DPF informed the committee that they will be notifying Bond for a January 12th, 2017 <br />meeting request at 5:OOpm with the Senior Vice President of Bond, to discuss the project <br />teams concerns. <br />PBC Meeting 12.22.16 2 <br />