Laserfiche WebLink
11 June 2008 <br />Meeting Minutes <br />Lexington Permanent Building Committee (LPBC) <br />Location: Cary Memorial Hall-Stone Conference Room <br />10 June 2008 <br />Date & Time: , 7:00PM <br />2.18 PCO 24 HKT <br />6-10-08 <br />PCO # 24 as previously submitted by CTA at an value of $17,452.11 for changes to the window <br />muntins. HKT is still reviewing these costs, as is CTA. There are reports that the cost proposal has <br />been reduced some 30%. <br />DPF stated that the changes warranted were not in their opinion something that could have been <br />determined in the bid process, that the plans and specs were based upon manufacturers <br />information that proved to be inaccurate, therefore requiring a change. It was discussed that some <br />cost may well be due to the subcontractor to accommodate the changes. DPF requested that HKT <br />pursue a timely resolution and determination of what the fair and reasonable cost to the <br />subcontractor should be so that the matter can be approved and the windows ordered before they <br />become an item that gives cause to delay. <br />2.19 Contract Change Orders Closed <br />6-10-08 <br />Contract Change Order # 4,containing previously approved PCOÔs # 4, 5, 6, and 7, with a credit <br />value to the Town of $72.30 was presented to the PBC for final signature and Approval. <br />Contract Change Order # 5,containing previously approved PCOÔs # 15, 17, 18, 19, 20, and 22. <br />with a cost of $96,314.13. was presented to the PBC for final signature and Approval. <br />It was discussed the several items within Change Order no.. 5 have a time, materials or other <br />variable element to them that may result in an additional pco to be issued to make any accounting <br />changes for the final costs based upon agreed unit costs in the original pcoÔs. If this is to happen it <br />will be performed under a separate pco and the value of this Contract Change Order will not change. <br />Motion: To approve Contract Change Order #4 and #5 in the amounts of $72.30 Credit and <br />$96,314.13 Add, respectively. <br />Motion: Dick Perry 2nd: Bill Bruckman Vote: Unanimous <br />2.20 Exterior Finishes HKT <br />6-10-08 <br />The mock up panel reflecting the exterior cladding and veneers was discussed. Some PBC members <br />visited the site to see the color options on the corrugated panel. The Architect expressed a desire to <br />use the Dove Grey color for the corrugated panel stating that it was in keeping with the monolithic <br />and utilitarian theme of the project from its development. Some PBC members expressed a <br />preference to the Antique bronze color, but deferred to the color choice presented by HKT. PBC <br />agreed the corrugated panel would be Dove Grey. <br />Discussion on the color choice for staining of the salt / Sand Shed, PBC asked for 4 color samples of <br />the proposed stain, Cottonwood, Belvedere Tan, Driftwood and Wood Smoke Grey. <br />7 <br /> <br />