Laserfiche WebLink
Lexington Permanent Building Committee <br />7.80 Transfer <br />2/14/13 <br />Motion to approve $1,447,323 in funds from contingency line to Construction line based upon approval of Estabrook GMP. <br />Motion: Eric 2nd: Carl Vote: 5-0-0 <br />5/9/13 <br /> upgrade and <br />extension (service) cost, and authorization of $79,508 to National Grid for gas line service upgrade from Grove Street to new <br />building. <br />Motion Phil 2 Chuck Vote 6-0-0 <br />nd <br />9/12/13 <br />Motion to transfer $143,393.00 from Owners Contingency to Constr <br />and the pre construction services. <br />Motion Dick 2 Chuck Vote 7-0-0 <br />nd <br />7.84 Project Update <br />8/8/13 <br />CP made presentation on project status <br />Stairs being enclosed, windows being installed, curtain walls <br />hoisted, concrete pans being poured in stairs, water testing on windows complete, binder course next week. <br />PBC asks is their a contingency plan if Shawmut fails? <br />9/12/13 <br />CP made a presentation on project status: <br />Schedule shows 9 days lag. Discussion on levels of manpower on site and expectations for timely completion. Shawmut <br />representatives confident they will make schedule, further they claim subs are underbiling which would explain lower monthly <br />requisitions. <br />Shawmut reports 105 men on site this week with 30 carpenters. <br />SC is to be 1/27/14 with students starting on 2/24/14 <br />10/10/13 <br />CP made a power point presentation on overall project status, inlucing submittal logs, pco logs, budget and schedule. <br />7.85 Interior Colors <br />4/11/13 <br />Ken DiNisco stated that a final discussion should take place soon on interior colors. <br />Ken will work directly with Carl and Eric to schedule a time too meet and review same, perhaps as early as next week. Ken will be <br />sure to include Sandy T. in those discussions. <br />5/9/13 <br />Carl attended meetings with the Architects and school Principals to review interior colors. <br />7.87 Application for Payment <br />8/8/13 <br />Motion to approve Application for Payment #13, in the amount of $2,815,589.25 from Shawmut Construction as approved and <br />recommended by the Architect of Record, DiNisco Design Partnership and Owners Project Manager Collaborative Partners. <br />Motion: Jon 2: Carl Vote: 6-0-0- <br />nd <br />9/12/13 <br />Motion to approve Application for Payment #14, in the amount of $2,230,402.52 from Shawmut Construction as approved and <br />recommended by the Architect of Record, DiNisco Design Partnership and Owners Project Manager Collaborative Partners. <br />Motion: Eric 2: Dick Vote: 7-0-0 <br />nd <br />10/10/13 <br />Motion to approve Application for Payment # 15, in the amount of $2,837,461.00 from Shawmut Construction as approved and <br />recommended by the Architect of Record, DiNisco Design Partnership and Owners Project Manager Collaborative Partners. OPM <br />to secure lien waivers from Shawmut on this and all future requisitions. <br />Motion: Jon 2: Phil Vote: 6-0-0 <br />nd <br /> Page 5 of 7 <br /> <br />